1200 Sixth Street, Llc v. United States

109 Fed. Cl. 1, 2013 U.S. Claims LEXIS 75, 2013 WL 571755
CourtUnited States Court of Federal Claims
DecidedFebruary 14, 2013
Docket00 S
StatusPublished

This text of 109 Fed. Cl. 1 (1200 Sixth Street, Llc v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
1200 Sixth Street, Llc v. United States, 109 Fed. Cl. 1, 2013 U.S. Claims LEXIS 75, 2013 WL 571755 (uscfc 2013).

Opinion

*2 Breach of Contract Claim; Rule 12(b)(6) Motion to Dismiss; GSA Option Agreement to Purchase Real Property; Whether Option Was Ever Exercised.

OPINION AND ORDER

WHEELER, Judge.

On June 18, 2012, plaintiff 1200 Sixth Street, LLC filed a breach of contract claim against the United States in this Court. Plaintiff alleges that the General Services Administration (“GSA”) breached a contract for the purchase of real property in Detroit, Michigan, and as a result, Plaintiff seeks $4.5 million in damages for the loss of property value and other costs. 1

On August 17, 2012, Defendant filed a motion to dismiss pursuant to Rule 12(b)(6) of the Court of Federal Claims (“RCFC”) for failure to state a claim upon which relief can be granted. Plaintiff filed a response to Defendant’s motion on September 18, 2012, and Defendant replied on October 2, 2012. Initially, this case was assigned to Judge Francis M. Allegra, but by mutual consent was transferred to the undersigned on January 7, 2013. The Court heard oral argument on January 30, 2013. After carefully reviewing the parties’ filings, the Court concludes that Plaintiff has failed to allege sufficient facts to support its claim for breach of contract. Accordingly, Defendant’s motion to dismiss is GRANTED.

Background

Plaintiff is a limited liability company with its principal place of business in Detroit, Michigan. Compl. ¶ 1. Plaintiff owns real property on the western edge of downtown Detroit, upon which there is a high rise office complex comprised of two towers and adjoining parking areas. Compl. ¶¶4-5. The building was vacant at the time of purchase except for the presence of telecommunication tower equipment operated by the Federal Aviation Administration (“FAA”) and the Michigan State Police (“MSP”). Compl. ¶ 6. The FAA and the MSP had an express easement for their use of the building, which Plaintiff was obligated to honor. Compl. ¶ 6.

In 2005, the GSA sought to create new field offices for the Federal Bureau of Investigation (“FBI”) and began soliciting bids for possible locations, including Detroit, Michigan. Compl. ¶ 7. Plaintiffs managing member, Sam Danou, attended a GSA conference regarding the sales process, and learned that the acquisition of any property would be made through an option agreement, assignable by the GSA to a third party developer. Compl. ¶¶ 8-9. Mr. Danou met with the GSA’s project supervisor, Julie Hoffman, among others, and the parties began negotiating a deal. Compl. ¶¶ 10-12. After preliminary meetings and tests on the property, the parties executed a Real Estate Option Agreement (“Option Agreement”) with an effective date of August 1, 2006. Compl. ¶¶ 16-19; Ex. E. Under the terms of the Option Agreement, the option was exercisable whether or not the GSA had selected a developer for the property. Compl. ¶ 21. Concurrently, the parties also drafted an unsigned Agreement for Purchase and Sale of Property (“Purchase Agreement”). Compl. ¶ 20; Ex. G.

The Option Agreement included an integration clause which provided that “the Option [Agreement] and its exhibits were the sole understanding between the parties.” Compl. ¶ 25; see Ex. E ¶ 18. Under the Option Agreement, both Plaintiff and the GSA were “obligated to expend substantial amounts of money, time, effort and energy” in pursuing the project even though the GSA was not obligated to purchase the property until it exercised the option. Compl. ¶26; see Ex. E ¶ 12. According to Plaintiff, these obligations included employing an expert to prepare an environmental assessment, achieving due care activities, securing title insurance and surveys, securing state, county, or city governmental approval for a Brownfield plan, street vacations, utility relo-cations, rezoning, site plan approval, special use permits and variances, and certain traffic studies if necessary. Compl. ¶ 27; Ex. E ¶¶ 5, 6, 8, 11, 12. Ultimately, if the GSA elected to exercise the option, Plaintiff was *3 required to deliver the property “free and clear of all liens and encumbrances whatsoever.” Ex. E ¶ 4.

Based upon “media disclosures” and the “conduct and activities of the GSA in approving the content of such disclosures” in the summer of 2006, Plaintiff believed the exercise of the option to be imminent. See Compl. ¶ 32; Exs. I & J. The last major encumbrance remaining on the property was the communication tower equipment on the building, held under the express easement by the FAA and the MSP. See Compl. ¶ 6; Pl.’s Resp. 4. Therefore, to fulfill the terms of the Option Agreement, Plaintiffs lawyer sought a prospective commitment from the MSP for removal of the communication tower equipment earlier than permitted by the easement. Compl. ¶ 33. Plaintiff learned that such early termination would require an approximate 90-day notice and cost $114,000, information it then relayed to the GSA. Compl. ¶¶ 33, 34.

Up until this point, the GSA’s Ms. Hoffman and Plaintiff had communicated much of the “required performance due from each other under the Option” by email. Compl. ¶35. On May 10, 2007, Ms. Hoffman instructed Plaintiff by email to “proceed with contacting the State regarding the 90-day notice for removal of the antennaes [sic],” referring to the communication tower equipment. Ex. L. In this email, Ms. Hoffman also noted the GSA’s intent to further “discuss the assignable option” the following day, and said she would be in contact with Plaintiff the next week. Ex. L; Compl. ¶¶ 38-39. Plaintiff assumed that this email constituted the exercise of the option, and immediately proceeded to have the towers removed at the cost of $114,000. Compl. ¶¶ 40-41.

By this time, however, the GSA had lost the only developer with which it had negotiated and, when it could not secure another acceptable developer, the GSA ended the deal with Plaintiff in August 2008. Compl. ¶¶ 61, 68. Plaintiff was left with a “building that had remained unoccupied for [two] years ... and had been left without maintenance, repair or ordinary upkeep.” Compl. ¶ 68. Plaintiff claims the property depreciated by more than $4 million between the date of purchase and April 5, 2012, the date of a recent Michigan tax assessment. Compl. ¶ 70; Ex. Q.

Plaintiff initially brought suit in the United States District Court for the Eastern District of Michigan, Southern Division, alleging claims of promissory estoppel and detrimental reliance, quasi contract, negligent misrepresentation, declaratory and injunctive relief, and attorney’s fees under the EAJA. Compl. ¶ 72; Ex. R at 5. The district court granted the Government’s motion to dismiss based on lack of subject matter jurisdiction due to sovereign immunity. Ex. R at 20; Compl. ¶ 73. Plaintiff has since filed its claim in this Court, and now alleges breach of contract and seeks attorney’s fees under the EAJA Compl. ¶¶ 74-86. Plaintiff demands $4.5 million in damages for its losses and other expenses incurred.

Discussion

I. Standard of Review

In reviewing Defendant’s motion to dismiss pursuant to RCFC 12(b)(6), the Court accepts as true all well-pleaded allegations in the complaint and draws all reasonable inferences in favor of the plaintiff. See Ashcroft v. Iqbal,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Aleman Food Services, Inc. v. The United States
994 F.2d 819 (Federal Circuit, 1993)
The Hunt Construction Group, Inc. v. United States
281 F.3d 1369 (Federal Circuit, 2002)
Allied Technology Group, Inc. v. United States
41 Cont. Cas. Fed. 77,179 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
109 Fed. Cl. 1, 2013 U.S. Claims LEXIS 75, 2013 WL 571755, Counsel Stack Legal Research, https://law.counselstack.com/opinion/1200-sixth-street-llc-v-united-states-uscfc-2013.