Universal Power Corp. v. United States

112 Ct. Cl. 97, 1948 U.S. Ct. Cl. LEXIS 85, 1948 WL 5014
CourtUnited States Court of Claims
DecidedOctober 4, 1948
DocketNo. 46258
StatusPublished
Cited by4 cases

This text of 112 Ct. Cl. 97 (Universal Power Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Power Corp. v. United States, 112 Ct. Cl. 97, 1948 U.S. Ct. Cl. LEXIS 85, 1948 WL 5014 (cc 1948).

Opinion

Jones, Chief Judge,

delivered the opinion of the court:

This is a suit to recover loss and damages which plaintiff alleges were caused by the cancellation of a contract which defendant had made for the purchase of two' generators from the plaintiff.

Plaintiff learned through trade channels that defendant desired to purchase generators for use in connection with the Canol project in Alberta, Canada. Plaintiff, who was engaged in special engineering, sales, distribution, and manufacturing of electrical equipment, after some preliminary telegrams of inquiry, on September 8, 1943, sent to defendant’s representative in Edmonton, Alberta, Canada, the following telegram:

Ke phone order HDQ 2987. Have located Buda 468 Diesel ample capacity §0 KW 62.5 KYA set 1800 speed with overload generator on hand 120/208 Wye price 6,800 dollars. This engine trifle small for previously proposed 1,200 speed generator. Have located Buda 691 Diesel horsepower scant for 900 speed 75 KW 93.8 KYA stock 575 volt generator previously proposed with step down transformer for 120/208 wye but can rerate generator 65 KW 81 KYA to match engine capacity price 12,400 dollars. Also located Buda gasoline engine • of ample horsepower to operate same 75 KW 93.8 generator 900 speed full capacity with overload price 9,900 dollars. All prices U. S. dollars f. o. b. Newark, New Jersey, standard commercial type machines including certified factory tests. No U. S. engineer inspection tests or specifications to apply. Shipment 30 days AA-1. Telegraph instructions to avoid losing these engines.

On the same date defendant’s'representative sent plaintiff the following telegram in reply:

Keurtel 6 [sic] September referring purchase order HDQ 2987 44 bid accepted on 1 only 50 KW generator driven by Buda 468 Diesel complete with necessary controls at six thousand eight hundred dollars and 1 only 691 Buda Diesel driven generator 900 EPM with genera[117]*117tor rerated 65 KW to match engine capacity complete at twelve thousand four hundred dollars all FOB plant Newark, New Jersey. Confirming purchase order and AA-1 preference rating certificate will be forwarded promptly. Government blading will be furnished by district engineer office, New York District. Certified copies shop test acceptable.

Belying upon the telegram that confirming purchase order and AA-1 preference certificate would be furnished, plaintiff placed its written order for the two generator sets with Electric Arc, Inc., its subcontractor.

By letter of September 8, 1943, plaintiff submitted its' proposal for furnishing two Diesel-driven generator sets, confirming its telegraphic proposal.

By letter dated September 14, 1943, defendant forwarded to plaintiff at its principal office in Cleveland, Ohio, a contract order bearing date of September 7, 1943, with filled-in acceptance date of September 16, 1943. Delivery within thirty days was specified. The order contained certain provisions, the following being material to the present inquiry:

10. DELAYS — DAMAGES.;—If the Contractor re- . fuses or fails to perform this contract within the time specified, or any extension thereof, the Government may, by written notice, terminate the right of the Contractor to proceed with, deliveries or with such part or parts • thereof as to which there has been delay, and may hold the Contractor liable for any damage caused the Government by reason of such termination. The right of the Contractor to proceed with the performance of this contract shall not be terminated under this General Provision 10 if the delay is due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including without being limited to, any preference, priority, or allocation order issued by the Government or any other act of the Government.
11.. DISPUTES. — Except as otherwise specifically provided in this contract, all disputes concerning questions of fact which may arise under this contract, and which, are not disposed of by mutual agreement, shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail a copy, thereof to the Contractor. Within 30 days from said mailing the Contractor may appeal to the Secretary of War, whose decision or that of his designated representative, rep[118]*118resentatives, or board shall be final and conclusive upon the parties hereto. Pending decision of a dispute hereunder the Contractor shall diligently proceed with the performance of this contract.

On October 5, 1948, the plaintiff accepted the contract.

The purchase order did not require the contractor to give the Government any notice of delay, nor was there any penalty provision calling for the payment of liquidated damages, which are usual conditions in standard Government contracts. The evidence shows that generator sets such as called for by the contract were difficult to obtain.

Manufacturers and suppliers were subject to defendant’s allocation and priority system. The top priority symbol was known as AAA. Below this rating were classifications known as AA-1, AA-2, etc. It was required that preference be given to the higher rating and where two orders were of the same rating the allocations were usually in the order of the respective dates of the contracts.

The details are set out in the findings and will not be repeated here.

The subcontractor operated its plant seven days a week from 8 a. m. to 9:30 p. m., except on Fridays the work terminated at 5 p. m., and on Saturdays and Sundays at 4:30 p. m.

It is manifest that the shortage of materials and the priority system caused the delay in the delivery of the generators. A change in priority from AA-1 to AAA on an order given by the Coast Guard, which was being filled at the same time, caused further delay. There were also other orders given by the defendant to plaintiff and the subcontractor for other generators and electrical equipment.

A dispute arose as to certain additional equipment, the plaintiff contending that its contract did not call for the extra equipment and the defendant claiming that plaintiff was not providing a circuit breaker, frequency meter, tachometer, housing, switch panel, safety shutoff, or fuel tanks. The plaintiff agreed to furnish a circuit breaker and switch panel. It also indicated a willingness to furnish the other items, provided they were classified as extras and paid for on tha1 basis.

[119]*119On November 24, 1943, defendant’s procurement officer, Gordon T. White, advised plaintiff by telephone that its contract was being cancelled because plaintiff had failed to deliver the two units within the period specified by the contract. Plaintiff protested vigorously, but the procurement officer insisted that the contract was being cancelled.

Notice of cancellation was confirmed on the same date by telegram to plaintiff signed by the division engineer at Edmonton, but sent by the contracting officer. Plaintiff replied by telegram dated November 27, 1943, requesting postponement of formal documentation until factual basis of cancellation could be established, and calling attention to Clause 10 of the contract, and again, offering to supply the extras as extras and advising that the machines were ready for shipment according to contract and quotations.. No action was taken by the contracting officer upon plaintiff’s protest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Poloron Products, Inc. v. United States
116 F. Supp. 588 (Court of Claims, 1953)
CLIMATIC RAINWEAR, CO. v. United States
88 F. Supp. 415 (Court of Claims, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
112 Ct. Cl. 97, 1948 U.S. Ct. Cl. LEXIS 85, 1948 WL 5014, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-power-corp-v-united-states-cc-1948.