Allied Technology Group, Inc. v. United States

41 Cont. Cas. Fed. 77,179, 39 Fed. Cl. 125, 1997 U.S. Claims LEXIS 189, 1997 WL 573494
CourtUnited States Court of Federal Claims
DecidedSeptember 12, 1997
DocketNo. 97-143C
StatusPublished
Cited by30 cases

This text of 41 Cont. Cas. Fed. 77,179 (Allied Technology Group, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Technology Group, Inc. v. United States, 41 Cont. Cas. Fed. 77,179, 39 Fed. Cl. 125, 1997 U.S. Claims LEXIS 189, 1997 WL 573494 (uscfc 1997).

Opinion

OPINION

HORN, Judge.

Allied Technology Group, Inc. (ATG) submitted a proposal in response to a Department of the Navy solicitation for the pre-installation coordination, refurbishment, and installation of the Joint Maritime Command Information System (JMCIS), fiber-optic systems, wide area networks, and local area networks onboard ships and at shore facilities. Contract award was made on November 21, 1996 to Computer Systems International, Inc. (CSI). The complaint in the above-captioned case originally was filed on March 5, 1997; an amended complaint was filed April 4,1997. The complaint before the court does not request injunctive relief. The complaint is a protest after award, seeking a declaration that the Navy’s cost evaluation of ATG’s proposal was unlawful, termination of the award to CSI, a remand to the Department of the Navy for award of the contract to ATG, and award to ATG of costs and legal fees.

The defendant and the intervenor jointly filed a motion for summary judgment on May 9, 1997. The defendant and the intervenor CSI assert that the plaintiff cannot prove by clear and convincing evidence that the Navy’s decision was arbitrary or capricious. The defendant and the intervenor also contend that if errors were made during proposal evaluations, they did not prejudice ATG, and that the award to CSI was proper and in compliance with the applicable laws and regulations. The defendant and the intervenor further argue that if the solicitation was unclear, the plaintiff had a duty to seek clarification of any discrepancies in the solicitation in a timely manner, but failed to do so.

ATG filed a cross-motion for summary judgment on May 13, 1997. ATG contends that, like CSI’s proposal, its proposal was technically acceptable; that cost estimates drove the award decision; and that, had errors not been made in evaluating its cost proposal, ATG would have been recognized as having the lowest evaluated cost proposal and, thus, would have received the contract award. ATG alleges that errors occurred during the Navy’s evaluation of overtime costs on each of the proposals submitted, and during the evaluation of warehousing costs in ATG’s proposal. Additional reply briefs and documents were filed by all parties in May and June, 1997, until the most recent set of memoranda and documents was filed by each of the parties on June 27,1997.

FACTS

On October 25, 1995, the Fleet and Industrial Supply Center (FISC), Norfolk, Detachment Philadelphia, Department of the Navy, issued Solicitation No. N00140-96-R-E109, requesting proposals for the pre-installation coordination, refurbishment and installation [127]*127of the JMCIS, fiber optic systems, wide area networks, and local area networks onboard ships and at shore facilities. The solicitation contemplated an 8(a) set-aside in accordance with the Federal Acquisition Regulation (FAR), 48 C.F.R. § 6.204 (1996); a cost plus fixed fee, indefinite delivery/indefinite quantity, level of effort contract; and a procurement with a base year, and four one-year options, with the option years being evaluated.

The Navy’s Request for Proposals indicated that award would be made to a responsible contractor, “whose offer, conforming to the solicitation, is determined most advantageous to the Government, eosVprice and other factors considered.” The solicitation also indicated that “[c]osts will be evaluated on the basis of cost realism. Cost realism pertains to the offeror’s ability to project costs which are realistic and reasonable and which indicate that the offeror understands the nature and scope of work to be performed.”

The first issue raised by the plaintiff at the agency level, and now with this court, concerns the Navy’s evaluation of overtime hours. Plaintiff contends that overtime costs should not have been evaluated in the award competition at all. Initially, the defendant had evaluated overtime hours with overtime rates. After plaintiffs agency protest, the Navy recomputed overtime hours using straight time rates, which resulted in CSI still having the lowest evaluated cost proposal.

The Level of Effort clause in the solicitation, at Section B, “SUPPLIES/SEKVTCES AND PRICES,” contains the Navy’s estimate of labor hours required, divided by base and option years, by work site, by labor category, and by straight time and overtime hours. The solicitation defines “straight time” as a 40-hour work week in accordance with 48 C.F.R. § 22.103-1 (1996); “overtime” was defined as time worked in excess of the normal work week. The table of estimated labor hours included is several pages in length, but the introductory language and a sample of the first five entries (for illustrative purposes) is reproduced below:

LEVEL OF EFFORT (COST TYPE CONTRACT) (FISC DET PHILA) (OCT 1992)

(a) The level of effort for the performance of this contract during the period from the start of contract performance to 12 months thereafter is based upon 223,900 estimated manhours of direct labor. If all options are exercised by the government, the level of effort for the performance of this contract will be increased by an additional 895,600 estimated manhours of direct labor, for a total level of effort of 1,119,500 estimated manhours of direct labor (hereinafter referred to as the ‘Estimated Total Hours’) (emphasis in original).

(b) The estimated composition by labor category of the Estimated Total Hours is as follows:

East Coast Labor Lot I Lot II Lot III Lot IV Lot V

^Program Manager 2000 2000 2000 2000 2000

* Sr Elec/Meeh Eng 2000 2000 2000 2000 2000

* Sr Elec/Meeh Eng OT 500 500 500 500 500

* Elec/Meeh Eng 2000 2000 2000 2000 2000

* Elec/Meeh Eng OT 500 500 500 500 500

* * *

Amendment 0004, effective on January 5, 1996, replaced the table originally issued in the solicitation. (Lot I represents the base year, Lots Il-V represent the four option years, and “OT” is overtime.)

Aso addressing overtime, Section M of the solicitation, titled “EVALUATION FACTORS FOR AWARD”, at paragraph (3), reads:

(3) Costs will be evaluated on the basis of cost realism. Cost realism pertains to the offeror’s ability to project costs which are realistic and reasonable and which indicate that the offeror understands the nature and scope of work to be performed.
Labor will be evaluated on the basis of 100% straight time. Uncompensated over[128]*128time and overtime rates will not be used in the evaluation. Foe [sic] evaluation purposes, a full man year of effort equates to 1,920 hours.

Plaintiff points to the language in the last paragraph of Section M(3), which addresses straight time and overtime, to support its contention that overtime should not have been evaluated.

The second issue raised by the plaintiff at the agency level and in this court concerns the evaluation of warehousing costs. Plaintiff contends that its proposed overhead allocation for warehousing costs, and not the Navy’s direct warehousing cost estimates provided in the solicitation, should have been evaluated in the award competition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Korte Construction Company
Armed Services Board of Contract Appeals, 2023
Draken International, Inc. v. United States
120 Fed. Cl. 383 (Federal Claims, 2015)
Griffin & Griffin Exploration, LLC v. United States
116 Fed. Cl. 163 (Federal Claims, 2014)
1200 Sixth Street, Llc v. United States
109 Fed. Cl. 1 (Federal Claims, 2013)
System Planning Corp. v. United States
107 Fed. Cl. 710 (Federal Claims, 2012)
Retirement Communities LLC v. United States
92 Fed. Cl. 587 (Federal Claims, 2010)
Grand Acadian, Inc. v. United States
87 Fed. Cl. 193 (Federal Claims, 2009)
Enron Federal Solutions, Inc. v. United States
80 Fed. Cl. 382 (Federal Claims, 2008)
Centech Group, Inc. v. United States
78 Fed. Cl. 496 (Federal Claims, 2007)
Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
Blue & Gold Fleet, L.P. v. United States
492 F.3d 1308 (Federal Circuit, 2007)
Rotech Healthcare Inc. v. United States
71 Fed. Cl. 393 (Federal Claims, 2006)
Information Systems & Networks Corp. v. United States
68 Fed. Cl. 336 (Federal Claims, 2005)
Dismas Charities, Inc. v. United States
61 Fed. Cl. 191 (Federal Claims, 2004)
ABF Freight System, Inc. v. United States
55 Fed. Cl. 392 (Federal Claims, 2003)
Comtrol, Inc. v. United States
49 Fed. Cl. 294 (Federal Claims, 2001)
Little v. United States
48 Fed. Cl. 843 (Federal Claims, 2001)
Baltimore Gas & Electric Co. v. United States
133 F. Supp. 2d 721 (D. Maryland, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
41 Cont. Cas. Fed. 77,179, 39 Fed. Cl. 125, 1997 U.S. Claims LEXIS 189, 1997 WL 573494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-technology-group-inc-v-united-states-uscfc-1997.