Albina Marine Iron Works, Inc. v. United States

79 Ct. Cl. 714, 1934 U.S. Ct. Cl. LEXIS 281, 1934 WL 2093
United States Court of Claims·Decided June 4, 1934·No. No. 42060·Published·Cited by 14 cases

Opinion

Whalet, Judge,

delivered the opinion of the court:

The plaintiff entered into a contract with the Department of Commerce to construct three lightships at a stated price. The ships were to be completed within a specified number of days from the date of the receipt of the notice to proceed with the construction. The contract contained a liquidated damage clause whereby the contractor was to pay $40 for each calendar day’s delay on each lightship. The three ships were completed and accepted but the limitation for completion on each vessel was far exceeded.

The question in this case is the number of days for which the contractor is chargeable with liquidated damages for the [719] delays occasioned in the completion of each ship. This involves the construction of the clause in article 9 of the contract which reads:

“ * * * Provided, That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control cund without the fault or negligence of the contractor, including, but not restricted to, * * * unusually severe weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within ten days from the beginning of any such delay notify the contracting-officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within thirty days, by the contractor to the head of the department concerned, whose decision on such appeal as to the facts of delay shall be final and conclusive on the parties hereto.” [Italics ours.]

The plaintiff is suing to recover on two items which involve, first, “ unforeseeable causes ”, and second, specifically “ umMSually severe weather.”

It appears that during the construction o.f the vessels certain garboard strake plates were fabricated by the subcontractor and when delivered at the site of the work, although apparently in good condition and having been inspected before shipment, were found not to measure up to the contract requirements and were rejected. It was necessary to have new plates fabricated and shipped. This necessitated a delay of 11 days on each ship. The contractor applied for remission of damages on the ground that the delay occasioned by the furnishing of new plates was due to unforeseeable causes beyond the control and without fault or negligence on the part of the contractor. The contracting officer, upon the reports and recommendation of his subordinates, found as a fact that the causes of the delays were not due to the fault or negligence of the contractor and were unforeseeable and remitted liquidated damages on each vessel for the number of days required for the supplying of the new plates. When the contractor applied for final settlement, the Comptroller General refused to acquiesce [720] in the finding of fact of the officer in the remission of liquidated damages and assessed against the contractor the per diem sum of $40 for each vessel in the amount of $9,240. '' The Comptroller General was not. a party to the contract. It was the duty of the contracting officer, under the terms of the clause of the contract above set out, to ascertain the facts and the extent of the delay. The contract stated that his findings of fact should be final and conclusive on the parties. The contracting officer did perform his duties under the terms of this clause of, the contract and found that the contractor was not to be, charged with the 77 days’ delay due to the furnishing of the new plates, and this finding by the contracting officer is not reviewable by the Comptroller General or the courts. What is an unforeseeable cause of delay is a question of fact and when the contracting officer made his decision that these causes were unforeseeable, that the contractor was not negligent and was without fault in respect to- them, it was a final disposition of the matter. Neither fraud nor bad faith is alleged or proven. The court cannot go behind the decision of the contracting officer where the contract makes him the final arbiter of the facts of the case unless there has been fraud or such gross error which, in effect, would imply bad faith. The cases in this court and the Supreme Court so holding are numerous. Kihlberg v. United States, 97 U.S. 398; United States v. Gleason, 175 U.S. 588; Penn Bridge Co. v. United States, 59 C.Cls. 892. See also Carroll v. United States 76 C.Cls. 103, where all the cases are fully reviewed. The action of the Comptroller General in denying plaintiff the relief granted by the contracting officer was without warrant of law. See Sun Shipbuilding and Dry Dock Company v. The United States, 76 C.Cls. 154, 193.

The defendant does not attempt to- impeach the good faith of the contracting officer in the decision made by him, but insists that his decision was based on the investigation of his subordinates who committed gross error in reporting and recommending to him that the failure of the garboard strake plates furnished by the subcontractor to meet the specifications of the contract was due to causes unforeseen and with[721] out negligence on tbe part of the contractor or subcontractor. The clause in the contract applies equally to the subcontractor as well as to the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Albina Marine Iron Works, Inc. v. United States, 79 Ct. Cl. 714, 1934 U.S. Ct. Cl. LEXIS 281, 1934 WL 2093 (cc 1934).

79 Ct. Cl. 714 (Albina Marine Iron Works, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Southwestern Engineering Co.
196 Ct. Cl. 782 (Court of Claims, 1971)
C. J. Langenfelder & Son, Inc. v. The United States
341 F.2d 600 (Court of Claims, 1965)
C. J. Langenfelder & Son, Inc. v. United States
341 F.2d 600 (Court of Claims, 1965)
Wunderlich v. United States
117 Ct. Cl. 92 (Court of Claims, 1950)
Pfotzer v. United States
77 F. Supp. 390 (Court of Claims, 1948)
S. J. Groves & Sons Co. v. Warren
135 F.2d 264 (D.C. Circuit, 1943)
Caribbean Engineering Co. v. United States
97 Ct. Cl. 195 (Court of Claims, 1942)
Brooks-Callaway Co. v. United States
97 Ct. Cl. 689 (Court of Claims, 1942)
General Steel Products Corp. v. United States
36 F. Supp. 498 (E.D. New York, 1941)
W. E. Callahan Construction Co. v. United States
91 Ct. Cl. 538 (Court of Claims, 1940)
McShain Co. v. United States
83 Ct. Cl. 405 (Court of Claims, 1936)