United States v. Renda Marine, Inc.

667 F.3d 651, 2012 WL 104999, 2012 U.S. App. LEXIS 796
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 13, 2012
Docket10-41296
StatusPublished
Cited by52 cases

This text of 667 F.3d 651 (United States v. Renda Marine, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Renda Marine, Inc., 667 F.3d 651, 2012 WL 104999, 2012 U.S. App. LEXIS 796 (5th Cir. 2012).

Opinion

BENAVIDES, Circuit Judge:

In this case, Renda Marine, Inc. (“Renda”) appeals the district court’s denial of its motion for partial dismissal for lack of subject matter jurisdiction and motion for partial summary judgment. Renda also appeals the district court’s grant of the Government’s motion for judgment on the pleadings. For the following reasons, we AFFIRM.

I. Factual and Procedural Background

In October 1998, Renda contracted with the Army Corps of Engineers to dredge a portion of the Houston Ship Channel and to construct containment levees and other structures at a disposal facility for dredge material. Renda experienced difficulties with the dredging and construction work, including allegedly unexpected site conditions that made completion of the work at the original contract price impossible. Renda submitted its claims for additional compensation to a contracting officer (“CO”) pursuant to the Contracts Dispute Act (“CDA”), 41 U.S.C. § 601, et seq. 1 The CO issued a unilateral contract modification in favor of Renda that increased the contract price by $3,083,833. The Army Corps of Engineers paid Renda this amount. Unsatisfied with the decision, Renda filed suit in the Court of Federal Claims (“CFC”) to recover an additional $906,364. The CFC determined that Renda was entitled to neither the additional $906,364 it sought, nor the equitable adjustment of $3,083,833 made by the CO.

*654 While Renda’s modification suit was pending before the CFC, the CO issued a final decision on six different claims the Government had brought against Renda for post-termination costs of completing certain aspects of the work originally covered by the contract. The CO granted the total amount of those claims, which was $11,860,016. The CO’s decision also stated that the Government withheld $259,840.85 in retainage. Renda did not appeal this decision directly. Rather, on July 1, 2004, Renda sought leave to amend its complaint in the ongoing CFC litigation to challenge the CO’s decision granting the Government $11,860,016. The CFC denied Renda’s motion and the Federal Circuit affirmed that denial.

On November 24, 2008 the Government filed the present lawsuit in federal district court, seeking to enforce the decisions of the CFC. In Count I, the Government alleges that Renda owes it $11,860,016, pursuant to the CO’s decision on the six counterclaims. In Count II, the Government seeks repayment of $3,083,833 — the amount paid to Renda in excess of the original contract price — based on the CFC’s determination that Renda was not entitled to any equitable adjustment of the contract price.

Renda filed a motion for partial dismissal, arguing that the district court lacked subject matter jurisdiction over Count II of the complaint because the Government allegedly failed to comply with the requirements of the CDA. Renda also filed a motion for partial summary judgment, arguing that the statute of limitations barred Count I. On September 30, 2010, the district court denied Renda’s motions, granted the Government’s motion for judgment on the pleadings on both claims, and entered judgment against Renda. The district court held that it had jurisdiction to enforce the CFC’s decision that Renda was not entitled to the $3,083,833 the Government had paid it, and that the Government had timely filed its suit to enforce the $11,860,016 judgment against Renda. The district court also held that Renda was not entitled to any offset of the Government’s recovery based on funds the Government had kept in retainage. Renda then timely filed this appeal of the district court’s judgment.

II. Standard of Review

A challenge to this court’s subject matter jurisdiction may be raised at any time on appeal. Arbaugh v. Y & H Corp., 546 U.S. 500, 506, 126 S.Ct. 1235, 163 L.Ed.2d 1097 (2006); Edge Petroleum Operating Co. v. GPR Holdings, L.L.C. (In re TXNB Internal Case), 483 F.3d 292, 298 n. 6 (5th Cir.2007). When considering a motion to dismiss for lack of subject matter jurisdiction, a district court may consider: “(1) the complaint alone; (2) the complaint supplemented by undisputed facts evidenced in the record; or (3) the complaint supplemented by undisputed facts plus the court’s resolution of disputed facts.” Rodriguez v. Christus Spohn Health Sys. Corp., 628 F.3d 731, 734 (5th Cir.2010) (quoting Ramming v. United States, 281 F.3d 158, 161 (5th Cir.2001)). The party asserting jurisdiction has the burden of proof. Ramming, 281 F.3d at 161.

We review de novo a district court’s grant of judgment on the pleadings under Federal Rule of Civil Procedure 12(c). Brittan Communs. Int’l Corp. v. Sw. Bell Tel. Co., 313 F.3d 899, 904 (5th Cir.2002). “[W]e must look only to the pleadings and accept all allegations contained therein as true.” Id. “The issue is not whether the plaintiffs will ultimately prevail, but whether they are entitled to offer evidence to support their claims.” *655 Ferrer v. Chevron Corp., 484 F.3d 776, 780 (5th Cir.2007).

We also apply a de novo standard of review to a motion to dismiss under Rule 12(b)(1), and motions for summary judgment under Rule 56. LeClerc v. Webb, 419 F.3d 405, 413 (5th Cir.2005). Summary judgment is appropriate if the moving party can show that “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a). “A factual dispute is ‘genuine’ where a reasonable party would return a verdict for the non-moving party.” Chiu v. Plano Indep. Sch. Dist., 339 F.3d 273, 282 (5th Cir.2003) (citation omitted). In considering a summary judgment motion, we view the evidence in the light most favorable to the non-moving party. United Fire & Cas. Co. v. Hixson Bros., Inc., 453 F.3d 283, 285 (5th Cir.2006). However, “[Unsubstantiated assertions, improbable inferences, and unsupported speculation are not sufficient to defeat a motion for summary judgment.” Brown v. City of Houston, 337 F.3d 539, 541 (5th Cir.2003).

III. Analysis

A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
667 F.3d 651, 2012 WL 104999, 2012 U.S. App. LEXIS 796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-renda-marine-inc-ca5-2012.