Pinewood Inc. fka PNI Incorporation

CourtArmed Services Board of Contract Appeals
DecidedApril 21, 2025
Docket63588, 63686
StatusPublished

This text of Pinewood Inc. fka PNI Incorporation (Pinewood Inc. fka PNI Incorporation) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pinewood Inc. fka PNI Incorporation, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Pinewood Inc. fka PNI Incorporation ) ASBCA Nos. 63588, 63686 ) Under Contract No. W912UM-22-C-0003 )

APPEARANCE FOR THE APPELLANT: Yong Eui Song, Esq. Central IP & Law Seoul, Korea

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Robert M. Sundberg, Esq SoCheung Lee, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Far East Seoul, Korea

OPINION BY ADMINISTRATIVE JUDGE STINSON

Appellant Pinewood Inc., formerly known as PNI INC, 1 appeals (1) a contracting officer (CO) final decision dated February 17, 2023, terminating PNI’s contract for default and (2) a CO final decision dated March 6, 2024, denying PNI’s May 30, 2023, claim seeking ₩399,734,850 (Korean Won) ($377,108.35 USD) for costs incurred prior to termination. We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. The parties agreed to submit these appeals on the record without a hearing pursuant to Board Rule 11.

FINDINGS OF FACT (FOF)

With their initial briefs, the parties submitted a Joint Statement of Stipulated Facts (JSSF). Our findings of fact, as set forth below, rely in part upon the parties’ JSSF, as well as documents contained in the parties’ respective Rule 4 submissions. 2

1 The contract was awarded to PNI INC and by Modification No. P00002 the contractor’s name was changed from “PNI INC to PINEWOOD INC” (R4, tab 6 at 3). For simplicity’s sake we refer herein to appellant as PNI. 2 The government submitted an initial and supplemental Rule 4 file, which we refer to as R4, tabs 1-144. Appellant submitted an initial and supplemental Rule 4 file, which we refer to as app. supp R4, tabs 1-48. Contract Award

1. On July 13, 2022, PNI entered fixed price Contract No. W912UM-22-C0003 with the U.S. Army Corps of Engineers (USACE), Far East District (FED), in the amount of ₩1,851,555,146 (USD $1,746,750.15), for repair of the Contingency Fuel Delivery System on Osan Air Base, Republic of Korea (R4, tab 1 at 1-3, 6, tab 5 at 1; JSSF ¶¶ 1-2, 9).

Teaming Agreement Between PNI and Two Track, Inc.

2. Prior to contract award, PNI entered a teaming agreement with Two Track, Inc. (Two Track), whereby Two Track would perform work on the project as PNI’s subcontractor (R4, tab 7 at 1). PNI and Two Track agreed “to combine their respective capabilities in a joint effort to submit said proposal for the Program and to complete the work required by any work statement in any contract . . .” (id.).

Project Description and Contract Line Items

3. Contract specification paragraph 1.2.1, Project Description, required “construction of an approximately 330 meter long rail spur, shift of approximately 180 meters of the existing rail main track, realignment of approximately 80 meters of existing reinforced concrete box culvert, relocation of impacted utilities, and incidental related work” (R4, tab 5 at 13; JSSF ¶ 5).

4. The contract includes six Contract Line Item Numbers (CLIN): 0001 Construct Rail Spur & Construct Site Preparation & Improvements (New Construction Work), 0002 Shift Existing Track & Site Work (Maintenance and Repair Work), 0003 Repair Drainage Facilities (Maintenance and Repair Work), 0004 Repair Electrical and Communications System (Maintenance and Repair Work), 0005 Repair Site Utilities (Maintenance and Repair Work), and 0006 Removals (Maintenance and Repair Work) (R4, tab 1 at 4).

FAR Provisions Incorporated into the Contract by Full Text or by Reference

5. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.236-15, SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984), which required the contractor, within five days of commencing work on the project, to prepare and submit to the CO for approval a construction schedule setting forth the order “in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient

2 features of the work” (R4, tab 1 at 6); 3 FAR 52.236-15(a). FAR 52.236-15(b) specified that, if in the opinion of the CO the contractor fell behind the approved schedule, the contractor shall take steps necessary to improve its progress, including any steps required by the CO, such as increasing the number of shifts, overtime operations, days of work, as well as submission of supplementary schedules to demonstrate how the approved rate of progress will be regained. FAR 52.236-15(c) specified that the contractor’s failure to comply with the CO’s requirements shall be grounds (1) for determination by the CO that the contractor is not sufficiently prosecuting work necessary to ensure timely completion of the contract, and (2) a decision terminating the contractor’s right to proceed with the work, in accordance with the default terms of the contract.

6. The contract incorporated by reference FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014), which provided, in part, under the subtitle, “Retainage,” that “if satisfactory progress has not been made, the CO may retain a maximum of 10% of the amount of the payment until satisfactory progress is achieved” (R4, tab 1 at 6); FAR 52.232-5(e).

7. The contract incorporated by reference FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (default clause), which granted the government the authority to terminate the contractor’s right to proceed if the contractor failed to prosecute the work with the diligence necessary to insure its completion within the time specified in the contract, as well as the right to “take possession of and use any materials, appliances, and plant on the work site necessary for completing the work” (R4, tab 1 at 6); FAR 52.249-10(a). The default clause also provided that “[i]f, after termination of the Contractor’s right to proceed, it is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government.” FAR 52.249-10(c).

8. The contract incorporated by full text FAR 52.211-12, LIQUIDATED DAMAGES -- CONSTRUCTION (SEP 2000), which provided, in part, “[i]f the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause” (R4, tab 1 at 7-8); FAR 52.211-12(b). The liquidated damages rate was ₩713,000 per calendar day” (R4, tab 1 at 8).

3 Some documents in the government's Rule 4 file are stamped with Bates numbers beginning with zeros. We cite herein to those Bates numbers but omit the initial unnecessary zeros. 3 9. The contract incorporated by reference FAR 52.236-13 Alt I, ACCIDENT PREVENTION (NOV 1991) – Alternate I (R4, tab 1 at 6). In accordance with FAR 52.236-13, the contract also incorporated by reference the USACE Safety and Health Requirements Manual (EM) 385-1-1 (R4, tab 1 at 21, tab 5 at 61) (2014 Safety and Health Requirements Manual (EM) 385-1-1). Specification Section 01 30 00, ADMINISTRATIVE REQUIREMENTS, likewise references EM 385-1-1 (R4, tab 5 at 19). EM 385-1-1 contains two sections addressing temporary power plans: Section 4, Temporary Facilities, and Section 11, Electrical (R4, tab 142 at 68, 232).

10. EM 385-1-1, Section 4, paragraph 04.A.01, states that plans for the layout of temporary construction buildings shall be submitted to and approved by the government designated authority (R4, tab 142 at 68).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Pinewood Inc. fka PNI Incorporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pinewood-inc-fka-pni-incorporation-asbca-2025.