Motorola, Inc. v. Togo D. West, Secretary of the Army

125 F.3d 1470
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 16, 1997
Docket97-1098
StatusPublished
Cited by14 cases

This text of 125 F.3d 1470 (Motorola, Inc. v. Togo D. West, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Motorola, Inc. v. Togo D. West, Secretary of the Army, 125 F.3d 1470 (Fed. Cir. 1997).

Opinion

RADER, Circuit Judge.

Aydin Corporation, proceeding through Motorola, Inc., the prime contractor, appeals a decision of the Armed Services Board of Contract Appeals (Board) partially denying Aydin Corporation’s appeal from a contracting officer’s final decision. Because no statute of limitations bars the Government’s claim and Aydin Corporation did not meet its submission requirements under the Truth in Negotiations Act (TINA), this court affirms.

I.

Aydin Corporation brings this appeal in the name and with the authorization of Motorola, Inc. (Motorola), the prime contractor. On August 10,1984, Motorola entered a contract with U.S. Army Communications and Electronics Command (CECOM). CECOM sought to modify the contract to add raster display subsystems from Aydin Computer Systems Division (Aydin), a division of Aydin Corporation.

On November 8, 1985, Aydin submitted a proposal to its competitor, Motorola. In the proposal, Aydin claimed that its “indirect and Burden Rates [were proprietary] in nature and [were] available for Audit through [the Defense Contract Audit Agency].” In other words, Aydin refused to share its cost data with Motorola. This undisclosed data included within its General and Administrative (G & A) expenses a “facilities capital charge” — a charge from Aydin Corporation to Aydin for an imputed cost of doing business.

In March 1986, Albert Shackerman of the Defense Contract Audit Agency (DCAA) audited Aydin’s proposal. DCAA issued a report dated March 17, 1986, recommending acceptance of Aydin’s proposed G & A rate of *1472 45%. Mr. Shackerman did not discover the facilities capital charge during that audit.

Aydin Corporation issued two corporate memoranda dated September 30, 1986, and August 21, 1987, directing all of its divisions to exclude the facilities capital charge from the G & A rate on its other Government contracts. Aydin’s president, Mr. Lohr, described the facilities capital charge as being like an imputed interest charge which “you could almost look at as a penalty.”

Beginning in December 1986, Motorola made several requests for a DCAA audit of Aydin’s proposal. A CECOM contract specialist later mistakenly requested cancellation of Motorola’s audit requests. During the week of February 27, 1987, CECOM provided Motorola with Aydin’s G & A rate, reported as 45%, based on telephonic verification with DCAA. Using that G & A rate, Motorola and Aydin negotiated a subcontract during March and April 1987, culminating in a firm, fixed price of $5,222,863. The Board later found that the amount of the subcontract would have' been different if Motorola had known of the facilities capital charge. On April 9, 1987, Aydin’s president, Mr. Lohr, executed a Certificate of Current Cost or Pricing Data for costs to and including April 3,1987.

During an April 1988 audit of Aydin Corporation, Aydin Corporation provided DCAA with its September 30, 1986, and August 21, 1987, corporate memoranda. Aydin’s financial statements, statements of operations, and general ledger offer no explanation for the facilities capital charge. Without some explanation, an auditor could not determine how the facilities capital charge was derived.

On September 30, 1991, DCAA issued an audit report recommending a price reduction of $933,787 based on a 24%, rather than a 45%, G & A rate. With September 24, 1986, as its baseline, that report disallowed Aydin’s facilities capital charge. After a change in the baseline to April 3, 1987 (the effective date of the certification of Mr. Lohr), the contracting officer issued a final decision dated August 5, 1993, reducing the price by $784,219. Later, on April 10, 1995, the contracting officer amended the final decision. On June 19, 1995, Aydin appealed the April 10, 1995, final decision to the Board. The Board concluded that Aydin’s submission included an unallowable facilities capital charge, that the charge was not disclosed, and that the Government detrimentally relied upon the submission.

II.

Standard of Review

41 U.S.C. § 609(b) (1988) governs the scope of review for appeals under the Contract Disputes Act (CDA):

[T]he decision of the agency board on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.

See Madigan v. Hobin Lumber Co., 986 F.2d 1401, 1403 (Fed.Cir.1993). Although contract interpretation is a question of law, the Board’s contract interpretation receives “careful consideration” from this court. Interstate Gen. Gov’t Contractors, Inc. v. Stone, 980 F.2d 1433, 1434 (Fed.Cir.1992).

Statute of Limitations

Aydin contends that one of two statutes of limitations bars the Government’s claim, either: (1) the six-year statute of limitations in 28 U.S.C. § 2415(a), or (2) the six-year statute of limitations added to CDA through the Federal Acquisition Streamlining Act of 1994 (FASA). The parties agree that the Government’s claim accrued on April 3, 1987. Although the parties disagree about which decision qualifies as the Government’s operative final decision, neither party disputes that the final decision came more than six years after April 3,1987. Therefore, if this court applies either statute of limitations, the Government’s claim is time-barred.

This court has determined that section 2415(a) does not apply to Government claims that cannot be asserted in federal court before issuance of a contracting officer’s final decision. By its terms, section 2415(a) applies only to an “action for money damages brought by the United States.” 28 *1473 U.S.C. § 2415(a) (1994). These terms do not cover a CDA claim, which necessarily arises only after issuance of an administrative decision:

[T]he challenged [CDA] action is not an “action for money damages brought by the United States,” as expressly required by the statute. Instead it is an administrative appeal by a contractor from a contracting officer’s decision that the contractor owes the Government the amount of certain disallowed costs. Therefore, we hold that 28 U.S.C. § 2415 is inapplicable on its face.

S.E.R., Jobs for Progress, Inc. v. United States, 759 F.2d 1, 5 (Fed.Cir.1985). Since section 2415 does not apply to Government claims under the CDA, we reject Motorola’s argument that FASA was intended to clarify existing law, e.g.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Expresser Transport Corporation
Armed Services Board of Contract Appeals, 2018
Sikorsky Aircraft Corporation v. United States
773 F.3d 1315 (Federal Circuit, 2014)
M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)
Parsons Transportation Group, Inc. v. United States
84 Fed. Cl. 779 (Federal Claims, 2008)
Ramah Navajo School Board, Inc. v. United States
83 Fed. Cl. 786 (Federal Claims, 2008)
American Ordnance LLC v. United States
83 Fed. Cl. 559 (Federal Claims, 2008)
Axion Corp. v. United States
68 Fed. Cl. 468 (Federal Claims, 2005)
Greenwood Associates, L.P. v. Perry
399 F.3d 1317 (Federal Circuit, 2005)
United States v. American States Insurance Company
252 F.3d 1268 (Eleventh Circuit, 2001)
Aero Union Corp. v. United States
47 Fed. Cl. 677 (Federal Claims, 2000)
City of Burbank, California v. United States
47 Fed. Cl. 261 (Federal Claims, 2000)
Sucesion J. Serralles, Inc. v. United States
46 Fed. Cl. 773 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
125 F.3d 1470, Counsel Stack Legal Research, https://law.counselstack.com/opinion/motorola-inc-v-togo-d-west-secretary-of-the-army-cafc-1997.