Draken International, Inc. v. United States

120 Fed. Cl. 383, 2015 U.S. Claims LEXIS 107, 2015 WL 644055
CourtUnited States Court of Federal Claims
DecidedFebruary 13, 2015
Docket14-1005C
StatusPublished
Cited by9 cases

This text of 120 Fed. Cl. 383 (Draken International, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Draken International, Inc. v. United States, 120 Fed. Cl. 383, 2015 U.S. Claims LEXIS 107, 2015 WL 644055 (uscfc 2015).

Opinion

Pre-award Bid Protest; 28 U.S.C. § 1491(b)(1); Competition in Contracting Act; 41 U.S.C. § 3306(a); Solicitation Terms Coupled With Procurement Delay Did Not Unduly Restrict Competition; Ripeness.

OPINION AND ORDER

WILLIAMS, Judge.

This pre-award bid protest comes before the Court on the parties’ cross-motions for judgment on the Administrative Record (“AR”). Plaintiff, Draken International, Inc. (“Draken”), challenges the procurement process implemented by the Department of the Navy’s Naval Air Systems Command (“NA-VAIR”) under solicitation number N00019-12-R-1001. Plaintiff argues that NÁVAIR violated the Competition in Contracting Act (“CICA”) and the Federal Acquisition Regulation (“FAR”) 2 because its delay in conducting the procurement coupled with the solicitation’s requirement that the awardee provide both subsonic (“Type III”) and supersonic (“Type IV”) aircraft unduly restricts competition. Plaintiff asserts that this solicitation process will result in a de facto sole-source award to Airborne Tactical Advantage Co., LLC (“ATAC”), the incumbent. Because ATAC is currently being paid by the Government to maintain its fleet, Plaintiff submits that ATAC can avoid the prohibitive cost foisted upon other offerors of meeting operational readiness requirements during a prolonged procurement process. Plaintiff also protests the duration of a sole-source bridge contract awarded to ATAC, which could potentially last until July 2015, given the option periods. Finally, Plaintiff contends that it was treated unequally compared to [* * *] other offerors that were allowed to provide new airworthiness data after the deadline for submission of initial offers, while it was not given this opportunity.

*387 Plaintiff seeks -a declaratory judgment that NAVAIR violated CICA and the FAR by unduly restricting competition in its conduct of this procurement. Plaintiff also asks the Court to order NAVAIR to limit the term of ATAC’s sole-source bridge contract to coincide with a final award date and to amend the solicitation to separately procure subsonic and supersonic aircraft services. Alternatively, Plaintiff asks the Court to limit an award under the current solicitation to the-base year and issue a new solicitation for subsequent years or allow all offerors the opportunity to offer new aircraft in the event their originally proposed aircraft are no longer available.

Defendant argues that Draken’s challenge to the solicitation’s terms combining procurement of supersonic and subsonic aircraft is untimely, that the delay in the procurement process resulted from multiple protests, and that the solicitation’s terms are reasonable and necessary to meet NAVAIR’s requirements. Defendant asserts that Draken was not treated any differently than other offer-ors, as Draken was also given a chance to amend its proposal. ATAC argues that Draken does not have standing to bring the instant protest because it no longer qualifies for award, that no improper bundling of requirements has occurred, and that Draken’s allegations of unfair treatment are not ripe.

For the reasons that follow, the Court finds that Plaintiff has standing, its protest is timely, the Agency’s delayed procurement process did not violate CICA, and Draken’s challenge to unequal treatment is unripe.

Findings of Fact 3

The Contracted Air Services Program and Issuance of Solicitation N00019-12-R-1001

The United States Department of the Navy’s Contracted Air Services (“CAS”) program “provides Contractor owned and operated aircraft, personnel, equipment and support for Fleet training and exercises to a variety of customers to include: United States Navy (USN), Foreign Military Sales, and other Department of Defense (DoD) agencies and DoD contractors.” AR 223. Contractors working under the CAS program provide aircraft and related services for “airborne threat simulation” and training exercises for the benefit of “shipboard and aircraft squadron weapon systems operators and aircrew....” Id. In May 2009, ATAC was awarded, a firm fixed price/indefinite-delivery indefinite-quantity contract for the provision of both subsonic Type III and supersonic Type IV aircraft, which fly at higher speeds and are more expensive and difficult to obtain, to support the CAS program. Id. at 35-36, 225, 3407. This contract ended on July 28, 2014, and NAVAIR has been obtaining these services via ATAC’s sole-source bridge contract since then. Id. At 3407..

On June 21, 2013, Sean Staekley, the Assistant Secretary of the Navy (Research, Development and Acquisition) wrote a “Determination and Findings For Authority to Award a Single Source Task Order Contract” for the solicitation at issue. Id. at 4469. This document was created because the Department of Defense may not award task and delivery order contracts exceeding $103 million, inclusive of options, to a single source, “unless the head of the agency determines in writing that the task or delivery orders expected under the contract are so integrally related that only a single source can reasonably perform the work.” Id. According to Assistant Secretary Staekley, a single-source indefinite-delivery/indefinite-quantity contract permitted “the greatest flexibility' in both quantities and schedule to meet the needs of the Fleet in providing combat readiness training.” Id. Furthermore, making a single contractor “the integrator across all locations” avoided the Government either having to take on this integrator role itself or expend additional resources that were not budgeted. Id. at 4470.

Assistant Secretary Staekley articulated reasons why Type III and Type IV aircraft were included in the same solicitation, stating:

The simultaneous presentation requirement for high subsonic and supersonic aircraft was developed based on the current contract practice of authorizing the contractor to fulfill high subsonic missions *388 with supersonic aircraft, which are billed at the lower high subsonic contract rate. This augmentation of high subsonic aircraft allows the Government to minimize the required quantity of high subsonic aircraft without compromising the ability to cover surge requirements.
With a multiple award contract, the ability to augment high subsonic aircraft for surge requirements is lost, and the Government would be required to increase the required number of high subsonic aircraft to maintain the same level of contractor coverage. .The ability to augment high subsonic aircraft saves the [United States Navy] and [the Department of Defense] money because it results in a higher utilization of supersonic aircraft and avoids the payment of fixed aircraft costs for additional high subsonic aircraft.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rmgs, Inc. v. United States
Federal Claims, 2018
Remote Diagnostic Technologies LLC v. United States
133 Fed. Cl. 198 (Federal Claims, 2017)
I3 Cable & Harness LLC v. United States
132 Fed. Cl. 495 (Federal Claims, 2017)
Omran Holding Group v. United States
128 Fed. Cl. 273 (Federal Claims, 2016)
Palantir Technologies Inc. v. United States
128 Fed. Cl. 21 (Federal Claims, 2016)
Visual Connections, LLC v. United States
120 Fed. Cl. 684 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
120 Fed. Cl. 383, 2015 U.S. Claims LEXIS 107, 2015 WL 644055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/draken-international-inc-v-united-states-uscfc-2015.