Jabez-Absher Small Business Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedOctober 2, 2025
Docket63898
StatusPublished

This text of Jabez-Absher Small Business Joint Venture (Jabez-Absher Small Business Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jabez-Absher Small Business Joint Venture, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Jabez-Absher Small Business Joint ) ASBCA No. 63898 Venture ) ) Under Contract No. W912DW-22-C-0011 )

APPEARANCES FOR THE APPELLANT: Mr. Stephen Montalvo Project Executive Kainui M. Smith, Esq. Counsel

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Benjamin T. Townsend, Esq. Anna Astrakhan, Esq. Eric M. Smith, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Seattle

OPINION BY ADMINISTRATIVE JUDGE TAYLOR PURSUANT TO BOARD RULE 11

Jabez-Absher Small Business Joint Venture (Jabez-Absher or appellant) seeks an increase in the contract price of $100,865.76 resulting from its decision to change the production facility for certain electrical equipment. Jabez-Absher contends it was required to change the production facility since the lead time for the equipment from the original production facility had increased from 50 to 80 weeks negatively impacting the construction schedule. Jabez-Absher further contends that it provided the U.S. Army Corps of Engineers (USACE or government) with notice of this change and the government acknowledged the change.

Jurisdiction is proper pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101–7109. The parties have elected for the Board to decide this appeal pursuant to the Board’s Rule 11 procedures. Board Rule 11 permits the parties to waive a hearing and submit the matter for decision on the written record. Pursuant to Rule 11, the Board decides the weight to be given the evidence and may make findings of fact on disputed facts. Board Rule 11(d). For the reasons stated below, the appeal is denied. FINDINGS OF FACT

I. The Contract

On August 23, 2022, the USACE awarded Jabez-Absher a firm-fixed price contract in the amount of $29,004,500 to repair a military barracks on Joint Base Lewis-McChord (R4, tab 3). The contract had a completion date of 720 calendar days from the date of the notice to proceed (id. at 33). 1 The government issued the notice to proceed on September 7, 2022, with an effective date of October 3, 2022, establishing a contract completion date of September 22, 2024 (R4, tab 9). The contract stated the contractor shall supply all supervision, labor, equipment and materials necessary to perform the required work (R4, tab 3 at 33).

The contract also specifically notified Jabez-Absher that only a warranted contracting officer had the authority to change the contract’s terms and conditions, and the contractor should not proceed with any attempted changes made by someone other than a warranted contracting officer without first notifying the contracting officer (R4, tab 3 at 37). Proceeding with such unauthorized work would be at the contractor’s own risk (id.).

The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.243-4, CHANGES (JUN 2007) which provides, in relevant part:

(b) Any other written or oral order . . . from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating (1) the date, circumstances, and source of the order and (2) that the Contractor regards the order as a change order.

(c) Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.

(Id. at 45) (emphasis added)

1 The government’s Rule 4 file is Bates numbered with a five-digit number. We omit the leading zeros in our citations to the government’s Rule 4 file.

2 II. The Electrical Subcontract

Jabez-Absher issued a subcontract to Danard Electric, Inc. (Danard) to perform the electrical work on the contract (Appellant’s Statement of Facts (ASOF) ¶ 3). 2 Danard contracted with the Eaton Corporation (Eaton) to manufacture the electrical components for the contract including the electrical switchgear equipment (ASOF ¶ 4). The electrical switchgear included a main switchboard (MSB) and several distribution panels, including distribution panel-C (DP-C) (R4, tab 22 at 2322-24). In a proposal dated July 13, 2022, Eaton stated that shipment of the switchgear would take up to 50 weeks (id.). The government approved the proposed Eaton switchboards for use in the switchgear on the project on February 3, 2023 (R4, tab 14). With the estimated 50 week lead time, Eaton would have delivered the switchgear including the approved switchboard to the project no later than January 19, 2024, allowing for timely project completion (ASOF ¶ 7).

On or about January 27, 2023, Danard informed Jabez-Absher that the lead time for producing the switchboard by Eaton had increased to approximately 80 weeks which could negatively impact the construction schedule (R4, tab 25 at 2340). Danard further informed Jabez-Absher that Eaton had the ability to build the switchboard at their specialty plant in Auburn, Washington with a current lead time at that plant of 40 weeks (id.). On February 16, 2023, Danard issued a change order request to Jabez-Absher in the amount of $88,660 for a “Switchboard assembly line change” (ASOF ¶ 8). The change order request provided the following in relevant part:

The lead time for the switchboard is currently at 80 weeks from approved submittals which may be too long for the construction schedule. Approved submittals have been received and the switchboards are currently released. Eaton has the ability to build the switchboard at their specialty plant in Auburn Washington and the current lead time at that plant is 40 weeks from receipt of contract modification. This change order is to change manufacturing plants only. This is not an expediting option.

(Id.)

2 In its Rule 11 brief, appellant included a statement of facts (app. br. at 3-8). The government did not dispute many of these facts (gov’t reply br. at 1-11). The finding of facts citing to appellant’s ASOF are undisputed or uncontroverted by the government. 3 On March 2, 2023, Jabez-Absher directed Danard to shift production of the “two switchgears” to the Auburn, Washington assembly line (R4, tab 72). 3

III. Project Coordination Meetings and Updates

Jabez-Absher and the USACE held weekly project coordination meetings. Following the government’s approval of the switchboards, Jabez-Absher informed the USACE at the February 9, 2023, project coordination meeting that its supplier had indicated the lead times for the switchgear were “extraordinary long” (R4, tab 15 at 2284). The February 16, 2023, project coordination meeting minutes reflect that Jabez-Absher had placed an order for the switchgear with the supplier with a lead time of 85 weeks (R4, tab 16 at 2290). The meeting minutes also indicate “Other Suppliers – No Better Lead Times”, “Temp Solutions – None available”, “Other Factories – Increased Cost, No GUARENTEE” (id.). The minutes further listed potential impacts from the long switchgear lead time as: “8-10 Month Delay”, “Project shutdown JAN 2024 until Switch Gear Arrive”, “est BOD: MAR 2025”, “est. CCD: JUL 2025”, “$1 MIL to $1.5 MIL Cost” (id. at 2290-91). The February 23, 2023, meeting minutes reflect the same information as the previous week’s minutes with respect to the switchgear except the cost of the switchgear delay is shown as “$0.5 MIL to $1.5 MIL Cost (Depending on Gov’t Direction)” (R4, tab 17 at 2299). Likewise, the March 2, 2023, meeting minutes reflect the same information for the switchgear and do not mention Jabez-Absher’s direction to Danard to change the production facility (R4, tab 18 at 2307).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)
Agility Public Warehousing Co. KSCP v. Mattis
852 F.3d 1370 (Federal Circuit, 2017)
Redland Co. v. United States
97 Fed. Cl. 736 (Federal Claims, 2011)
Cleveland Chair Co. v. United States
557 F.2d 244 (Court of Claims, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
Jabez-Absher Small Business Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jabez-absher-small-business-joint-venture-asbca-2025.