Cross Petroleum, Inc. v. United States

57 Fed. Cl. 34, 2003 U.S. Claims LEXIS 154, 2003 WL 21513057
CourtUnited States Court of Federal Claims
DecidedJune 20, 2003
DocketNo. 97-251C
StatusPublished

This text of 57 Fed. Cl. 34 (Cross Petroleum, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cross Petroleum, Inc. v. United States, 57 Fed. Cl. 34, 2003 U.S. Claims LEXIS 154, 2003 WL 21513057 (uscfc 2003).

Opinion

OPINION

MILLER, Judge.

This case comes for decision after trial on the reasonableness of the Government’s remediation of a national park contaminated by a gasoline spill. The wrongfully terminated contractor contends that the Government’s cleanup efforts exceeded what the contractor would have done if it had been afforded the opportunity to clear the site of contaminants. Defendant claims that its remediation course, still ongoing at the time of trial, was commensurate with the industry standard.

In an earlier trial, the court found that the Government had wrongfully terminated plaintiff’s cleanup efforts which were collateral to the performance of its fuel-delivery contract. The parties’ commitment to settlement halted the trial before defendant put on its case to justify the damages claimed. Settlement collapsed, trial resumed, and the proofs underscored the following anomaly: Plaintiff, as the wrongfully terminated contractor, is in precisely the same position as it would have been had the termination been upheld. In other words, regardless of the circumstances of its termination, plaintiff is still the party responsible for the spill, and the only question is whether the Government’s costs in assuming plaintiffs site cleanup are reasonable.

BACKGROUND

A gasoline spill that occurred over ten years ago at the United States Forest Service (the “Forest Service”) facility in the Klamath National Forest, California, known as the Oak Knoll Work Center (“Oak Knoll”), was the genesis of this litigation.

In quite possibly the most disastrous first — and, presumably, last — day on the job, an employee from Cross Petroleum, Inc. (“plaintiff’), on April 30, 1993, pumped 2,000 gallons of unleaded gasoline into a monitoring well that he mistook for an underground storage tank. The gasoline seeped through the monitoring well, which was not designed to hold liquid, and contaminated the subsurface.

Plaintiff accepted responsibility for the spill as a matter of fact, but the parties disputed responsibility for the remediation. In Cross Petroleum, Inc. v. United States, 51 Fed.Cl. 549 (2002), the court found that the indemnity provision of plaintiffs contract with the Forest Service for the delivery of diesel fuel also applied to the delivery of unleaded gasoline. The case proceeded to trial in August 2002. When settlement was not consummated, the court issued an opinion that 1) concluded that the Forest Service [36]*36■wrongfully terminated plaintiffs remediation efforts and 2) established the burdens of proof that would govern the subsequent damages proceeding. See Cross Petroleum, Inc. v. United States, 54 Fed.Cl. 317 (2002).

Under traditional termination principles, the Forest Service, owing to its improper termination of plaintiff, would bear the cost of remediation. See J.D. Hedin Constr. Co. v. United States, 187 Ct.Cl. 45, 408 F.2d 424, 431 (1969) (“Plaintiff is, of course, entitled to be liberated from the negative consequences of the [improper] default termination----”). However, the traditional paradigm made little sense when applied to the case at bar, as the party responsible for the pollution would be absolved of financing the remediation. After a search for binding precedent addressing the unique situation at hand yielded no case on point, the court, at defendant’s behest, consulted the liability rubric in the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, 42 U.S.C. §§ 9601-9675 (2002) (“CERCLA”), which allocates responsibility for the cost of cleanup financed by the Government to the party responsible for the pollution. Under CERCLA if the Government establishes that it expended costs to remedy a release or threatened release of hazardous substances and that defendants are the responsible parties, defendants then have the burden of proving that the costs incurred were “inconsistent with the national contingency plan,” which is designed to ensure cost-effective remediation efforts. See 42 U.S.C. § 9607(a)(l)-(4)(A); 40 C.F.R. § 300.1 (2002); 40 C.F.R. § 300.3(b).

Defendant sought to enforce plaintiffs responsibility relying on Minnesota v. Kalman W. Abrams Metals, Inc., 155 F.3d 1019 (8th Cir.1998). Defendants in Abrams Metals contested liability for the cost of an environmental cleanup when the state of Minnesota, in violation of CERCLA, failed to afford them an opportunity to comment on or to undertake cleanup activities at their own expense. The Eighth Circuit refused to wipe the slate clean for the cleanup merely because “the environmental constable blundered,” but also balked at rewarding the state’s “wasteful agency action.” 155 F.3d at 1026. The court struck a balance between the two wrongs, holding that the state could not recover costs for aspects of the cleanup that defendants proved that they could have accomplished more cost effectively. Id.

The scenario in Abrams Metals parallels that of the parties at hand, insofar as the responsible parties in both cases “were precluded from meeting their obligations under the contract and object to the costly manner in which that obligation ultimately was discharged by others. The Government entities in both cases persuasively argue that technical defects in the process by which a cleanup is conducted should not absolve a hable party of the entire cost of remediation.” Cross, 54 Fed.Cl. at 329.

Persuaded that plaintiff must bear responsibility for the cleanup, the court determined that the following burdens of proof would apply to the damages phase of the proceedings: Defendant would bear the initial burden of justifying its remediation costs, after which the burden would shift to plaintiff to show that “the costs were unreasonable, i.e., that plaintiff could have accomplished the cleanup more cost effectively.” Cross, 54 Fed.Cl. at 330, ! 3.1 However, the court rejected defendant’s contention that remediation actions approved by the North Coast Regional Water Quality Control Board (the “Water Board” or the “Board”) are presumptively reasonable, as that organization’s approval does not signify that the most cost-effective means were used to complete a remediation. Id. at 329-30.

The court announced that it would not apply CERCLA in the case at bar (as the Court of Federal Claims lacks jurisdiction to do so) and advised the parties, that, if they wished to resolve damages in a pending district court case, they could try the issue in [37]*37their preferred forum.2 Cross, 54 Fed.Cl. at 330 n. 4. Defendant reiterated its willingness to remain in the Court of Federal Claims, but plaintiff reserved its objection to this forum. See Pl.’s Br. filed Dec. 30, 2002, at 4 n. 4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Royal Indemnity Co. v. United States
313 U.S. 289 (Supreme Court, 1941)
Minnesota v. Kalman W. Abrams Metals, Inc.
155 F.3d 1019 (Eighth Circuit, 1998)
Cross Petroleum v. United States
51 Fed. Cl. 549 (Federal Claims, 2002)
Cross Petroleum, Inc. v. United States
54 Fed. Cl. 317 (Federal Claims, 2002)
General Electric Co., Aerospace Group v. United States
36 Cont. Cas. Fed. 75,899 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
57 Fed. Cl. 34, 2003 U.S. Claims LEXIS 154, 2003 WL 21513057, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cross-petroleum-inc-v-united-states-uscfc-2003.