Bethlehem Steel Corp. v. Litton Industries, Inc.

468 A.2d 748, 321 Pa. Super. 357
CourtSupreme Court of Pennsylvania
DecidedApril 30, 1984
Docket197
StatusPublished
Cited by10 cases

This text of 468 A.2d 748 (Bethlehem Steel Corp. v. Litton Industries, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Steel Corp. v. Litton Industries, Inc., 468 A.2d 748, 321 Pa. Super. 357 (Pa. 1984).

Opinions

WICKERSHAM, Judge:

The central issue in this case is whether a certain written option agreement is a contract. The matter was contested in a bifurcated non-jury trial and, by consent of both parties, liability alone was at issue. The trial judge, Honorable Maurice Louik entered an adjudication in which he held that the plaintiff-appellant had not sustained its burden of proving that the parties intended to be contractually bound. Exceptions to the trial court’s adjudication were argued before a court en banc comprised of the Honorable Judge Louik, Judge Nicholas P. Papadakos and the Honorable Joseph A. Del Sole which court en banc dismissed the exceptions of plaintiff-appellant and affirmed the adjudication of Judge Louik. This appeal followed. We agree with the conclusion reached by Judge Louik and the court en banc and we affirm.1

On June 19, 1974 Bethlehem Steel Corporation, plaintiff-appellant filed a complaint in assumpsit against .Litton [360]*360Industries Inc. and Erie Marine, Inc., a division of Litton Industries, trading as Erie Marine division of Litton Industries, hereinafter Litton, appellee.

Basically the complaint alleged that on or about April 25, 1968 Litton entered into an agreement with Bethlehem whereby Litton would construct and deliver and Bethlehem would purchase a one thousand foot self-unloading ore vessel. The vessel constructed under that agreement was delivered, accepted, and the price paid therefor.

The complaint further alleged that Litton extended to Bethlehem by letter dated April 25, 1968 “a written offer good until December 31, 1968 for the entry into an option agreement for five vessels.” Furthermore, it was alleged that on or about December 31, 1968 Bethlehem accepted the Litton’s offer to enter into an option agreement under which Bethlehem was granted the right for a period of five years after the execution of the option agreement to obtain from Litton from one to five vessels for prices varying between $22,400,000.00 and $18,400,000.00 each. Further, the complaint alleged that Bethlehem, pursuant to the option agreement, by letter dated November 16, 1973 exercised its option for two vessels and thereby ordered the first and second vessels in accordance with the option agreement. On December 26, 1973 Bethlehem, pursuant to the option agreement, exercised its option for an additional (third) vessel.

Finally, the complaint alleged that Litton expressly and unequivocally refused to perform in accordance with its obligations under the option agreement; that Litton demanded the payment of a price for each vessel many millions of dollars in excess of the price provided for in the option agreement and indicated delivery dates substantially later than the delivery provided in the option agreement. Damages were sought in a sum in excess of $95,000,000.00 together with interest and costs. On March 8, 1976, the case was designated as complex and was assigned to the Honorable Maurice Louik for all further proceedings.

[361]*361In its defense, Litton responded, inter alia: (1) PX-1 (the letter of December 31, 1968) was never intended to be and was not a contract; (2) no contract was formed in any event because the vital terms left for later negotiation could not be filled by the court on a reasonably certain basis; (3) any purported “option agreement” had been rejected prior to exercise by Bethlehem’s assertions that it would “never” order another vessel from Litton; (4) since an “option” unsupported by consideration is revocable at will, any purported “option agreement” had been revoked prior to exercise by Litton’s notice to Bethlehem that the Erie shipyard. was to be closed; (5) any purported “option” had never been properly exercised; and (6) Litton had never breached or repudiated any “agreement” which might have existed.

On June 28, 1978 a non-jury trial began and Judge Louik filed his adjudication on June 6, 1979 which provided, in part, as follows:

“ADJUDICATION

“LOUIK, J.

“After a protracted trial of approximately nine months with over 12,000 pages of testimony and some 500 exhibits, this matter is now before the Court for determination. The claim in excess of 95 million dollars, together with a counterclaim, is based on a two-page letter between two giant corporations. The Court has bifurcated the trial as to liability and damages. The issue before the Court presently is that of liability. Although the matter proceeded during such a lengthy period of time, the facts may be succinctly stated as follows.

“For background purposes, it should be noted that on April 25, 1968, at a formal signing ceremony, the plaintiff and defendant entered into a ship-construction contract for a newly designed 1,000 foot self unloading ore vessel. This vessel, known as Hull 101, was commissioned “The Cort”. In the contract for the Cort, the plaintiff was given the right of first refusal in connection with any possible future construction of such vessels. In addition, a two-ship option [362]*362agreement was executed on the same day. Although these items are not an issue in this case, the relevancy and effect of the provisions of the right of first refusal and, the two-ship option agreement in the instant claim will be the subject of discussion later.

“In addition, there is in evidence as PX-4 a document which was executed on that very same day, April 25, 1968, together with a document dated December 31, 1968, in evidence as PX-1. These are the documents in issue in the instant case.

“The primary and fundamental question now before the Court is whether or not there has been an option contract. The plaintiffs claim is based upon the following two-page letter:

ERIE MARINE, INC.

ERIE, PENNSYLVANIA

April 25, 1968

Bethlehem Steel Corporation

Bethlehem, Pennsylvania

Attn: Ralph K. Smith

Gentlemen:

Reference is made to the ship construction contract signed by our companies this date for the construction by us of a 1,000' self-unloading ore vessel for you. Reference is also made to my letter to you of this date extending to you an option to purchase either one or two additional vessels upon the terms therein set forth.

We hereby extend to you an offer to enter into an option agreement to have us construct for you from one to five additional vessels in accordance with “Specifications covering the Construction of a Self-Unloading Bulk Carrier for Bethlehem Steel Corporation” (Number Y 917) dated March 1968, addendum number 1 thereto dated March 28, 1968 and addendum number 2 thereto dated April 17, 1968. This [363]*363offer to enter into an option agreement shall be firm and irrevocable until December 31, 1968 at 5:00 P.M. E.S.T.

The terms of the option agreement are to be as follows:

(a) The specifications for the vessels shall be the specifications referred to above, except for mutually agreeable reduced test schedules of the vessels, if the testing of the vessel to be delivered under the contract executed this date proves successful.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

COMAN v. ACA COMPLIANCE GROUP
W.D. Pennsylvania, 2022
Chen v. Shum
22 Pa. D. & C.5th 225 (Lancaster County Court of Common Pleas, 2011)
Viola v. Bocher
740 A.2d 1176 (Superior Court of Pennsylvania, 1999)
Burge v. Western Pennsylvania Higher Education Council, Inc.
570 A.2d 536 (Supreme Court of Pennsylvania, 1990)
Morosetti v. Louisiana Land & Exploration Co.
564 A.2d 151 (Supreme Court of Pennsylvania, 1989)
Computer Network, Ltd. v. Purcell Tire & Rubber Co.
747 S.W.2d 669 (Missouri Court of Appeals, 1988)
Ceco Corp. v. Carson Concrete Corp.
691 F. Supp. 850 (E.D. Pennsylvania, 1988)
Bethlehem Steel Corp. v. Litton Industries, Inc.
488 A.2d 581 (Supreme Court of Pennsylvania, 1985)
Robert Wooler Co. v. Fidelity Bank
479 A.2d 1027 (Supreme Court of Pennsylvania, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
468 A.2d 748, 321 Pa. Super. 357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-steel-corp-v-litton-industries-inc-pa-1984.