Morris Mechanical Enterprises, Inc. v. United States

554 F. Supp. 433, 30 Cont. Cas. Fed. 70,529, 1 Cl. Ct. 50, 1982 U.S. Claims LEXIS 2305
CourtUnited States Court of Claims
DecidedNovember 17, 1982
Docket508-80C
StatusPublished
Cited by3 cases

This text of 554 F. Supp. 433 (Morris Mechanical Enterprises, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morris Mechanical Enterprises, Inc. v. United States, 554 F. Supp. 433, 30 Cont. Cas. Fed. 70,529, 1 Cl. Ct. 50, 1982 U.S. Claims LEXIS 2305 (cc 1982).

Opinion

OPINION

Statement of Facts

SPECTOR, Judge:

This is a contract case arising out of a project for the development of a Federal Law Enforcement Training Center on an old military base at Glynco, Georgia. The project was administered by the General Services Administration (GSA). Instead of awarding a single prime contract for construction of the project, with the various aspects of the work then being performed by subcontractors coordinated by and working under that prime contractor, GSA elected to award a multiplicity of prime contracts for the various segments of the work. 1 Still another prime contract was awarded to Lasker-Goldman Corporation to act as construction manager.

Plaintiff is a small mechanical contractor specializing in heating and air conditioning systems, which it has installed in settings ranging from family homes to major military installations. Government contracts account for about 70% of its business and it has successfully performed several of these at prices ranging from $100,000 to about $1 million. On this project, plaintiff was one of that multiplicity of prime contractors. Its sole obligation was to buy and deliver to the project site a 650-ton centrifugal chiller, 2 which was then to be installed by another prime contractor.

Ordinarily the Government or its general prime contractor for the entire project would purchase the chiller directly from one of the major air conditioning manufacturers, which would bid to and contract directly with the Government, or that general prime contractor. In this instance, however, plaintiff was the “beneficiary” of GSA’s small-business set-aside program. It was awarded a prime contract covering just the purchase of the chiller, as a means of satisfying the agency’s small business set-aside requirements. As a result, one of the major manufacturers of air conditioning equipment was destined to become a bidder to, and subcontractor under, a small business entity. 3 This effectively eliminated bids that large chiller manufacturers would ordinarily have submitted directly to defendant.

Defendant issued a pre-invitation notice for purchase of the chiller on November 16, 1977, and plaintiff Morris picked it up in a commercial periodical. The notice indicated an estimated cost of $25,000 to $100,000, well within Mr. Morris’ experience, so he sent for the invitation and contacted three major manufacturers, Carrier, York, and Airtemp. Plaintiff was initially most impressed with the York chiller because it best fit the contract requirements and was in fact the only chiller which would exactly satisfy the length and width requirements. 4 But York refused to set a firm delivery date, an important factor since the proposed contract required delivery within 120 days of receipt of a notice to proceed from defendant. Carrier also refused to set a firm delivery date, and in addition refused to perform certain factory tests required by the proposed contract. In addition, the Carrier chiller was far too large to meet the limited space requirements. 5 That left Air-temp as the only manufacturer willing to *435 schedule a firm delivery date and to perform the necessary factory tests. 6

Defendant issued its Invitation for Bids on December 16, 1977 and plaintiff submitted its responsive bid in the amount of $78,763 on February 23, 1978. Six other bids ranging in amount from $93,970 to $165,800 were received. 7 The 120-day (17 weeks) delivery requirement was extremely tight. Evidence of record shows that it ordinarily takes 16 to 26 weeks to produce and deliver such a piece of equipment. Unknown to plaintiff, defendant’s construction manager, Lasker-Goldman, had in fact informed defendant based on its own investigations of six major manufacturers 8 that the requisite chiller could not be produced and delivered in less than 19 to 20 weeks.

By late February 1978, «plaintiff’s efforts had necessarily focused on Airtemp, a reputable subsidiary of Chrysler Corporation, which had produced chillers for many years. He talked with Charles D. Woodward, a manufacturer’s representative for Airtemp and for other mechanical equipment manufacturers in the Atlanta area. 9 Woodward was authorized to quote on equipment, subject to Airtemp’s acceptance. Since he had no authority to bind Airtemp to a contract, plaintiff asked him to obtain a specific delivery date. In a letter dated March 1, 1978, Woodward replied:

Airtemp has indicated that they can ship this machine by July 10, 1978, based on a tentative order this week. Assuming we can delay the starting date for the Government schedule with submittal and bonding procedures, we should have no problem meeting the 120 day specified schedule.

He further promised that “[i]n the event that production delays occur, and we are unable to obtain an extension of the government schedule,” he would be willing to reimburse plaintiff for half its liquidated damages, up to a total of $2000. This promise reflected Woodward’s confidence, based on assurances from Airtemp, that the chiller would be delivered on time. 10 He testified that in accordance with standard industry practice he considered July 10, 1978 to be a firm delivery date and that he was so assured by Airtemp. Soon after he received Woodward’s letter, plaintiff spoke with Airtemp’s national sales manager and received assurances that the Airtemp chiller would be delivered by July 10,1978. Under these circumstances it was reasonable for plaintiff to assume that the July 10, 1978, delivery date was firm.

On March 3, 1978, plaintiff issued a purchase order for a 650-ton chiller to Airtemp “[sjubject to and in full accordance with the attached job specifications.” The purchase order plainly stated that the “[cjhiller must be shipped on or about July 10, 1978.” In an Airtemp order form dated March 6,1978, Woodward submitted plaintiff’s order to Airtemp. It will be noted that this preceded by almost, a month the award of a contract to plaintiff by defendant. Plaintiff knew it was the low bidder, and wanted to place its order as early as possible in order to insure timely delivery. Also in an effort to save time, on March 6, 1978, plaintiff submitted to GSA certain relevant information about the chiller it would buy. 11

The contract was awarded to plaintiff on March 29, 1978. On April 18, 1978 plaintiff *436 received its notice to proceed which started the running of the 120-day delivery schedule, thereby fixing the delivery date of August 18, 1978.

The issues in this case are governed by Clause 5, “General Provisions,” providing in relevant part as follows:

(a) * * * Whether or not the Contractor’s right to proceed with the work is terminated, he and his sureties

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fortec Constructors v. United States
32 Cont. Cas. Fed. 73,702 (Court of Claims, 1985)
Morris Mechanical Enterprises, Inc. v. United States
30 Cont. Cas. Fed. 70,861 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
554 F. Supp. 433, 30 Cont. Cas. Fed. 70,529, 1 Cl. Ct. 50, 1982 U.S. Claims LEXIS 2305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morris-mechanical-enterprises-inc-v-united-states-cc-1982.