Advanced Materials, Inc. v. United States

54 Fed. Cl. 207, 2002 U.S. Claims LEXIS 291, 2002 WL 31441208
CourtUnited States Court of Federal Claims
DecidedSeptember 6, 2002
DocketNo. 94-621C
StatusPublished
Cited by2 cases

This text of 54 Fed. Cl. 207 (Advanced Materials, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Materials, Inc. v. United States, 54 Fed. Cl. 207, 2002 U.S. Claims LEXIS 291, 2002 WL 31441208 (uscfc 2002).

Opinion

OPINION

SMITH, Senior Judge.

I. Introduction

Plaintiff Advanced Materials, Inc. (the “plaintiff’ or “AMI”) filed a complaint, since amended, against the United States (the “defendant”) alleging that the defendant owes it $46,960.22 for costs related to a contract with the U.S. Army (“Army”). On May 17, 2000, the court granted defendant’s motion to dismiss in part relating to a breach of contract claim. Advanced Materials, Inc. v. United States, 46 Fed.Cl. 697 (2000). This opinion comes after a 4-day trial was held in New Orleans, Louisiana, on the remaining termination for convenience claim and after a thorough consideration of the briefs. Because the plaintiff has failed to meet its burden of proof that it is entitled to recover any costs, the court finds for the defendant for the reasons enumerated below. The clerk is directed to enter final judgment pursuant to this opinion.

II. FACTS2

On September 26, 1990, the U.S. Department of the Army awarded a cost plus fixed [209]*209fee contract, Contract No. DAAA60-90-C0111, to AMI for the design and fabrication of 56 backpacks to keep troops cool under extreme temperatures. The Army terminated the contract for convenience by letter on June 10, 1992, effective May 27, 1992. On July 10, 1992, the termination contracting officer (TCO) told AMI that it could submit vouchers for allowable costs until November 30, 1992. On January 13, 1993, AMI submitted a settlement proposal to the TCO requesting $10,500.70, which AMI was paid on Jan. 27, 1993, subject to later audit. An audit of AMI performed by the Defense Contract Audit Agency (“DCAA”) for Fiscal Years 1991 and 1992 resulted in a referral to the Defense Criminal Investigative Service (“DCIS”) in 1993 for a fraud investigation. A summary report dated May 15, 1996 from the DCIS indicated that they were planning to close the investigation in mid-1996.

Settlement of the termination was never officially completed as the two sides bickered over disposal of the remaining government property. On April 11,1994, AMI submitted a public voucher to the TCO for $18,002.00 for “the total costs and profits” due AMI for the contract. The TCO informed AMI that the voucher period had ended in November 1992, and she would not accept any new vouchers.

AMI submitted a “claim” by letter on June 27, 1994, for the $18,002 previously mentioned plus $3,500 in additional legal and settlement costs for a total of $21,502. AMI presented the letter to the TCO as a “claim for equitable adjustment in the contract funding and price for this contract.” AMI included a “certification” that the “claim is submitted pursuant to the Contract Disputes Act,” and requested a resolution of the claim within sixty days. The TCO advised AMI on July 18, 1994, that the settlement amounts were not in dispute at that time. In a subsequent letter, the TCO noted the discrepancy between the amount in AMI’s “claim” versus its settlement proposal, and stated that because the contract had been terminated for convenience, not breached, all claims must be merged within the termination settlement proposal.

On September 6, 1994, AMI wrote the TCO and notified her that because she had not resolved the claim within sixty days, AMI deemed it denied. AMI also informed the TCO that if she did not produce a final decision within fifteen days from the date of the letter, AMI would file a claim in the United States Court of Federal Claims. AMI filed this action on September 21, 1994. At trial, the parties stipulated that the government had paid AMI a total of $270,031 for the contract.

In June 1996, the court temporarily stayed this case while AMI litigated a companion case before the Armed Services Board of Contract Appeals. The litigation resumed in this court in June 1998.

III. DISCUSSION

1. Jurisdiction

In a previous ruling on defendant’s motion to dismiss, the court found that the plaintiff had submitted a valid claim to the contracting officer related to its termination for convenience and that the failure of the contracting officer to respond within 60 days constituted a denial. Advanced Materials, Inc. v. United States, 46 Fed.Cl. 697 (2000). Thus, under the Contract Disputes Act, plaintiffs claim is properly before the court. See 41 U.S.C. § 601 et seq. (1987 & 2002 Supp.)

2. Standard of Review

Plaintiff has the burden of proving its allowable costs by a preponderance of the evidence. See Ryan-Walsh, Inc. v. United States, 37 Fed.Cl. 639 (1997) (citing Delco Elecs. Corp. v. United States, 17 Cl.Ct. 302, 319 (1989)). As this court has articulated previously, “[Wjhen damages are sought, the contractor must prove the amount of its damages ‘with sufficient certainty so that the determination of damages will be more then mere speculation.’ ” Malissa Co., Inc. v. United States, 18 Cl.Ct. 672, 674, quoting Willems Indus., Inc. v. United States, 155 Ct.Cl. 360, 376, 295 F.2d 822 (1961), cert. denied, 370 U.S. 903, 82 S.Ct. 1249, 8 L.Ed.2d 400 (1962). In a case such as this, where plaintiff seeks costs which have been [210]*210disallowed by a government auditor, it is incumbent on the plaintiff to produce probative evidence as to the allowability of the costs in order to recover. See Roberts v. United States, 174 Ct.Cl. 940, 949, 357 F.2d 938 (1966).

3. Termination for Convenience

a. Has AMI Been Paid All that It Is Due?

A threshold issue for the court to consider is the government’s contention that AMI has been fully paid on the contract. During contract performance and the settlement phase, AMI submitted 24 vouchers to the government for reimbursement for costs associated with this contract. The final voucher that was submitted, voucher number 24, indicates that AMI was paid $10,500 per its termination settlement proposal for a grand total of $270,817.26. The parties stipulated at the beginning of trial that AMI was paid just less than that amount, namely $270,013.3 The government contends that these 24 vouchers are conclusive proof that AMI has been fully paid under the contract according to its own requests and that no further funds are due.

Plaintiff disputes the government’s contention alleging that the government has yet to pay upwards of $38,000 to AMI. Although plaintiffs amended complaint seeks $46,960.22, the actual recovery figure has been a moving target. Plaintiff conceded at trial that the cost limitation clause in the contract of $308,000 caps any recovery at roughly $38,000. Tr. Trans, at 535. In addition, plaintiff further testified that his recovery was limited to $18,002 as per AMI’s submission via voucher 24. Tr. Trans, at 557. Plaintiff pointed to the bottom of voucher 24 where it states that the voucher seeks $18,002 for “current G & A plus profit due AMI for years ’90, ’91, and ’92.” 4 Def. Ex 28.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D-STAR Engineering Corp.
Armed Services Board of Contract Appeals, 2025
Valte v. United States
Federal Claims, 2021

Cite This Page — Counsel Stack

Bluebook (online)
54 Fed. Cl. 207, 2002 U.S. Claims LEXIS 291, 2002 WL 31441208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-materials-inc-v-united-states-uscfc-2002.