Tangfeldt Wood Products, Inc. v. The United States

733 F.2d 1574, 32 Cont. Cas. Fed. 72,459, 1984 U.S. App. LEXIS 15013
CourtCourt of Appeals for the Federal Circuit
DecidedMay 9, 1984
DocketAppeal 83-1373
StatusPublished
Cited by9 cases

This text of 733 F.2d 1574 (Tangfeldt Wood Products, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tangfeldt Wood Products, Inc. v. The United States, 733 F.2d 1574, 32 Cont. Cas. Fed. 72,459, 1984 U.S. App. LEXIS 15013 (Fed. Cir. 1984).

Opinion

DAVIS, Circuit Judge.

The Department of Agriculture Board of Contract Appeals (BCA or Board) denied recovery to a contractor (under a timber sale contract) for the cost of cutting and preparing for removal timber which remained on the sale area after the contract was terminated by the Government under a special provision dealing with catastrophies. In the circumstances of this ease, we affirm.

I

In October 1979 appellant Tangfeldt Wood Products, Inc. (Tangfeldt) was awarded by the Forest Service of the Department of Agriculture the Worm Salvage timber sale contract for the removal and purchase of several types of timber from a government forest in Oregon. The original termination date of the contract was March 31, 1981; this was later extended until March 31, 1982 (and again to April 30, 1982). The normal operating season was June 1st to November 30th of each year.

*1575 Tangfeldt commenced operations in March 1981 and continued through July 1981; removal of cut timber stopped in June 1981, and apparently was never resumed. By October 1981, appellant had failed to pay the required deposit (due in September 1981) for extension of the termination date, and by letter of October 5th Agriculture gave it 30 days to pay that sum. Shortly thereafter (October 16, 1981), the Forest Service informed Tangfeldt in writing of the importance of removing during the 1981 operating season timber which had been previously cut but not removed.

On November 13 and 14, 1981, a wind storm blew down a considerable amount of timber within the Worm Salvage timber sale area. Before that blow-down Tangfeldt had felled, bucked, yarded and decked some 500 Thousand Board Feet (MBF) of timber at a cost of $30.50 per MBF. 1 This timber was not removed but remained on the site.

There followed a series of suggestions and counter-suggestions, apparently rooted in the damage caused by the blow-down. A Forest Service letter of December 8, 1981, told Tangfeldt that unless it paid the unpaid deposit (mentioned above) by December 30th, the sale would be cancelled for breach. This date was extended to February 2, 1982, if appellant agreed to a contract modification proposed by the Government. That modification provided for the deletion from the sale of all timber except for that in the area of the decked logs, and also called for payment of the deposit. On February 2nd appellant stated that it would not accept the proposed modification.

A week later (February 9, 1982), Tangfeldt asked for a two-year extension of the contract. On April 1st, the Forest Service approved a two-year extension to March 31, 1984, contingent on appellant’s execution of a proposed contract modification. Appellant never executed the modification. Meanwhile the contract term was extended to April 30, 1982.

On April 9th, Tangfeldt requested termination of the sale for catastrophe (due to the blow-down) under clauses B2.133 and B8.221 of the contract. Clause B2.133 defines “Catastrophic Damage” and clause B8.221 authorizes unilateral termination for catastrophe by the contractor if certain conditions are met. By letter of April 16th, the Forest Service determined that the blow-down qualified as catastrophic damage, 2 but also that the conditions of B8.221 were not met. However, the damage qualified for Government termination under B8.222 (another clause dealing with catastrophies) if the contractor did not agree to a catastrophic modification under B8.33 (still another catastrophe clause). Appellant did not desire such a modification and waived its 30-day contractual period for considering such a modification.

Accordingly, on April 21, 1982, the Agriculture Department terminated the Worm Salvage timber sale for catastrophe damage under clause B8.222, supra. Thereafter, the Forest Service resold the Worm Salvage contract timber, including the 500 MBF of merchantable timber previously felled, bucked, yarded and decked by Tangfeldt and left by it on the site after the termination. The resale was awarded to another bidder but Tangfeldt was the runner-up.

This case arose because appellant filed a claim (on May 7, 1982) with the contracting officer seeking $15,250 for the work it performed on the 500 MBF of timber remaining in the area. The contracting officer denied the claim and the Board rejected Tangfeldt’s appeal to that tribunal. The contractor now appeals here under the Contract Disputes Act, as amended by the Federal Courts Improvement Act.

II

Tangfeldt does not contend that the Government was unauthorized to terminate *1576 the sale for catastrophe as it did, nor is there any claim that the specific terms of the special catastrophe clause so empowering the Forest Service (B8.222) required payment of the sum now demanded. 3 The sole argument is that the contractor is entitled to restitution for benefits it conferred on the Government. The BCA found that appellant — by its felling, bucking, decking, and yarding of the 500 MBF — had enhanced the value of that timber beyond the value the timber would have had in its natural condition as standing timber; the Board also seemed to imply that, because of that enhanced value, the Forest Service may well have received a better bid on the resale of that timber. 4 Though the appellee challenges that finding, we accept it as adequately supported. The question then is whether that is a benefit for which the United States owes restitution.

Appellant's principal argument is that the catastrophe termination was effectively a termination for impracticability of performance (because of the blow-down) and under a well-settled common law rule the contractor is entitled to restitution for benefits it conferred on the Government by way of past performance prior to such termination. We are asked to apply the principle of such decisions as Clark v. United States, 95 U.S. 539, 24 L.Ed. 518 (1877) (quantum meruit for recovery for past performance of invalid oral sea carriage contract frustrated by a wreck of the ship); Crocker v. United States, 240 U.S. 74, 36 S.Ct. 245, 60 L.Ed. 533 (1916) (quantum valebant recovery for past performance of contract invalid for contractor’s fraud and rescinded by the Government); Yosemite Park and Curry Company v. United States, 582 F.2d 552, 560-61 (Ct.Cl.1978) (quantum meruit recovery for services actually rendered under a contract invalid for violation of statutes and regulations); New York Mail and Newspaper Transportation Co. v. United States, 154 F.Supp. 271, 139 Ct.Cl. 751 (1957), cert. denied, 355 U.S. 904, 78 S.Ct. 332, 2 L.Ed.2d 260 (1957) (damages allowed to put contractor in same position as it would have occupied without the invalid contract).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
733 F.2d 1574, 32 Cont. Cas. Fed. 72,459, 1984 U.S. App. LEXIS 15013, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tangfeldt-wood-products-inc-v-the-united-states-cafc-1984.