Spackman v. Ralph M. Parsons Co.

414 P.2d 918, 147 Mont. 500, 1966 Mont. LEXIS 408
CourtMontana Supreme Court
DecidedJune 2, 1966
Docket10924
StatusPublished
Cited by55 cases

This text of 414 P.2d 918 (Spackman v. Ralph M. Parsons Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spackman v. Ralph M. Parsons Co., 414 P.2d 918, 147 Mont. 500, 1966 Mont. LEXIS 408 (Mo. 1966).

Opinion

MR. CHIEF JUSTICE JAMES T. HARRISON

delivered the Opinion of the Court.

This is an appeal by defendant, Ralph M. Parsons Company, (hereafter called Parsons) from a verdict and judgment for damages in the sum of $29,825.00, rendered in the district court of Silver Bow County in favor of plaintiffs.

The case involves damages to real and personal property caused by sewage flooding and exemplary damages in relation thereto.

During late April 1963, defendant Parsons was engaged in constructing a water line from Anaconda to Butte in connection with a new concentrator being built by the Anaconda Company.

The progress of the ditch digging reached a point behind the plaintiffs’ motel, located at Montana and Front Streets in Butte, about April 25th.

On April 26th or 27th (the date is in conflict and will be discussed later) a machine called a “backhoe” bit into the earth and tore out four feet of the top half of a 24-ineh sanitary sewer pipe line. Three men were present. One began digging *503 with a hand shovel to clear the dirt and debris away from the pipe openings, thereby encouraging the water to flow freely. A short time later, the backhoe tore out a similar four-foot section of an 18-inch sanitary sewer line.

The earth through which the ditch was being dug was a fill of' decomposed granite — crumbly and given to caving-in. The sewage water worked swiftly on this type of soil and almost immediately caused the banks of the ditch to cave. The workmen did two things: first they built a small, Afoot high earthen retaining dam across the ditch to prevent the water from flowing down the ditch. Then, with the use of the backhoe, they sloped the sides of the ditch away from the severed pipe inlets and outlets at an angle they considered sufficient to prevent further caving (1^2 to 1). These efforts resulted in a widening of the ditch — originally 4 feet wide — to about 40 feet at the top and 12 feet at the bottom. The ditch was 16 feet deep. When about 4 feet of unbroken pipe was exposed, the men decided enough precautions had been taken. When they left the ditch for the weekend at 4:30, quitting time, the water was gushing out of the inlet, flowing across four feet of open dirt and broken pipe tile, entering the intended outlet and continuing its invisible journey. At the time, no one considered it necessary, if they thought of it, to notify the Butte Sanitation Division which had jurisdiction over the sewer lines and was responsible for maintenance thereof. No watchman or guard was placed at the ditch. By Sunday evening, the situation had changed drastically. Dirt and rock had caved into the ditch and plugged the outlets for the sewage. The ditch rapidly filled up. Seeking its own level, the water reversed its direction in the sewer pipes and flowed back toward its sources. On its way it sought out the plaintiffs’ sink and floor drains and escaped through them into the plaintiffs’ basement. Mr. Spackman discovered 2 to 3 inches of water in his basement about 6 o’clock Sunday evening.

A long series of frantic telephone calls followed which even *504 tually succeeded in reaching several of the defendant’s employees. The first employee, Mr. Nuckols, reached the motel between 7:00 and 8:00 p. m. The plaintiff’s attorney reached the motel between 8:00 p. m. and 8:30 p. m. He called a photographer who began taking pictures of the flooding basement about 9:30. These are in evidence. The plaintiff’s son-in-law arrived and took more pictures about 10:00. These also are in evidence. Shortly thereafter, more of the defendant’s employees arrived with a small pump and began pumping out the basement. Other men worked on the ditch, extending it and pumping it out in an effort to lower the level of the water in the ditch. The water crested at 19y2 inches before the pumps took effect. The basement was fully drained by Monday morning and the defendant sent in a crew of five or six men to remove the damaged property and clean the basement. It took them about two days to remove the items and scour the basement thoroughly. The motel was closed for those two days. The Butte Health Officer was called in to inspect the items removed from the basement and he ordered the greater portion of them destroyed.

The amended complaint prayed for the following damages:

1. $ 9,671.51 — damage to personal property 355.25 — laundry expenses 36.00 — fumigation expenses 252.00 — loss of motel business for 2 days
$10,314.76
2. $ 825.00 — Cost of replacing damaged basement floor
3. $25,000.00 — exemplary damages
4. Costs of suit

The defendant confessed negligence in the severing of the sewer pipe lines and admitted liability for the laundry, fumigation and loss of business damages — a total of $646.25 — and denied all the other alleged damages.

The jury returned a verdict for the plaintiffs on the first *505 claim in the amount of $9,000; on the second claim in the amount of $825; and on the third claim in the amount of $20,000.

The defendant’s brief is extremely lengthy. The arguments and specifications of error can be grouped generally as: (1) -whether plaintiffs breached their duty to mitigate the damages ; (2) whether exemplary damages are proper in this case, and; (3) whether the actual damages and exemplary damages are excessive.

The duty to reduce or mitigate damages is a positive one upon the injured person, but it has limits. The test is: What would an ordinarily prudent person be expected to do if capable, under the circumstances? See generally 25 C.J.S., Damages, § 33, p. 701. The defendant claims the plaintiffs were obliged to wade into the sewage water and either remove the property from the basement or place it on shelves above the reach of the rising water. The contention is rather absurd since we are not dealing with drinking water, we are concerned with raw human sewage. It is beyond reason to say that a man and a woman have the duty to wade into such filth. Not only would such an act violate normal sensitivities, it would constitute a positive danger to one’s health. The duty to mitigate damage occurring to one’s property does not demand that a person place his health in jeopardy. In this case, where the property in the basement was largely of the type immediately contaminated by the mere presence of the sewage — linens, paper, bedding and other absorbent materials — regardless of whether it actually soaked in the water, it seems especially fruitless to say that the duty to mitigate demanded its removal. Most of it was contaminated before the plaintiffs discovered the flood. It must be remembered that the plaintiffs had no boots at the time the invading water was discovered, and did not obtain boots until about 10:00, four hours later, by which time the water had almost crested. Whatever damage was done had already been done by that time.

*506 The defendant stresses the point that Mr. Nuckols attempted to remove a television set from the basement and was ordered by Mrs. Spackman to leave it alone. The testimony is conflicting about Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Timpano v. Central MT HRDC
2022 MT 169 (Montana Supreme Court, 2022)
Wittman v. City of Billings
2022 MT 129 (Montana Supreme Court, 2022)
Labair Ex Rel. Labair v. Carey
2012 MT 312 (Montana Supreme Court, 2012)
Kraft v. HIGH COUNTRY MOTORS, INC.
2012 MT 83 (Montana Supreme Court, 2012)
State v. Kalal
2009 MT 103 (Montana Supreme Court, 2009)
Sunburst School District No. 2 v. Texaco, Inc.
2007 MT 183 (Montana Supreme Court, 2007)
Sherner v. NATIONAL LOSS CONTROL SER. CORP.
2005 MT 284 (Montana Supreme Court, 2005)
Sherner v. National Loss Control Services Corp.
2005 MT 284 (Montana Supreme Court, 2005)
Semenza v. Bowman
885 P.2d 451 (Montana Supreme Court, 1994)
Montana Pole & Treating Plant v. I.F. Laucks & Co.
993 F.2d 676 (Ninth Circuit, 1993)
Montana Pole & Treating Plant v. IF Laucks and Co.
775 F. Supp. 1339 (D. Montana, 1991)
Burk Ranches, Inc. v. State
790 P.2d 443 (Montana Supreme Court, 1990)
Romain v. Earl Schwartz Company
779 P.2d 54 (Montana Supreme Court, 1989)
Romero v. J & J TIRE
777 P.2d 292 (Montana Supreme Court, 1989)
Davis v. Sheriff
762 P.2d 221 (Montana Supreme Court, 1988)
Hostetter v. Donlan
719 P.2d 1243 (Montana Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
414 P.2d 918, 147 Mont. 500, 1966 Mont. LEXIS 408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spackman-v-ralph-m-parsons-co-mont-1966.