Sea Crest Construction Corp. v. United States

59 Fed. Cl. 615, 2004 U.S. Claims LEXIS 1, 2004 WL 51835
CourtUnited States Court of Federal Claims
DecidedJanuary 8, 2004
DocketNo. 02-261C
StatusPublished
Cited by1 cases

This text of 59 Fed. Cl. 615 (Sea Crest Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sea Crest Construction Corp. v. United States, 59 Fed. Cl. 615, 2004 U.S. Claims LEXIS 1, 2004 WL 51835 (uscfc 2004).

Opinion

OPINION AND ORDER

HODGES, Judge.

Sea Crest alleges that the Government breached plaintiffs contract by delaying approval of a final site plan for design and construction of family housing units at the United States Military Academy. Defendant filed a motion for summary judgment on liability, and plaintiff filed a Rule 56(f) affidavit requesting additional discovery. Defendant’s motion for summary judgment is granted in part. Plaintiffs Rule 56(f) request is moot.

BACKGROUND

A. Request for Proposal

The Army Corps of Engineers issued a Request for Proposal and Specifications in February 1995, for design and construction of housing units at West Point. The contractor was to build 118 units in Phase One and design forty-two optional units. It would demolish existing housing units on the site in Phase Two. The contract required completion of site design prior to construction. If defendant exercised the option for forty-two additional units, the contractor would construct these units in Phase Three. A design that would accommodate 160 units was due within 135 days after the Notice to Proceed. All work was to be completed within 1000 days.

The RFP required that the site plan respect the architectural character of the area and be compatible with the environment. It directed the contractor to employ a design [616]*616that would discourage through traffic near the housing units. The Corps suggested homes clustered around cul-de-sacs or courts, avoiding excessively long or short loop streets. A site sketch attached to the RFP included the following caption: “A Main Circulatory Spine Acting as the Main Connector; Whereby the Buildings are in Cluster Arrangements Around Parking Courts.”

B. Sea Crest’s Bid

Sea Crest submitted its first proposal May 25, 1995. Defendant responded on June 9, listing “numerous areas where your design either fails to address the requirements or provides data which indicates non-compliance.” The letter required revisions to the proposal and a response no later than June 28, 1995. Plaintiff responded with two letters in July, adding “an allowance for 10,000 cubic yards of rock excavation for site trenching, building foundations, and general site cuts.” The parties met to discuss the proposed site plan. A July 26 letter from defendant directed plaintiff to correct the deficiencies, remove the allowance for rock excavation, and submit a Best and Final Offer no later than July 27,1995.

Plaintiff submitted a site plan with the July 27 Best and Final Offer showing 160 housing units in a six-pod layout with cul-de-sacs.1 Plaintiffs BAFO included the assertion that “some revisions to the site plan will be necessary.” Such revisions were to be made “in conjunction with the approval of the Army Corps of Engineers.” Sea Crest bid $21,085,000 for design and construction of 118 units, $900,000 for demolition of the existing units, and $6,916,000 for the forty-two optional units. The Corps accepted plaintiffs BAFO on July 31, 1995 and approved the contract prices. It issued a Notice to Proceed on September 6,1995.

C. Site Plans

Plaintiff presented a site plan known as “Drawing No. 1” to the Government for the first time at a September 18, 1995 pre-work meeting. The new drawing proposed loop streets instead of cul-de-sacs and made other changes in the approved BAFO design. A copy of the BAFO transmittal letter stating that “some revisions to the site plan will be necessary” accompanied the Drawing. Drawing No. 1 “differed significantly” from plaintiffs BAFO according to defendant’s Area Engineer, Mr. Passantino. It “depicted a big loop or ring around the mountain, comprised of long, looped streets.” Mr. Pas-santino told plaintiff that it could present the drawing at the second pre-work meeting to be held on October 6,1995.

Sea Crest displayed the new design at the second meeting as a large model that Mr. Passantino stated “was never validated as to any scale accuracy and the houses pasted on it were not at all designed until many months later.” Government representatives were not happy with the proposed revisions. According to Mr. Passantino, Sea Crest agreed to “adhere to the concept of quad layout presented in their BAFO, and the Government agreed to be flexible about site geometries and quad size, and to be open to considering other ways in which Sea Crest might reduce rock cut and fill quantities.” He thought that Sea Crest was satisfied with the Government’s response and had no objection to the quad layout. Plaintiff did not submit the Drawing to the Contracting Officer, who did not attend either pre-work meeting.

Sea Crest submitted a number of site plans between September 1995 and July 1997. The Government rejected the plans for a variety of reasons, including budgetary concerns and the plans’ noncompliance with RFP requirements. During that period, the Corps requested site plans for 160, 137, 131, and 118 housing units. The Corps announced its decision to build the contract minimum of 118 units in July 1997, twenty-two months after issuing the Notice to Proceed. By then, Sea Crest had nearly completed construction of the main road and two pods containing a total of sixty-two housing units. The Corps accepted thirty-two housing units in December 1997, thirty units in July 1998, and fifty-eight units in November 1998.

[617]*617Sea Crest submitted claims totaling $10,621,560 to the Contracting Officer in July 1999. These included claims for delay, breach of contract, breach of warranties of good faith and fair dealing, quantum meruit, unjust enrichment, and bad faith. The claims relate to defendant’s rejection of Drawing No. 1 and its alleged failure to approve a final site plan in a timely manner. The Contracting Officer denied plaintiffs claims in April 2001.

DISCUSSION

Plaintiff argues that the Corps’ rejection of Drawing No. 1 was improper, and that its delay in approving a final site plan caused Sea Crest to incur delay damages. Defendant responds that plaintiff did not submit Drawing No. 1 to the Contracting Officer for approval, and in any event that rejection of an improper site design would not have been wrongful. Plaintiffs own inefficiency caused any delays in approving a site plan according to the Government.

Summary judgment is proper when the record shows no genuine issue of material fact. The moving party is entitled to judgment as a matter of law. RCFC 56(c); Celo-tex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The court will view the evidence in the light most favorable to the party opposing the motion. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) (quoting United States v. Diebold, Inc., 369 U.S. 654, 655, 82 S.Ct. 993, 8 L.Ed.2d 176 (1962)).

A. Drawing No. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sea Crest Construction Corp. v. United States
59 Fed. Cl. 473 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
59 Fed. Cl. 615, 2004 U.S. Claims LEXIS 1, 2004 WL 51835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sea-crest-construction-corp-v-united-states-uscfc-2004.