Parsons Transportation Group, Inc. v. United States

84 Fed. Cl. 779, 2008 U.S. Claims LEXIS 347, 2008 WL 5136511
CourtUnited States Court of Federal Claims
DecidedDecember 3, 2008
DocketNo. 08-079C
StatusPublished
Cited by3 cases

This text of 84 Fed. Cl. 779 (Parsons Transportation Group, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parsons Transportation Group, Inc. v. United States, 84 Fed. Cl. 779, 2008 U.S. Claims LEXIS 347, 2008 WL 5136511 (uscfc 2008).

Opinion

OPINION

DAMICH, Chief Judge.

I. Introduction

Parsons Transportation Group, Inc. (“Parsons”) alleges that the Federal Railroad Administration (“FRA”) breached a contract with it1 when the FRA refused Parsons’ requests for indemnification. There is a provision in the contract, whereby the FRA is required to indemnify Parsons for certain losses exceeding a $1 million deductible. Parsons asserts that covered losses from its payments to other parties have now exceeded $2.4 million.

The case is now before the Court on a set of three motions filed by the Government. First, in Defendant’s Motion to Dismiss Counts I, II, and III for Lack of Subject Matter Jurisdiction (“Defendant’s Motion to Dismiss”), the Government argues that the first three counts in Parsons’ five-count Complaint are time-barred by the Court’s six-year statute of limitations in 28 U.S.C. § 2501 (2000). However, that statute does not apply to claims pursued under the Contract Disputes Act of 1978 (“CDA”), 41 U.S.C. §§ 601-613 (2000). And Parsons’ claims for breach of contract for failure to honor the contract’s indemnification clause are covered by the CDA. Accordingly, the Court denies Defendant’s Motion to Dismiss.

Next, in Defendant’s Motion for Judgment Upon the Pleadings Upon Counts I and III (“Defendant’s Motion for Judgment on the Pleadings”), the Government argues that two of Parsons’ claimed losses fall outside the scope of the indemnification clause. Parsons disagrees with the Government’s interpretation of the contract. The Court denies this motion because the Government has not met its burden of showing that the facts Parsons presents cannot support Parsons’ interpretation.

Finally, in Defendant’s Motion for Summary Judgment Upon Count III (“Defendant’s Motion for Summary Judgment”), the Government argues that Parsons cannot recover an amount paid to settle certain litigation because Parsons released the Government from any liability regarding that matter. Here, the Court agrees and grants summary judgment for the Government on Count III.

II. Background

In the late 1970s, the FRA awarded Parsons a contract to serve as prime architect-[781]*781engineer and program manager of the Northeast Corridor Improvement Project (“NECIP”), a project to improve rail facilities. Pl.’s Br. in Opp’n to Def.’s Mot. to Dismiss 1. Initially, the FRA had issued a letter contract to Parsons in 1976. Negotiations followed and the contract was finalized in October 1979. Id. at 2. In Article XIV of the contract, the FRA agreed to indemnify Parsons against certain claims for damages by third parties. Compl. HH12-13.

Beginning in the 1980s, Parsons allegedly made payments to satisfy claims asserted against it by other parties. Id. HH15-32. Parsons claims that those payments and associated fees have now exceeded $2.4 million, surpassing a $1 million deductible that the indemnification provision of the contract requires Parsons to meet. Id. UK 13-32. Following unsuccessful efforts to obtain indemnification in the amount exceeding the deductible, Parsons filed a five-count Complaint in this Court on February 8, 2008. Only the first three counts are addressed by the Government’s present motions.

Count I corresponds to the “Stamford claims.” Those claims were brought against Parsons by Wilber Smith Associates (“WSA”), which performed engineering services for the design and construction of the Stamford Transportation Center in Stamford, Connecticut. Id. fit 22-23. In 1986, WSA submitted a claim to Parsons “for extra work on the structural elements of the Stamford Station” that resulted from “numerous design defects [] discovered in connection with the work.” Id. II23. In 1989, an arbitration panel awarded WSA $377,636 plus interest and attorney’s fees. Id. 1124.

Count II relates to the “A & C Fuel claims.” In 1985, a vessel owned by A & C Fuel Corporation collided with the Penn Mainline Bridge, which Parsons had designed under the NECIP. Id. 1125. In 1989, Parsons paid $20,833.33 to settle these claims. Id. H26. Parsons’ combined attorney’s fees for the Stamford Claims and the A & C Fuel Claims (Counts I and II) amounted to $408,002.74. Id. II28.

Count III stems from claims asserted by the Massachusetts Bay Transportation Authority (“MBTA”) against Parsons. Under the NECIP, Parsons performed architectural engineering services for the South Station in Boston, Massachusetts in coordination with the MBTA. Id. H 30. In 1988, the MBTA sued Parsons for delay damages allegedly incurred by the South Station Project’s general contractor, JF White Construction Company. Id. 1131. In March 1995, Parsons paid $425,000 to settle the MBTA claims and incurred total expenses, including attorney’s fees, of $978,943.43. Id. 1132.

III. Defendant’s Motion to Dismiss

The Government argues that Counts I, II, and III must be dismissed for failure to satisfy the six-year statute of limitations in 28 U.S.C. § 2501. Section 2501 limits the Court’s jurisdiction under the Tucker Act, 28 U.S.C. § 1491. See John R. Sand & Gravel Co. v. United States, — U.S.-,-- -, 128 S.Ct. 750, 753-55, 169 L.Ed.2d 591 (2008). But it does not apply to CDA suits. Pathman Constr. Co. v. United States, 817 F.2d 1573, 1580 (Fed.Cir.1987) (“Once a contractor elects to proceed under the [Contract] Disputes Act, the six-year statute of limitations in 28 U.S.C. § 2501 is not applicable.”). Although the CDA now contains a six-year statute of limitations of its own, that provision does not apply here because this contract was awarded before October 1,1995. See Motorola, Inc. v. West, 125 F.3d 1470, 1473-74 (Fed.Cir.1997). As the Government conceded during status conferences held on August 1, 2008 and October 24, 2008, if the CDA covers Parsons’ claims they will not be time-barred and Defendant’s Motion to Dismiss must be denied.

Parsons’ claims are for breach of contract and are covered by the CDA. Despite the FRA’s refusal to consider this claim under the CDA, Parsons’ Complaint clearly asserts CDA jurisdiction: “This claim is for breach of contract for the failure of the FRA to honor its obligation, pursuant to Article XIV of the parties’ contract, to indemnify Parsons for damages____” Compl. 113; Compl. H 4 (“This is a civil action brought ... pursuant to the Contract Disputes Act____”). Notwithstanding the language of the Complaint, the Government continually frames this case as a request for indemnification pursuant to [782]*782Public Law No. 85-804, 72 Stat. 972 (1958) (codified as amended at 50 U.S.C. §§ 1431-1435 (2000)). E.g.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

System Planning Corp. v. United States
95 Fed. Cl. 1 (Federal Claims, 2010)
BLR Group of America, Inc. v. United States
94 Fed. Cl. 354 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
84 Fed. Cl. 779, 2008 U.S. Claims LEXIS 347, 2008 WL 5136511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parsons-transportation-group-inc-v-united-states-uscfc-2008.