Merrick Construction, LLC

CourtArmed Services Board of Contract Appeals
DecidedMarch 22, 2018
DocketASBCA No. 60906
StatusPublished

This text of Merrick Construction, LLC (Merrick Construction, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merrick Construction, LLC, (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Merrick Construction, LLC ) ASBCA No. 60906 ) Under Contract No. W912P8-08-D-0038 )

APPEARANCE FOR THE APPELLANT: Michael S. Blackwell, Esq. Shields Mott L.L.P. New Orleans, LA

APPEARANCES FOR THE GOVERNMENT: Thomas J. Warren, Esq. Acting Engineer Chief Trial Attorney William G. Meiners, Esq. Engineer Trial Attorney U.S. Army Engineer District, New Orleans

OPINION BY ADMINISTRATIVE JUDGE D' ALESSANDRIS ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

Appellant, Merrick Construction, LLC. (Merrick), appeals from a contracting officer's final decision denying its claim in the amount of $203,015.82 for rental costs for a bypass pumping system installed pursuant to a government change order. Respondent, the United States Army Corps of Engineers (government or Corps) moves for summary judgment, asserting that Merrick's claim is precluded by the general release signed by Merrick's vice president. The Corps additionally argues that there is an accord and satisfaction based upon a modification to the contract and that Merrick's claim is precluded because it was filed after final payment on the contract. For the reasons set forth below, we grant the Corps' motion for summary judgment.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

On 8 April 2008, the Corps awarded Multiple Award Task Order Contract (MATOC) No. W912P8-08-D-0038 for construction services to Merrick (R4, tab 17). No construction services were actually procured at the time of award, but, as one of multiple awardees of the MATOC, Merrick was eligible to submit offers in response to subsequent task order solicitations issued under the contract. On 10 April 2009, the Corps awarded MATOC Task Order 0002, to Merrick (R4, tab 16). The task order involved construction work on a hurricane protection levee near New Orleans, Louisiana (id.). The contract contains the Federal Acquisition Regulation (FAR) 52.243-4(f), CHANGES (JUN 2007) clause, providing that "[n]o proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract" (R4, tab 17 at 104-05).

On 25 March 2011 the Corps issued a unilateral change order, designated as C0-013 (Modification No. lZ), for the installation of a 300 cubic feet per second bypass pumping system at the construction site. The change order required the installation, operation and monitoring of a temporary "bypass pumping system." The change order provided that the "Bypass Pumping System Rental" would be paid for on a "unit price per month" and, that the contract price was presently unchanged, but that a formal modification would later be issued with an agreed-to price. (R4, tab 8 at 1, 5, 9)

The pumping equipment was delivered to the job site on 6 July 2011, and was operational by 18 July 2011 (R4, tabs 9-10). Following testing of the flow rate, the pumps were provisionally accepted on 10 August 2011, and fully accepted on 11 August 2011 (R4, tab 12).

On 19 July 2011, the Corps issued Modification No. 03, partially settling the change order for the bypass pumping system. Modification No. 03 included contract line item numbers (CLINs) for Mobilization and First Month's Rent (CLIN 0045), two months rental of the pumping system (CLIN 0046), and provided that the monthly rental for the bypass pumping system, would be $208,015.82 (R4, tab 13). On 30 March 2012, Modification No. 10 (also known as VEQ-004) added seven months rental of the bypass pumping system (gov't mot., ex. A). The rental of the bypass pumping system ended on 11 September 2012, when Merrick was directed by the Corps to shut down the bypass pumping system (R4, tab 3 at 5).

On 3 January 2013, the Corps issued Modification No. 18 (VEQ 005). It was signed on behalf of Merrick by Mr. Lemoine, and by Cynthia A. Nicholas, the government contracting officer. Modification No. 18 added an additional three months rental to the bypass pumping system. (R4, tab 14) Modification No. 18 included the following settlement language:

This adjustment constitutes compensation in full on behalf of the contractor and its subcontractors and suppliers for all costs and markups directly or indirectly attributable to Variations in Estimated Quantities, and for all delays, impacts and extended overhead relative thereto and for performance of the change within the time frame stated.

(Id. at 2)

At some point after the bypass pumping system was removed, Max Merrick, the owner of Merrick, became aware of an "accounting discrepancy" regarding the

2 monthly rental charges from its subcontractor, Associated Pump & Supply Co., L.L.C. (APS) and the amounts Merrick received from the Corps (app. opp'n, ex. G). Mr. Merrick attributed the discrepancy to an overpayment by Merrick to APS. Mr. Merrick contends that the Corps agreed that the accounting discrepancy was due to APS overbilling Merrick. On 22 April 2014, Merrick filed suit against APS for return of the amount Merrick believed had been overbilled. (Id.)

On 23 January 2015, Mr. Lemoine, the project manager, ended his employment with Merrick, and Mr. Clay Juneau, Merrick's vice president, began overseeing completion of the project, although he had not been involved in negotiating the modifications of the contract with the Corps (app. opp'n, ex. G at 3). On 6 July 2015, Merrick submitted its final payment request in the amount of $39,496.51 (gov't mot., ex. C). On 10 July 2015, Merrick's vice president, Mr. Juneau, signed a general release document, which read as follows:

The undersigned contractor under Contract W912P8-08-D-0038-0002 dated 4/10/2009 between the United States and the said contractor, for WBV-15b.2 Lake Cataouatche PS Fronting Protection, PS fronting protection, modification, floodwall tie-ins to the 100 year protection level., in accordance with Contract Clause, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, paragraph, hereby releases the United States, its officers, agents, and employees from any and all claims arising under or by virtue of said contract or any modification or change thereof, except with respect to those claims, if any, listed below ....

The release document did not list any exceptions or reservations below the quoted language. (R4, tab 15) The Corps made final payment under the task order on 17 July 2015, in the amount of$39,496.51 (gov't mot., ex. F).

On 24 September 2015, during negotiations with APS, Mr. Merrick concluded that the accounting discrepancy was due to an underpayment by the Corps, rather than overbilling by APS (app. opp'n, ex. G). On 4 May 2016, Merrick filed a claim for an additional month's rent of the bypass pumping system under CLIN 0046, at the contract unit price of $208,015.82 (R4, tab 3). In a final decision dated 31 August 2016, contracting officer Michelle R. Dalmado denied Merrick's claim in its entirety based upon a finding that Merrick had released any potential claims regarding the bypass pumping system through the release in Modification No. 18, as well as the general release at final payment (R4, tab 2). Merrick subsequently timely appealed to this Board.

3 DECISION

We will grant summary judgment if there is no genuine issue as to any material fact, and the moving party is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 4 77 U.S. 317, 322 ( 1986). A material fact is one that may affect the outcome of the decision. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)
Shepherd v. United States
113 F. Supp. 648 (Court of Claims, 1953)
J. G. Watts Construction Co. v. United States
161 Ct. Cl. 801 (Court of Claims, 1963)
Jo-Bar Manufacturing Corp. v. United States
535 F.2d 62 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
Merrick Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merrick-construction-llc-asbca-2018.