Axxon International, LLC

CourtArmed Services Board of Contract Appeals
DecidedMarch 24, 2020
DocketASBCA No. 61549
StatusPublished

This text of Axxon International, LLC (Axxon International, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Axxon International, LLC, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Axxon International, LLC ) ASBCA No. 61549 ) Under Contract No. W912P5-16-C-0002 )

APPEARANCE FOR THE APPELLANT: Eric Lee, Esq. Lee & Amtzis, P.L. Boca Raton, FL

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Bonnie B. Jagoditz, Esq. Engineer Trial Attorney U.S. Army Engineer District, Nashville

OPINION BY ADMINISTRATIVE JUDGE MELNICK

This appeal arises out of the termination for cause of a contract between Axxon International, LLC (Axxon) and the United States Army Corps of Engineers (Corps) for pump repairs to Wheeler Lock in Florence, Alabama. We have jurisdiction pursuant to the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109. The parties have elected to proceed solely upon the record submitted pursuant to Board Rule 11. We deny the appeal.

FINDINGS OF FACT

1. On May 24, 2016, the Corps awarded Axxon the above-captioned firm fixed-price commercial item service contract (contract) for the replacement of “wash down” and “gate spray” pumps on Wheeler Lock. The work to be performed included the removal of existing equipment and materials and the installation of new equipment, including a new control system. The contract included six line items (CLINs) for demolition, pump platforms, pumps, pipes and fittings, valves and strainers, and electrical equipment and conduit. (R4, tab 4 at 1-5) The delivery date was March 23, 2017 (id. at 19).

2. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.212-4, CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS (MAY 2015) (R4, tab 4 at 20). Subparagraph (m), which addresses termination for cause, reads as follows: The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

FAR 52.212-4(m)

3. The contract also incorporated by reference FAR 52.232-40, PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (DEC 2013) (R4, tab 4 at 20). 1 Subparagraph (a) of that clause states in part the following:

Upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor.

FAR 52.232-40(a)

1 This clause first appeared in the FAR as a result of a series of Office of Management and Budget (OMB) memoranda specifying that agencies should accelerate payments to prime contractors so that they could promptly pay their small business subcontractors. See FAR; Accelerated Payments to Small Business Subcontractors, 78 Fed. Reg. 70477-01 (Nov. 25, 2013). Originally intended to be a temporary policy, it was extended several times through subsequent OMB memoranda. See OMB Memorandum M-17-13 (Jan. 11, 2017). It expired on December 31, 2017, id., and has not been renewed since then.

2 4. By purchase order dated May 26, 2016, Axxon entered into an agreement with B.H. Craig Construction Company (Craig) to perform the work contemplated by the contract for a price of $358,400 (later increased to $365,400). 2 The purchase order divided the work into six CLINs mirroring the CLINs contained in Axxon’s contract with the Corps. (R4, tab 15 at 9) Under a heading entitled “Terms,” the purchase order has an entry stating “31 Days from Government Acceptance” (id.). The purchase order also includes the following paragraph:

By your signature herein below, you hereby warrant and represent that you acknowledge Axxon International, LLC as the prime contractor with respect to any and all communication with the U.S. Government and furthermore that you, as a subcontractor to Axxon, will not interact with any personnel representing the Federal Government regarding this contract. All communications will be conducted exclusively with Axxon International, LLC unless, and only in the event, that Axxon authorizes such other communication to you in writing.

(Id.)

5. By email dated August 12, 2016, Axxon advised the Corps that it projected completion of all CLINs by November 17, 2016. It also requested a contract modification for progress payments “under either, FAR 52.232-14[,] Notice of Availability of Progress Payments Exclusively for Small Business Concerns [,] FAR 52.232-16[,] Progress Payments, [o]r other FAR clause as may be appropriate.” (R4, tab 64) Neither of those clauses appear in the contract, either in full text or incorporated by reference (R4, tab 4 at 20-29), and there is no evidence in the record that the Corps ever issued the requested contract modification. Nevertheless, at some point the Corps agreed to make progress payments to Axxon (app. supp. R4, tab 60 at 10-12).

6. By email dated September 9, 2016, Axxon submitted an invoice to the Corps in the amount of $116,400, which it described as representing “20% of contract value” for CLINs 0002 through 0006 “based upon our measurable progress timeline to early contract completion, plus material costs and tooling and technical work thus far performed” (app. supp. R4, tab 50 at 1). Axxon subsequently submitted documentation the Corps had

2 We were not provided with a copy of the original purchase order between Axxon and Craig. Instead, we received what appears to be a version of the original purchase order, modified to reflect the increased value. This version of the purchase order was executed on August 3, 2016. (R4, tab 15 at 9-10) As neither party has objected to the authenticity of this document as reflecting the original agreement between Axxon and Craig, we will accept it as such.

3 requested for this payment, and stated that “[t]his will be our only progress payment request on this contract, with the remaining balance to be invoiced only after turn-key acceptance of the entire project . . .” (app. supp. R4, tab 52 at 1-2). Notwithstanding that representation, Axxon submitted four additional invoices for progress payments between October 2016 and March 2017 (app. supp. R4, tabs 43-45, 51).

7. By March 8, 2017, the Corps had paid all five invoices submitted by Axxon, representing complete payment on all CLINs but CLIN 0003, for which $14,100 remained unpaid (app. supp. R4, tabs 44 at 3, 60 at 17-19, 58; ex. A at 6-7; R4 tab 72). Under CLIN 0003, the Corps was still awaiting receipt of as-built and redlined drawings. In addition, final testing to allow for acceptance of the project as a fully functional system had yet to occur. (R4, tab 60 at 19-20)

8. Meanwhile, during the course of performance the parties realized that a number of system components not included in the contract’s original specifications were nonfunctional. Without replacement, the contract’s verification and testing requirements could not be completed. (R4, tab 6; app. supp. R4, tab 60 at 23-24) The Corps, therefore, decided to modify the contract to add CLIN 0007, which required that the nonfunctional system components be removed and replaced with contractor-supplied materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Axxon International, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/axxon-international-llc-asbca-2020.