American Ordnance LLC v. United States

83 Fed. Cl. 559, 2008 U.S. Claims LEXIS 269, 2008 WL 4266125
United States Court of Federal Claims·Decided September 12, 2008·No. No. 07-867C·Published·Cited by 3 cases

Opinion

OPINION AND ORDER

WHEELER, Judge.

This case presents the issue of which party, American Ordnance LLC (“AO”) or the United States Army, owns the Line 3A manufacturing equipment at the Iowa Army Ammunition Plant in Middletown, Iowa. Line 3A is used to manufacture M795 projectiles. The dispute stems from a December 12,1995 letter contract1 between Mason & Hanger Corporation (“Mason & Hanger”) and the Army that the parties definitized on August 15, 1996. AO is the successor-in-interest to Mason & Hanger in operating the Iowa plant for the Government. The Court agreed to hear this case on an expedited basis because the Government wants to provide the manufacturing equipment as “government-furnished property” in a competitive acquisition. AO objects to this approach, arguing that the Government does not own the property. AO seeks a declaratory judgment that it is the owner of the Line 3A equipment.

The Court has jurisdiction of this matter under the Contract Disputes Act (“CDA”), 41 U.S.C. § 609(a)(1) (2006). AO filed suit on December 10, 2007, after receiving the Contracting Officer’s September 26, 2007 final decision. The Army’s assertion of ownership of the Line 3A manufacturing equipment is a claim by the Government against the contractor under 41 U.S.C. § 605(a). The Contracting Officer’s final decision did not result from a claim submitted by the contractor. The property ownership dispute arose only when the Army elected in 2007 to alter its position regarding the Line 3A equipment from the prior eleven years. The Court conducts a de novo review under 41 U.S.C. § 609(a)(3).

The issue before the Court is one of contract interpretation. In considering the parties’ June 30, 2008 cross-motions for summary judgment, the Court found the definitive contract ambiguous as to which party owns the Line 3A equipment. While the definitive contract provides for the reimbursement to the contractor of the agreed fixed price of the Line 3A equipment ($9,310,071), it does not specify which party, Mason & Hanger or the Government, was to take ownership of the equipment. Accordingly, on August 1, 2008, the Court denied both motions for summary judgment. The Court conducted a trial during August 12-15, 2008, at which it received evidence outside the four corners of the contract to determine the parties’ intent.2 The Court considered provisions that were removed from the letter contract when it was definitized, the parties’ correspondence in negotiating the definitive contract, and the actions of the parties before and after definitization. The Court endeavored to harmonize all of the definitive contract provisions with the intentions and actions of the parties.

At the conclusion of trial, the Court issued a bench ruling that AO is the owner of the [562]*562Line 3A manufacturing equipment. Originally, the letter contract indicated that the Army was to take title to this equipment, but the Army reversed its position during negotiations leading to the definitive contract. After analyzing the risks and responsibilities of ownership, Mason & Hanger agreed to accept title to the equipment. The correspondence between the parties, coupled with the changes made in the definitive contract, make this conclusion crystal clear. If any doubt remained, the parties’ conduct before and after the definitization of the contract confirms their intent. At all times from May 16, 1996 (the date of a key Contracting Officer letter) until September 6, 2007 (the date that the Government first asserted ownership), the parties acted consistently with the conclusion that Mason & Hanger, and now AO, owns the equipment. The Government’s attempt to paint a different picture at trial contradicts the contemporaneous record and lacks credibility. The Court by this Opinion and Order formalizes the declaratory judgment in Plaintiffs favor issued at the close of trial.

AO asserts in the alternative that the Government’s claim is barred by the six-year limitations period contained in the CDA, 41 U.S.C. § 605(a). That section provides that “[e]ach claim by a contractor against the government relating to a contract and each claim by the government against a contractor relating to a contract shall be submitted within 6 years after the accrual of the claim.” Id. (emphasis added). The Court finds that the Government’s claim of ownership of the Line 3A equipment accrued not later than October 21, 1997, the date when the Contracting Officer confirmed that Mason & Hanger had successfully completed the installation of the equipment. By that date, Mason & Hanger had placed property ownership tags on the equipment, and had recorded the equipment on its records as property owned by Mason & Hanger. Accordingly, the Court further concludes that the Government’s claim of ownership of the Line 3A equipment, first asserted in September 2007, is barred by the CDA’s six-year statute of limitations.

Findings of Fact 3

A. Background

The Iowa Army Ammunition Plant (“IAAP”) is a Government-owned, contractor-operated facility located in Middletown, Iowa. The plant occupies approximately 19,-000 acres of land, and includes production and storage facilities, as well as an administration building. A wide range of munitions is produced at the plant. From 1951 to 1998, Mason & Hanger operated the IAAP for the Army. (Daniel, Tr. 72).4 In 1998, Mason & Hanger and General Dynamics Ordnance Systems, Inc. formed a joint venture known as American Ordnance LLC (“AO”). (Daniel, Tr. 55-56). AO has operated the IAAP from 1998 to the present. Before 1990, Mason & Hanger operated the IAAP under cost-plus-fixed-fee contracts. (Daniel, Tr. 72-73). Beginning in the early 1990s, the Government started replacing cost-plus-fixed fee contracts with “facilities use” contracts, requiring contractors to make capital investments in equipment and personal property in the government facility. (Daniel, Tr. 74).

B. M795 Contract Negotiations

On October 11, 1995, the Army issued Request for Proposal (“RFP”) No. DAAE3096-R0004 for the production of M795 projectiles at the IAAP. (PX 2). The M795 projectile had never been mass-produced before, and therefore no production history existed permitting an assessment of the manufacturing process. (Daniel, Tr. 77-78). The RFP contained a Contract Line Item (“CLIN”) 0001AA under “Basic Requirement” directing the contractor to “Design, Fabricate and [563]*563install equipment in accordance with statement of work Section C.3.9.” (PX 2 at 5). The Statement of Work, Section C.3.9, provided:

Equipment—Equipment purehased/fabricated by the contractor under this procurement shall be property of the U.S. government. A partial list of equipment includes: Preheat Ovens, Grid Melter, Melt Kettles, Pour Machines, Controlled Cooling Apparatus, and Post Cyclic Conditioners.

Id. at 10.

Free access — add to your briefcase to read the full text and ask questions with AI

American Ordnance LLC v. United States, 83 Fed. Cl. 559, 2008 U.S. Claims LEXIS 269, 2008 WL 4266125 (uscfc 2008).

83 Fed. Cl. 559 (American Ordnance LLC v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)