Grinnell Fire Protection Systems Co. v. Regents of the University of California

554 F. Supp. 495, 9 Educ. L. Rep. 126, 1982 U.S. Dist. LEXIS 9887
CourtDistrict Court, N.D. California
DecidedMarch 9, 1982
DocketC-81-3257 RFP
StatusPublished
Cited by5 cases

This text of 554 F. Supp. 495 (Grinnell Fire Protection Systems Co. v. Regents of the University of California) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grinnell Fire Protection Systems Co. v. Regents of the University of California, 554 F. Supp. 495, 9 Educ. L. Rep. 126, 1982 U.S. Dist. LEXIS 9887 (N.D. Cal. 1982).

Opinion

MEMORANDUM AND ORDER

PECKHAM, Chief Judge.

I. FACTS

This is an action filed on August 7, 1981 for breach of written contract and for money based upon diversity of citizenship within the terms of 28 U.S.C. § 1332. Plaintiff, Grinnell Fire Protection Systems Company, Inc. (“Grinnell”) is a Delaware corporation with its principal place of business in Rhode Island. Defendant, Regents of the University of California (“University”), is a public corporation organized pursuant to the laws of the State of California.

Plaintiff’s causes of action arise from a contract between the parties calling for Grinnell to install a fire sprinkler system in two buildings at Lawrence Berkeley Labs (“LBL”). The agreement is designated “Subcontract 480” in recognition of the fact that it is in furtherance of a “prime contract” between the University and the United States to conduct national security related energy research and development for the Department of Energy (“DOE”).

Plaintiff seeks relief in the sum of $138,-866.23 plus 18 percent interest from March 31, 1981. This sum comprises $86,830 for University delays in processing contractor submittals, $30,515 for additive work, and $20,321 withheld in partial satisfaction of liquidated damages assessed for Grinnell’s allegedly unexcused delay in completing the project.

II. THE MOTION TO DISMISS OR TO STAY ACTION

The University moves to dismiss or alternatively to stay the action against it on the ground that plaintiff Grinnell has not complied with the disputes resolution clause contained in the contract upon which the action is based. Article 8A (“Disputes”) is a standard dispute resolution clause found in government contracts and subcontracts. It provides for referral of fact disputes between Grinnell and the University to the University’s Department of Energy (DOE) Contracting Officer. 1

*497 Grinnell answers that Article 8A is unenforceable under the terms of Cal.Civ.Code § 1670, which governs arbitration in public agency construction contracts such as Subcontract 480. Section 1670 prohibits a party to a contract, or that party’s agent or employee, from arbitrating disputes arising under the contract. 2 Plaintiff alleges in the alternative that the arbitration provision is unconscionable and hence unenforceable under the terms of Graham v. Scissor Tail Inc., 28 Cal.3d 807, 824, 171 Cal.Rptr. 604, 623 P.2d 165 (1981).

The University has replied that section 1670 and the California unconscionability doctrine are both inapplicable because the contract in dispute is governed by federal rather than state law. It further argues that even under the applicable California law, the arbitration provision of the contract is valid and binding upon the plaintiff.

It is undisputed that if federal law applies and the arbitration is not otherwise infirm, the subcontractor is not entitled to seek relief in a district court without first exhausting the administrative remedies described in the clause. Crown Coat Front Co. v. United States, 386 U.S. 503, 508, 512, 87 S.Ct. 1177, 1180, 1182, 18 L.Ed.2d 256 (1967); Kyle Engineering Co. v. Kleppe, 600 F.2d 226, 230 (9th Cir.1979).

III. CHOICE OF LAW

Whether state or federal law applies to disputes brought under the court’s diversity jurisdiction depends upon the degree to which the outcome will affect the interests of the federal government. Bank of America National Trust & Savings v. Parnell, 352 U.S. 29, 77 S.Ct. 119, 1 L.Ed.2d 93 (1956); Pankow Const. Co. v. Advance Mortgage Corp., 618 F.2d 611, 613 (9th Cir.1980). The application of federal law is appropriate where “a uniform national rule” is necessary to further federal interests, Clearfield Trust Co. v. United States, 318 U.S. 363, 63 S.Ct. 573, 87 L.Ed. 838 (1943), or where “there is significant conflict between some federal policy or interest and the use of state law,” Miree v. DeKalb County, 433 U.S. 25, 29, 97 S.Ct. 2490, 2493, 53 L.Ed.2d 557 (1977), quoting Wallis v. Pan American Petroleum Corp., 384 U.S. 63, 68, 86 S.Ct. 1301, 1304, 16 L.Ed.2d 369 (1966).

In diversity cases involving contract disputes, the federal courts ordinarily apply state law. Reliance Finance Corp. v. Miller, 557 F.2d 674 (9th Cir.1977); C.R. Fredrick, Inc. v. Borg-Warner Corp., 552 F.2d 852 (9th Cir.1977). See generally Erie Railroad Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938). Similarly, state law normally controls the construction of contracts between government contractors and their subcontractors. American Pipe & Steel Corp. v. Firestone Tire & Rubber Co., 292 F.2d 640 (9th Cir.1961); Peter Kiewit Sons’ Co. v. Summit Construction Co., 422 F.2d 242 (8th Cir.1969); 1A Moore’s Federal Practice (1980) § 0.321. See also the Ninth Circuit Miller Act cases collected in United States v. Western Casualty & Surety Co., 498 F.2d 335, 338 n. 4 (9th Cir.1974). However, where the federal interest in the subcontract is sufficient, federal law will con *498 trol. American Pipe & Steel Corp. v. Firestone Tire & Rubber Co., supra at 644; United States v. Taylor, 333 F.2d 633 (5th Cir.1964), adhered to on rehg., 336 F.2d 149 (5th Cir.1964). 3

According to the defendant, the federal interest involved here is that of national defense and security.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vetro, Inc. v. Active Plumbing and Heating, Inc.
403 F. Supp. 2d 1033 (D. Colorado, 2005)
Linan-Faye Construction Co. v. Housing Authority
847 F. Supp. 1191 (D. New Jersey, 1994)
Whittaker Corp. v. Calspan Corp.
810 F. Supp. 457 (W.D. New York, 1992)
S & M Constructors, Inc. v. The Foley Company
959 F.2d 97 (Eighth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
554 F. Supp. 495, 9 Educ. L. Rep. 126, 1982 U.S. Dist. LEXIS 9887, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grinnell-fire-protection-systems-co-v-regents-of-the-university-of-cand-1982.