Stevens v. Federal Cartridge Corp.

32 N.W.2d 312, 226 Minn. 148
CourtSupreme Court of Minnesota
DecidedApril 23, 1948
DocketNo. 34,617.
StatusPublished
Cited by5 cases

This text of 32 N.W.2d 312 (Stevens v. Federal Cartridge Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stevens v. Federal Cartridge Corp., 32 N.W.2d 312, 226 Minn. 148 (Mich. 1948).

Opinions

Frank T. Gallagher, Justice.

Plaintiff appeals from an order overruling its demurrer to defendant’s answer insofar as it relates to the defense that plaintiff had not exhausted the administrative remedies provided by the Contract Settlement Act of 1944, 41 USCA, §§ 101 to 125, and by U. S. Public Law 657, c. 864 (approved August 7,1946), and the rules and regulations promulgated thereunder. The court below certified that the question raised by plaintiff’s demurrer is important and doubtful.

Defendant is a corporation which was engaged by the United States government during the period from 1941 to 1945 as a prime contractor with the war department to operate and manage the Twin Cities Ordnance Plant, a government arsenal at New Brighton, Minnesota, to manufacture ammunition exclusively for the government during the war. Plaintiff, a copartnership, is a subcontractor which on or about August 28, 1944, entered into a written agreement with defendant under which defendant agreed to furnish to plaintiff, and plaintiff agreed to repair and recondition, on a fixed-price basis, 200,000 ammunition boxes to be used by defendant for the boxing and storage of ammunition. On October 18, 1944, defendant gave formal notice to plaintiff that the repair operation was terminated and that no additional boxes would be sent to plaintiff for repair after that date. At that time, approximately 186,000 boxes had been delivered to plaintiff for repair, but only 93,080 boxes had been accepted by defendant as repaired. Plaintiff seeks to recover $41,769.96 as the reasonable value of services rendered and materials supplied between October 7 and November 22, 1944, in the repair and recon *150 ditioning of ammunition boxes. Defendant admits a liability of $2,965.47, for which it has tendered payment. As to any further liability, defendant alleges in its answer:

“* * * Pursuant to the Contract Settlement Act, Title 41, U. S. Code, Secs. 101 to 125, the defendant requested of plaintiff that it prepare and file its claim with defendant for such claimed additional benefits on the forms provided for that purpose, and as provided by the joint termination regulations promulgated pursuant to the Contract Termination [Settlement] Act, but the plaintiff has refused and neglected to prepare and submit its claim so prepared, as that Act provides or as provided by Public Law 657, Chapter 864, 79th United States Congress, entitled ‘An Act to authorize relief in certain cases where work, supplies or services have been furnished to the Government under contracts during the war,’ which Act was approved on August 7, 1946.”

Defendant further alleges that by reason of plaintiff’s failure to comply with the provisions of the acts mentioned plaintiff had not exhausted the administrative remedies provided for the submission and adjustment of their claim, and that until such action was taken the court had no jurisdiction of the subject matter of the action. Plaintiff demurred to that defense, and, as stated, this appeal was taken from the order of the trial court overruling the demurrer.

The question presented is whether it is necessary for plaintiff subcontractor to first prepare and file a claim against defendant prime contractor on forms prescribed either by the Joint Termination Regulation issued pursuant to the Contract Settlement Act of 1944 or by U. S. Public Law 657 before the subcontractor can sue the prime contractor for services performed and materials supplied under the contract, when the contract between the parties does not contain any provision for its termination and it is terminated by the prime contractor before it is performed. Plaintiff claims that it is not necessary to file such claim, on the ground that there is no provision in the contract or in the Contract Settlement Act requiring it to file such claim with defendant before commencing suit.

*151 At the outset, it must be stated that an examination of the Contract Settlement Act and regulations issued thereunder discloses no express language which specifically requires a subcontractor to attempt to make a settlement with his prime contractor before bringing suit in a court of law. Granting that, the issue then resolves itself into whether there is such ambiguity in the language of the Contract Settlement Act as to make it reasonably susceptible of more than one interpretation. If there is such ambiguity, what, then, was the intent of congress in passing the act?

Plaintiff does not question the power of congress to enact a statute requiring contractors and subcontractors to comply with administrative procedures of the type involved in this act as a condition precedent to bringing an action in a court of law. That congress, under the war powers granted it under the federal constitution, may generally employ such measures as are necessary and appropriate to provide for the common defense and to wage war is established by clear authority. Hirabayashi v. United States, 320 U. S. 81, 63 S. Ct. 1375, 87 L. ed. 1774. This power is given by the constitution to meet the emergency of war and permits the harnessing of the entire energies of the people in a supreme cooperative effort to preserve the nation. Home Bldg. & Loan Assn. v. Blaisdell, 290 U. S. 398, 54 S. Ct. 231, 78 L. ed. 413, 88 A. L. R. 1481. Plaintiff concedes, therefore, that congress, under its war powers, could make, modify, and terminate war contracts, and that the Contract Settlement Act and the regulations issued thereunder, to the extent that they applied to the parties, became binding upon the respective parties. Plaintiff also concedes that a requirement that a war contractor file a formal claim for additional compensation under a terminated war contract, before commencement of suit is not an unreasonable requirement. Plaintiff contends only that the Contract Settlement Act was not intended by congress to impose such a condition precedent to the enforcement of its rights as a subcontractor against a prime contractor in a court of law. It is established law that the decisions of the United States Supreme Court on the construction of a federal statute are binding on state courts. Pakarinen v. Butler Bros. 218 *152 Minn. 496, 16 N. W. (2d) 769. In the case at bar, counsel have called our attention to no federal decisions directly governing this case, nor have we discovered any.

Our attention has been directed to Aircraft & Diesel Equip. Corp. v. Hirsch, 331 U. S. 752, 67 S. Ct. 1493, 91 L. ed. 1796, a case not involving the Contract Settlement Act, but closely analogous as to the legal principle involved. In that case, while proceedings were pending in the tax court for a redetermination of excessive profits determined by the Secretary of War and the War Contracts Price Adjustment Board to have been realized by a subcontractor on production of war equipment, the subcontractor sued in a district court for a declaratory judgment that the Renegotiation Acts were unconstitutional and for an injunction against further proceedings thereunder. The United States Supreme Court affirmed the lower court’s dismissal of the suit. The Supreme Court said (331 U. S. 767, 67 S. Ct. 1500, 91 L. ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jardine Mining Co. v. United States
88 F. Supp. 265 (Court of Claims, 1950)
Rumsey Mfg. Corp. v. U. S. Hoffman Machinery Corp.
88 F. Supp. 394 (W.D. New York, 1949)
Stevens v. Federal Cartridge Corp.
38 N.W.2d 154 (Supreme Court of Minnesota, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
32 N.W.2d 312, 226 Minn. 148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stevens-v-federal-cartridge-corp-minn-1948.