Advanced Materials, Inc. v. United States

46 Fed. Cl. 697, 2000 U.S. Claims LEXIS 88, 2000 WL 656214
CourtUnited States Court of Federal Claims
DecidedMay 17, 2000
DocketNo. 94-621C
StatusPublished
Cited by10 cases

This text of 46 Fed. Cl. 697 (Advanced Materials, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Materials, Inc. v. United States, 46 Fed. Cl. 697, 2000 U.S. Claims LEXIS 88, 2000 WL 656214 (uscfc 2000).

Opinion

OPINION

SMITH, Chief Judge.

This case is before the court on defendant’s Motion to Dismiss. Defendant’s motion asserts that plaintiffs claim should be dismissed pursuant to Rule 12(b)(1) or alternatively 12(b)(4) of the Rules of the United States Court of Federal Claims. After reviewing the briefs and hearing oral argument, the court hereby DENIES defendant’s motion with regard to plaintiffs termination for convenience claim, and GRANTS the motion on the breach of contract claim.

FACTS

On September 26, 1990, the U.S. Dept, of the Army awarded a cost plus fixed fee contract to Advanced Materials, Inc. (AMI) for the design and fabrication of 56 backpacks to keep troops cool under extreme temperatures. The army terminated the contract for convenience on June 15, 1992, effective May 27, 1992. On July 10, 1992, the termination contracting officer (TCO) told AMI that it could submit vouchers for allowable costs until November 30, 1992. On January 13, 1993, AMI submitted a settlement proposal to the TCO requesting $10,500.70, which AMI was paid on Jan. 27, 1993, subject to later audit.

Settlement of the termination was never officially completed as the two sides bickered over disposal of the remaining government property. On April 11,1994, AMI submitted a public voucher to the TCO for $18,002.00 for “the total costs and profits” due AMI for the contract. See Def.’s Mot. to Dismiss at 5. The TCO informed AMI that the voucher period had ended in November, 1992, and she would not accept any new vouchers.

[699]*699AMI submitted a “claim” by letter on June 27,1994 for the $18,002 previously mentioned plus additional legal and settlement costs for a total of $21,502. AMI presented the letter to the TCO as a “claim for equitable adjustment in the contract funding and price for this contract.” Def.’s Mot. to Dismiss at 5. AMI included a “certification” that the “claim is submitted pursuant to the Contract Disputes Act,” and requested a resolution of the claim within sixty days. See Def.’s Mot. to Dismiss at App. 43. The TCO advised AMI on July 18,1994 that the settlement amounts were not in dispute at that time. In a subsequent letter, the TCO noted the discrepancy between the between the amount in AMI’s “claim” versus its settlement proposal, and stated that because the contract had been terminated for convenience, not breached, all claims must be merged within the termination settlement proposal.

On September 6, 1994, AMI wrote the TCO and notified her that because she had not resolved the claim within sixty days, AMI deemed it denied. AMI also informed the TCO that if she did not produce a final decision within fifteen days from the date of the letter, AMI would file a claim in the United States Court of Federal Claims. AMI filed this action on September 21, 1994.

DISCUSSION

I. JURISDICTION

The United States, as sovereign, is immune from suit unless Congress specifically waives this immunity. See United States v. Testan, 424 U.S. 392, 399, 96 S.Ct. 948, 47 L.Ed.2d 114 (1976); Soriano v. United States, 352 U.S. 270, 276, 77 S.Ct. 269, 1 L.Ed.2d 306 (1957). Pursuant to the Tucker Act, this court has jurisdiction to “render judgment upon any claim against the United States founded ... upon ... any Act of Congress.” 28 U.S.C. § 1491 (1988). The Contract Disputes Act of 1978(CDA) governs the majority of suits brought in this court that are based upon express contracts and implied-in-fact contracts with the government. See 41 U.S.C. §§ 601-13 (1988). In actions brought pursuant to the CDA, Congress has placed conditions on the waiver of sovereign immunity. See SMS Data Products Group, Inc. v. United States, 19 Cl.Ct. 612, 614 (1990). For the court to have valid jurisdiction under the CDA, there must be: 1) a valid claim submitted to the contracting officer; and 2) a contracting officer’s (CO) final decision on that claim. See 41 U.S.C. § 605(a) (1988); James M. Ellett Construction Co. v. United States, 93 F.3d 1537, 1541-42 (Fed.Cir.1996); SMS Data Products Group, Inc., 19 Cl.Ct. at 614-15.

The contracting officer is required to issue a decision within “sixty days from his receipt of a written request from the contractor that a decision be rendered within that period.” 41 U.S.C. § 605(c)(1) (1988). If the contracting officer fails to issue a decision within the required period, the failure will be deemed a decision by the CO denying the claim and will authorize the commencement of an appeal as provided in the CDA. See 41 U.S.C. § 605(c)(5) (1988). Thus, the jurisdictional and RCFC 12(b)(1) motion turns on whether AMI submitted a valid claim to the CO. See Ellett, 93 F.3d at 1541-42.

II. STANDARD OF REVIEW

RCFC 12(b)(1) authorizes dismissal of a complaint when the court lacks jurisdiction over the subject matter, and RCFC 12(b)(4) authorizes dismissal if, assuming the truth of all allegations, the complaint fails to state a claim upon which relief may be granted as a matter of law. In ruling upon a motion to dismiss, the court must accept as true the complaint’s allegations and construe the facts in the light most favorable to the plaintiff. See Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 40 L.Ed.2d 90 (1974). Dismissal is appropriate, however, whenever “it appears beyond a reasonable doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Id. (quoting Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957)). Dismissal pursuant to RCFC 12(b)(1) is appropriate whenever the court is lacking subject matter jurisdiction.

III. TERMINATION FOR CONVENIENCE

A. Did AMI file a valid “claim” under the [700]*700Federal Acquisition Regulation1 (FAR) with the contracting officer?

Defendant contends that AMI’s letter to the CO did not meet the requirements necessary to constitute a valid “claim” under the Federal Acquisition Regulation. Under the FAR, as interpreted by the Court of Appeals for the Federal Circuit in Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575 (Fed.Cir.1995) (in banc), a non-routine submission must contain three elements: 1) a written demand; 2) seeking as a matter of right; 3) a sum certain. Ellett and Reflectone

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emiabata v. United States
Federal Claims, 2017
Seh Ahn Lee v. United States
127 Fed. Cl. 734 (Federal Claims, 2016)
Armour of America v. United States
69 Fed. Cl. 587 (Federal Claims, 2006)
Kiewit Construction Co. v. United States
56 Fed. Cl. 414 (Federal Claims, 2003)
Atlanta Appraisal Services, Inc. v. United States
54 Fed. Cl. 51 (Federal Claims, 2002)
Advanced Materials, Inc. v. United States
54 Fed. Cl. 207 (Federal Claims, 2002)
Made in the USA Foundation v. United States
51 Fed. Cl. 252 (Federal Claims, 2001)
J. Cooper & Associates, Inc. v. United States
47 Fed. Cl. 280 (Federal Claims, 2000)
Libertatia Associates, Inc. v. United States
46 Fed. Cl. 702 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
46 Fed. Cl. 697, 2000 U.S. Claims LEXIS 88, 2000 WL 656214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-materials-inc-v-united-states-uscfc-2000.