Korte Construction Company

CourtArmed Services Board of Contract Appeals
DecidedMay 6, 2024
Docket63148
StatusPublished

This text of Korte Construction Company (Korte Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Korte Construction Company, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Korte Construction Company ) ASBCA No. 63148 ) Under Contract No. W912BV-19-C-0017 )

APPEARANCE FOR THE APPELLANT: Michael E. Wilson, Esq. Greenfelder, Hemker & Gale, P.C. St. Louis, MO

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Lauren M. Williams, Esq. Thomas R. Alford, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Tulsa

OPINION BY ADMINISTRATIVE JUDGE STINSON ON APPELLANT’S MOTION FOR RECONSIDERATION

Appellant Korte Construction Company (Korte) requests reconsideration of our October 26, 2023, decision granting the government’s motion for summary judgment and denying appellant’s motion for summary judgment. Korte Constr. Co., ASBCA No. 63148, 23-1 BCA ¶ 38,454. Korte appealed a contracting officer’s final decision denying Korte’s claim challenging the government’s entitlement to a credit in the amount of $493,639.43, for a deductive change to the contract work. We granted the government’s motion for summary judgment, finding that Korte and its subcontractor recognized pre-award an ambiguity or discrepancy in the solicitation regarding whether certain work was required to be performed, and that Korte failed to fulfill its duty to seek clarification from the government pre-award regarding that work. Familiarity with that decision is presumed. For the reasons stated below, appellant’s motion for reconsideration is denied.

DISCUSSION

“Motions for reconsideration do not afford litigants the opportunity to take a ‘second bite at the apple’ or to advance arguments that properly should have been presented in an earlier proceeding.” Dixon v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014). Reconsideration may be appropriate, however, “if we made mistakes in our findings of fact or conclusions of law, or [failed] to consider an appropriate matter.” Supreme Foodservice GmbH, ASBCA No. 57884 et al., 20-1 BCA ¶ 37,716 at 183,090 (citation omitted). “[I]f we have made a genuine oversight that affects the outcome of the appeal, we will remedy it.” Relyant, LLC, ASBCA No. 59809, 18- 1 BCA ¶ 37,146 at 180,841.

I. Appellant’s Contentions

Korte alleges that the Board erred (1) “by failing, as required by well- established law on the interpretation of government contracts, to consider the requisite initial step for determining whether an ambiguity exists, to wit: is each party’s contract interpretation within the ‘zone of reasonableness’” (app. mot. at 2), (2) “by concluding that the record establishes that an ambiguity exists” (id.), and (3) by “failing to consider and by failing to correctly apply the following controlling Federal Acquisition Regulation (FAR) clause: ‘In case of difference between drawings and specifications, the specifications shall govern.’ FAR 52.236-21” (id.).

II. The Board Did Not Err or Fail to Apply Well-Established Law Governing Interpretation of Government Contracts

Appellant argues in its motion for reconsideration that the Board “summarily concluded that the solicitation documents were ambiguous regarding whether chilled water improvements were required,” and “did not undertake the initial requisite step in contract interpretation, i.e., ascertaining whether each party’s interpretation falls within the ‘zone of reasonableness’” (app. mot. at 4). According to appellant, there existed “no ambiguity because the Government’s interpretation does not fall with the ‘zone of reasonableness’” (app. mot. at 21 n.10).

a. Contract Interpretation

Our decision did not “summarily” conclude that the chilled water improvements requirements were ambiguous. Rather our decision included a lengthy statement of facts relevant to the contractual issues raised by the parties, as well as the parties’ positions regarding those facts. Korte, 23-1 BCA ¶ 38,454 at 186,901-906 (SOF ¶ 6 (Korte’s subcontractor’s understanding of the RFP), SOF ¶ 9 (RFP specification requirements), SOF ¶ 10 (addition of new RFP Phase 2 specification paragraph 4.5.6, requiring that the contractor “[e]xtend the base wide chilled water, hot water, and compressed air piping to the slab edge of the hangar. Provide connection location for future projects”), 1 SOF ¶¶ 11-13 (RFP Phase 2 schematic drawings depicting three

1 Korte argued in its response to the government’s motion for summary judgment that appellant’s subcontractor conducted an “investigation of pre-existing utility lines at Tinker AFB,” and “confirmed via available base documents that no base-wide or campus chilled water system or hot water system existed ….” (app. resp. at 43; see also Korte, 23-1 BCA ¶ 38,454 at 186,905 (SOF ¶ 34)). 2 parallel lines labeled “CW”), SOF ¶ 22 (Korte’s RFP Phase 2 Proposals which included annotated drawings contained in the solicitation with three parallel lines labeled “CW”), SOF ¶¶ 32-34 (Korte’s subcontractor’s interpretation of the RFP requirements), SOF ¶ 38 (Korte’s August 24, 2021, claim admitting knowledge of the ambiguity discovered during development of Korte’s pricing, stating, “since there is no base wide chilled water system, terms purporting to extend such a non-existing system are obviously the product of a scrivener's mistake—one which was recognized during the development of Korte’s pricing—and cannot have any force and effect”)).

Our decision likewise considered the parties’ legal arguments. Korte, 23-1 BCA ¶ 38,454 at 186,907. On the merits, we found “it is undisputed the RFP Phase 2 specification included a new paragraph 4.5.6, which required the contractor to ‘[e]xtend the base wide chilled water, hot water, and compressed air piping to the slab edge of the hangar. Provide connection location for future projects.’” Id. at 186,908 (citing SOF ¶ 10). We likewise found “[t]here is no legitimate dispute that the RFP Phase 2 documents included reference to chilled water piping, i.e., contract drawings with three parallel lines running east to west labeled ‘CW,’” id. at 186,908 (citing SOF ¶¶ 13, 22), and that Korte’s “attempt to downplay the import of the reference to ‘CW’ on certain contract drawings” because of their size or difficulty in reading them on the drawings “does not excuse appellant from attempting to understand its import, nor does it somehow cast the information as less important or less relevant than other, larger markings or information set forth on the drawings.” Id. at 186,910 (citing Natkin and Co., ASBCA Nos. 26072, 29071, 84-2 BCA ¶ 17,469 at 87,044 (where contract drawings are “difficult to read” it is incumbent upon the contractor to resolve “the matter by inquiry prior to submitting its proposal”)).

Noting appellant’s argument that “[t]here was simply no good reason to extend chilled water piping from the slab edge of the hangar per the above-quoted SOW … when there was no apparent need for chilled water piping in the first place,” and that “it was absurd to read the SOW statement as extending something that was non- existent,” id. at 186,908 (citing app. mot. at 27) (emphasis in original), we held that “Korte’s chosen course of action - to simply ignore the import of the actual language that Korte’s viewed as ‘absurd’ - in no way justifies Korte’s decision to make no inquiry regarding the meaning of the new specification paragraph 4.5.6, or the government's reference in that specification to ‘future projects.’” Id. We likewise held that “[t]he record establishes that Korte’s subcontractor recognized pre-award an ambiguity in the solicitation documents regarding installation of chilled water lines, although rather than seeing a relatively limited set of ambiguities, chose (and, let there be no mistake, it was a choice) to interpret the contract to its benefit.” Id. (citing SOF ¶¶ 6, 32-34, 38; app. resp. at 9; app.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fortec Constructors v. The United States
760 F.2d 1288 (Federal Circuit, 1985)
Dixon v. Shinseki
741 F.3d 1367 (Federal Circuit, 2014)
James A. Mann, Inc. v. United States
535 F.2d 51 (Court of Claims, 1976)
Newsom v. United States
676 F.2d 647 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Korte Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/korte-construction-company-asbca-2024.