James Talcott Construction, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedMarch 4, 2019
Docket14-427
StatusUnpublished

This text of James Talcott Construction, Inc. v. United States (James Talcott Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Talcott Construction, Inc. v. United States, (uscfc 2019).

Opinion

United States Court of Federal Claims No. 14-427 C March 4, 2019 ____________________________________

JAMES TALCOTT CONSTRUCTION INC.,

Plaintiff, v.

UNITED STATES OF AMERICA,

Defendant. ____________________________________

Steven D. Meachem, Esquire, Peel Brimley LLP, Seattle, WA, for plaintiff.

Mariana Terea Acevedo, Esquire, United States Department of Justice, Civil Division, Washington, DC; Michael Duane Austin, Esquire, United States Department of Justice, Civil Division, Washington, DC; and Ryan Michael Majerus, Esquire, United States Department of Justice, Civil Division, Washington, DC, for defendant.

POST-TRIAL ORDER AND OPINION

Hodges, Senior Judge.

This case arises from a dispute between James Talcott Construction, Inc., and the United States through the Department of Defense, Department of the Army, and the United States Army Corps of Engineers.

The contract called for the construction of military family housing at Malmstrom Air Force Base in Great Falls, Montana. Talcott alleges that it suffered damages because the Government supplied an incomplete contract and a defective design, which led to the performance of additional work.

We conducted a nine-day trial in Seattle, Washington, and made the following relevant conclusions: (1) the contract contained performance specifications, not design specifications; (2) Talcott knew, or should have known, that site conditions favored mold growth; (3) the Government did not direct Talcott to perform work outside the contract terms; and (4) Talcott is not entitled to costs associated with scheduling delays.

-1- BACKGROUND

Talcott Begins Construction

The Government sought to replace deteriorating housing for military families at the Malmstrom Air Force Base in Great Falls, Montana. The Government awarded the “Phase 7E” contract to Talcott in May 2010 and issued a “Notice to Proceed” effective June 2010.

Phase 7E involved the construction of thirteen buildings, each with seventy units constructed with pile and grade beam foundation systems, wood framed and shingled roofs, one-car garages, fenced back yards, and concrete patios.1 The Government expected completion of the project by March 3, 2012.

Talcott began construction by pouring concrete foundations. After the concrete set, Talcott installed wooden floor joists and subfloor decking within the foundation area. The design made it clear that these materials would be enclosed in a crawl space. A crawl space is enclosed when sheathing is installed on the first floor. Sheathing is a board of material, usually wood, used to construct floors, roofs, and walls. Talcott elected to use untreated “Exposure 1” Opposed Strand Board for the first-floor sheathing and Opposed Strand Board joists for crawl spaces framing; Exposure 1 requires the moisture content level to be maintained below nineteen percent.

A building’s crawl space is typically ventilated by exterior vents and the air circulation regulates temperature and humidity. An enclosed crawl space depends on a mechanical system to maintain its temperature and humidity. It blows cool, dry air in the enclosed area to prevent moisture buildup and frozen pipes.

The Government’s design also incorporated sloped grading surfaces to drain water into sump basins and trench drains to divert water away from the foundation. To prevent groundwater vapor from entering the crawl space, a twenty-milliliter thick plastic polyethylene sheet covers the soil below the sheathing.

In this case, the concrete, wood, and soil remained exposed to snow and rain before Talcott enclosed the subfloor with sheathing. Talcott did not install temporary ground vapor barriers despite the presence of moisture on site.

Talcott Refuses Inspections of Building 620

An Air Force project manager visited the site for an inspection in November 2010. The project was always subject to reasonable inspections to certify the quality of

1 Buildings 620-626, 628, 630-633, 635, and 637.

-2- construction. FAR 52.246-12 (Inspection of Construction). He discovered that anchor bolts, which secure the finished structure to its foundation, installed out of alignment, misplaced, or missing entirely in buildings 620, 621, and 622. Concerned about the poor workmanship at such an early stage of the project, he called for an immediate inspection by the lead project engineer at the base.

The lead project engineer and the project manager returned two weeks to evaluate its quality. Their inspection confirmed that building 621 and building 622 did not comply with the contract. An assessment of building 620 did not occur because sheathing covered the subfloor structure. Talcott refused to cut access holes in the first-floor sheathing to allow for an examination of the anchor bolts on November 15, December 1, and December 29, 2010.

Talcott Discovers Mold

On January 5, 2011, workers discovered vast amounts of mold growth in building 620 after they cut access holes to install pipes in the crawl space. Talcott initiated preliminary mold clean up procedures, resealed the crawl space, and formally notified the Corps about the mold on January 6, 2011. The humidity measured more than eighty percent. JX 100-4912, 4922; Tr. 825:3-12 (Albrecht).

The contract’s “Safety and Occupational Health” clause demands that mold abatement be “overseen by a person experienced in mold behaviors and building design and construction, such as an industrial hygienist” and that “post-remediation air sampling shall be done in the immediate area and in any areas in the mold-spore or vegetative air- pathway, to verify that the remediation has been done properly and to ensure that there is no remaining hazard.” JX601-11594; Tr. 1157:17-25 (Henson). On January 26, 2011, the Corps advised Talcott that a remediation plan must “include any applicable testing required, that includes immediate measures to stop existing and future mold growth within 7 days” of the letter’s receipt. DX 18.

Talcott hired CTA Construction and Environmental, LLC, to develop a mold remediation plan. On February 10, 2011, CTA’s certified industrial hygienist presented Talcott with a mold remediation plan after evaluating the crawl space in January and in February. The plan included three recommendations that varied in price. For reasons unknown, Talcott did not deliver CTA’s recommendations with the Corps until March 1, 2011.

Talcott Alleges Damages

Talcott completed the project on July 25, 2012, a total of 145 days after the deadline. In October 2012, Talcott filed a Request for Equitable Adjustment claiming that it incurred additional costs under the “changes clause” of the contract because: “(1) the

-3- contract disc provided by [the Government] to Talcott lacked Amendment 6; (2) design flaws resulted in foundation mold problems; (3) a change in established inspection standards; (4) civil and structural design ambiguity; [and] (5) performance of out-of- scope work.”2 Talcott subsequently petitioned for a final decision from a Government contracting officer in June 2013. The contracting officer denied the claim and determined that it lacked merit.

Talcott filed a complaint against the Government in May 2014, which included claims for breach of contract, breach of implied warranties, and breach of good faith and fair dealing, and sought the following relief: (1) a court order entering judgment against the Government for breach of contract and breach of implied warranties; (2) a court order awarding Talcott damages in the amount proven at trial; (3) a court order directing the Government to change Talcott’s performance evaluation from “unsatisfactory” to “above average”; (4) attorneys’ fees and costs pursuant to the Equal Access to Justice Act, 28 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
McCormick Construction Co. v. United States
35 Cont. Cas. Fed. 75,721 (Court of Claims, 1989)
Wilner v. United States
26 Cl. Ct. 260 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
James Talcott Construction, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-talcott-construction-inc-v-united-states-uscfc-2019.