United States v. American States Insurance Company

252 F.3d 1268, 2001 U.S. App. LEXIS 11282, 2001 WL 585695
CourtCourt of Appeals for the Eleventh Circuit
DecidedMay 31, 2001
Docket00-15411
StatusPublished
Cited by7 cases

This text of 252 F.3d 1268 (United States v. American States Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. American States Insurance Company, 252 F.3d 1268, 2001 U.S. App. LEXIS 11282, 2001 WL 585695 (11th Cir. 2001).

Opinion

KRAVITCH, Circuit Judge:

Defendant American States Insurance Co. (“American States”) appeals the district court’s entry of summary judgment in favor of the United States for damages from the breach of a surety agreement. Because we find that the statute of limitations contained in 28 U.S.C. § 2415(a) bars the suit, we reverse and remand with instructions that judgment be entered for American States.

*1270 I. BACKGROUND

In 1984, the United States (“the Government”) contracted with Skip Kirchdorfer, Inc. (“SKI”) for the renovation of certain military housing at Eglin Air Force Base, Florida. Pursuant to the Miller Act, 40 U.S.C. § 270a-270d, American States issued a performance bond as surety on behalf of SKI. Under the terms of the bond, American States and SKI shared joint and several liability up to $2,937,704 for any breach of the contract.

In December 1985, the Government terminated the contract, citing SKI’s failure to perform in accordance with the contract provisions. After investigating the termination, American States informed the Government of its conclusion that the termination was wrongful. SKI and the Government litigated the propriety of the termination and the Federal Circuit Court of Appeals upheld the termination. See Skip Kirchdorfer, Inc. v. Rice, 944 F.2d 912 (Fed.Cir.1991).

During the pendency of the litigation, the Government employed another company to complete the construction contract. The new company completed the renovations for $977,009.61 in excess of the contract price. On July 20, 1992, the contracting officer responsible for terminating SKI’s contract demanded that SKI and American States reimburse the Government for these excess costs. Both SKI and American States refused to pay and challenged the propriety of the demand. Three years later, on July 26, 1995, the contracting officer issued a final decision demanding the same amount.

American States filed suit in the Court of Federal Claims in June 1996, seeking a declaration that it was not required to pay the excess costs. The court dismissed the suit for lack of jurisdiction. On November 16, 1999, the Government sued American States to recover the excess costs under the terms of the bond. The Government sought $977,009.61, which was the same amount requested in the 1992 demand letter. American States moved to dismiss the action on the ground that it was barred by the statute of limitations. The district court denied the motion to dismiss and instead granted the Government’s motion for summary judgment, holding that American States was bound by the contracting officer’s final decision.

II. DISCUSSION

American States challenges the district court’s conclusion that the Government filed its lawsuit within the statute of limitations. 1 We review de novo a district court’s interpretation and application of a statute of limitations. See United States v. Gilbert, 136 F.3d 1451, 1453 (11th Cir.1998).

The statute of limitations for “every action for money damages” brought by the Government is six years from the accrual of the cause of action or one year from a final decision in any administrative proceeding required by law or contract, whichever is later. 28 U.S.C. § 2415(a). 2 *1271 “For the purpose of computing the limitations periods established in section 2415, there shall be excluded all periods during which ... facts material to the right of action are not known and reasonably could not be known by an official of the United States charged with the responsibility to act in the circumstances.... ” 28 U.S.C. § 2616(c).

The Government makes two arguments: (1)that § 2415(a) does not apply to this lawsuit, and (2) that even if § 2415(a) applies, the limitations period did not begin to run until the contracting officer made his final decision, which was less than six years before the Government filed suit.

A. Applicability of § 24-15(a)

The Government contends that § 2415(a) does not apply to this lawsuit because the action is not a “suit for money damages” within the meaning of § 2415(a). The Government argues instead that its lawsuit is akin to a suit to enforce a judgment-in this case the judgment of the contracting officer. Because a suit to enforce a judgment is an equitable action, § 2415(a) does not apply to such an action. See United States v. Hannon, 728 F.2d 142, 145 (2d Cir.1984). The Government argues that this same principle applies when the Government sues a surety to recover on a performance bond.

We disagree. Even though the decisions of contracting officers are not subject to challenge on the merits, they are not themselves judgments. See United States v. Suntip Co., 82 F.3d 1468, 1475 (9th Cir.1996). Section 2415(a) recognizes this fact by requiring the Government to sue “within one year after final decisions have been rendered in applicable administrative proceedings.” As the Ninth Circuit noted in Suntip, this provision covers actions by the Government to enforce a final administrative decision, and thereby suggests that such decisions are not judgments exempted from the statute of limitations. 82 F.3d at 1475-76.

Furthermore, this lawsuit essentially is a breach of contract suit. The Government seeks damages from American States because American States has refused to honor its obligation under the surety agreement. Although the amount in question was determined by the contracting officer, the obligation sought to be enforced is contractual. American States would not be liable but for the surety agreement. See United States v. Seaboard Sur. Co., 817 F.2d 956, 962-63 (2d Cir.1987) (holding that surety’s liability is distinct from contractor’s liability and therefore does not have to be litigated in the claims court under the Contract Disputes Act, 41 U.S.C. § 601 et seq.). By suing to recover damages for the breach of this surety agreement, the Government has brought an action for money damages. Accordingly, § 2415(a) governs.

In further support of its argument that § 2415(a) does not apply, the Government points to Motorola Inc. v. West, 125 F.3d 1470 (Fed.Cir.1997), in which the Federal Circuit held that § 2415(a) does not control claims under the Contract Disputes Act (“CDA”), 41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Renda Marine, Inc.
667 F.3d 651 (Fifth Circuit, 2012)
United States v. Renda Marine, Inc.
750 F. Supp. 2d 755 (E.D. Texas, 2010)
Inyang Peter Oduok v. Sean Phillips
154 F. App'x 878 (Eleventh Circuit, 2005)
American States Insurance v. Kirchdorfer
92 F. App'x 103 (Sixth Circuit, 2003)
Preferred Sites, LLC v. Troup County
296 F.3d 1210 (Eleventh Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
252 F.3d 1268, 2001 U.S. App. LEXIS 11282, 2001 WL 585695, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-american-states-insurance-company-ca11-2001.