United States v. Wunderlich
This text of 120 Ct. Cl. 822 (United States v. Wunderlich) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
On writ of certiorari (341 U. S. 924) to review a judgment of the Court of Claims holding that in a contract with the Government for the construction of the Vallecito Dam in southern Colorado, where claims made by the contractor were denied by the contracting officer, whose decisions were affirmed on appeal, and the claims in suit were excepted from the final settlement, the departmental action was not final and binding upon the plaintiff, under the terms of the contract, and plaintiff was entitled to recover.
[823]*823The judgment of the Court of Claims was reversed by the Supreme Court November 26, 1951, in an opinion holding that in the absence of a finding of fraud a determination by the department head under the “finality clause” of a Government contract is conclusive.
delivered the opinion of the Supreme Court, as follows:
This Court is again called upon to determine the meaning of the “finality clause” of a standard form government contract. Respondents agreed to build a dam for the United States under a contract containing the usual “Article 15.”
The same Article 15 of a government contract was before this Court recently, and we held, after a review of the authorities, that such Article was valid. Moorman v. United States, 338 U. S. 457. Nor was the Moorman case one of first impression. . Contracts, both governmental and private, have been before this Court in several cases in which provisions equivalent to Article 15 have been- approved and enforced “in the absence of fraud or such gross mistake as would necessarily imply bad faith, or a failure to exercise an honest judgment * * *.” Kihlberg v. United States, 97 U. S. 398, 402; Sweeney v. United States, 109 U. S. 618, 620; [824]*824Martinsburg & P. R. Co. v. March, 114 U. S. 549, 553; Chicago, S. F. & C. R. Co. v. Price, 138 U. S. 185, 195.
In Ripley v. United States, 223 U. S. 695, 704, gross mistake implying bad faith is equated to “fraud.” Despite the' fact that other words such as “negligence,” “incompetence,” “capriciousness,” and “arbitrary” have been used in the course of the opinions, this Court has consistently upheld the finality of the department head’s decision. unless it was founded on fraud, alleged and proved. So fraud is in essence the exception. By fraud we mean conscious wrongdoing, an intention to cheat or be dishonest. The decision of the department head, absent fraudulent conduct, must stand under the plain meaning of the contract.
If the conclusiveness of the findings under Article 15 is to be set aside for fraud, fraud should be alleged and proved, as it is never presumed. United States v. Colorado Anthracite Co., 225 U. S. 219, 226. In the case at bar, there was no allegation of fraud. There was no finding of fraud nor request for such a finding. • The finding of the Court of Claims was that the decision of the department head was “arbitrary,” “capricious,” and “grossly, erroneous.” But these words are not the equivalent of fraud, the exception which this Court has heretofore laid down and to which it now adheres without qualification.
Respondents were not compelled or coerced into making the contract. It was a voluntary undertaking on their part. As competent parties they have contracted for the settlement of disputes in an arbitral manner. This, we have said in Moorman, Congress has left them free to do. Moorman v. United States, supra, at 462. The limitation upon this arbitral process is fraud, placed there by this Court. If the standard of fraud that we adhere to is too limited, that is a matter for Congress.
Since there was no pleading of fraud, and no finding of fraud, and no request for such a finding, we are not disposed to remand the case for any further findings, as respondents urge. We assume that if the evidence had been sufficient to constitute' fraud, the Court of Claims would have so found. In the absence of such finding, the decision of the department head must stand as conclusive, and the judgment is reversed.
“Article 15. Disputes. — Except as otherwise specifically provided In this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed; with the work as directed,”
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
120 Ct. Cl. 822, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-wunderlich-cc-1951.