H&L Contracting LLC

CourtArmed Services Board of Contract Appeals
DecidedNovember 21, 2024
Docket63695
StatusPublished

This text of H&L Contracting LLC (H&L Contracting LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H&L Contracting LLC, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) H&L Contracting LLC ) ASBCA No. 63695 ) Under Contract No. W912WJ-22-C-0012 )

APPEARANCES FOR THE APPELLANT: Michael H. Payne, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

Matthew C. Long, Esq. Cohen Seglias Pallas Greenhall & Furman PC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Theresa A. Negron, Esq. Sheena M. Wandera, Esq. Engineer Trial Attorneys U.S. Army Engineer District, New England

OPINION BY ADMINISTRATIVE JUDGE MCLISH ON THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT

Appellant H&L Contracting LLC (H&L) appeals from a final decision of a contracting officer for the United States Army Corps of Engineers (USACE or respondent) denying H&L’s claims arising from a contract to dredge two channels in Newburyport Harbor in Newburyport, Massachusetts. The government moves for summary judgment in its favor, and H&L moves for summary judgment on the issue of entitlement. For the reasons stated below, the motions are denied. STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS 1

USACE awarded H&L a contract to dredge shoaled sediments from the 9-foot and 15-foot navigation channels in Newburyport Harbor, Newburyport, MA. 2 The solicitation for the contract said this about the sea conditions in the channels in Section 1.4.1 of Specification 01 11 00:

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

a. Site Conditions: The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys. The conditions represented prevailed at the time the investigations and surveys were made. A pre-dredge survey may be performed by the Government prior to the start of Contractor dredging operations at the site. Before commencing work at the site, the Contractor shall verify the existing conditions indicated on the drawings and in the specifications. See CONTRACT CLAUSE entitled “SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK”.

b. Weather Conditions: The monthly normal mean temperature and the monthly normal mean precipitation for the site may be obtained by the Contractor from the nearest U.S. National Weather Service Office.

1 In contravention of Board Rule 7, USACE’s opposition to H&L’s Motion for Summary Judgment did not include a Statement of Genuine Issues of Material Fact responding to H&L’s Statement of Undisputed Material Facts. USACE belatedly submitted a “Reply to H&L Statement of Undisputed Material Facts” that, in conclusory fashion, purports to deny certain of H&L’s statements of fact. Although Rule 7(c)(2) allows us to consider each of H&L’s statements of fact to be undisputed in these circumstances, here we opt to treat as disputed those for which USACE makes properly-supported assertions in its Statement of Undisputed Material Facts. 2 Appellant’s Statement of Undisputed Material Facts (ASUMF) ¶¶ 1, 89; Respondent’s Statement of Undisputed Material Facts (RSUMF) ¶ 1; Appellant’s Statement of Genuine Issues of Material Facts (ASGIMF) ¶ 1; R4, tab 4 at 125-26. 2 c. Conditions of 9 Foot Channel: Under most weather conditions, the 9 Foot Channel has swells up to 1 foot. The 9 Foot Channel was last dredged in 2011 and has experienced considerable shoaling since that time.

d. Conditions at 15 Foot Entrance Channel: The tidal currents at the entrance to the harbor can be substantial, creating potentially dangerous conditions. Under good weather conditions, the sea swell is typically 1-2 feet in a northerly direction. In normal weather conditions, the sea swell can range from 2 to 4 feet or more. 3

In preparing its bid for the contract, H&L relied on the information provided in the solicitation, as well as its extensive dredging experience. 4 Although H&L did not attend a site visit hosted by USACE, its managing member had twice visited and observed the Newburyport channels. 5 H&L did not consult publicly available websites containing weather data for the Newburyport area or make inquiries with the Newburyport Harbormaster or U.S. Coast Guard. 6 What such inquiries would have revealed regarding the sea conditions in the 15-foot channel is not evident from the record.

H&L compared the specifications for the Newburyport project to those used for a similar dredging project H&L had performed for USACE a few years earlier at Hampton Harbor, located at Hampton and Seabrook, New Hampshire. 7 Hampton Harbor is about five miles from Newburyport harbor and the physical orientation of its channel is similar to that of Newburyport channels. 8 USACE’s solicitation for the Hampton Harbor project described the ocean conditions there using language very similar to the language it used to describe the 15-foot channel in Newburyport Harbor. 9 H&L successfully completed dredging of the Hampton Harbor entrance channel using a 16-foot’ cutterhead dredge in November and December 2019. 10 Because of the similarities in solicitation language and channel orientation, H&L

3 ASUMF ¶ 66; RSUMF ¶¶ 5, 6, 12, 13; ASGIMF ¶¶ 5, 6, 12, 13; R4, tab 6 at 182. 4 ASUMF ¶ 17, 81. 5 ASUMF ¶ 82; RSUMF ¶ 16; ASGIMF ¶ 16. 6 Gov’t opp’n at ex. 6, Haney depo tr. at 32:4-15, 49:6-14. 7 ASUMF ¶ 81. 8 Id. ¶¶ 18, 81. 9 Id. ¶ 21; app. supp. R4, tab 3 at 0402. 10 ASUMF ¶¶ 22, 23. 3 expected that the 15-foot entrance channel conditions at Newburyport Harbor would be similar to those it had experienced at Hampton Harbor. 11

Based on the information it reviewed, H&L concluded that normal conditions in the 15-foot channel during the permitted dredging season would consist of swells between two and four feet, with swells occasionally exceeding four feet. H&L also concluded that the 15-foot channel would experience some days of good weather, where swells would be between one and two feet. 12

H&L selected two dredges to perform the Project – the 16-inch Finn for work in the 9-foot channel and the 20-inch Oyster Bay for work in the 15-foot channel. Both dredges are hydraulic cutterhead dredges. 13 Cutterhead pipeline dredges are less suitable for rough seas than hopper dredges. 14 USACE was aware that H&L was proposing to use a cutterhead pipeline dredge. 15

The Oyster Bay can comfortably dredge in swells up to three feet. It must cease dredging when swells are more than three feet, but the dredge can stay moored at its location. Where swells reach or exceed five feet, however, the Oyster Bay must return to shore. This results in downtime of approximately 48 hours. 16

H&L successfully completed dredging of the nine-foot channel in November 2022. 17 For the 15-foot channel, H&L mobilized the Oyster Bay to Newburyport Harbor in December 2022 and anticipated a dredging duration of 47 days. 18 Prior to and after mobilization of the Oyster Bay, USACE inspected the vessel four times and on each occasion found deficiencies that required correction.19

H&L began its efforts to dredge the 15-foot channel using the Oyster Bay in December 2022, but the Oyster Bay was unable to complete any dredging.20 On February 3, 2023, H&L submitted a request for an extension of time that contended that, throughout December and January, H&L encountered sea swells in the 15-foot entrance channel that were significantly larger than expected. 21 USACE approved this

11 Id. ¶ 81. 12 Id. ¶ 83. 13 Id. ¶ 84. 14 Id. ¶¶ 13, 15. 15 Id. ¶¶ 87, 90. 16 Id. ¶ 85. 17 Id. ¶ 92. 18 Id. ¶ 94. 19 RSUMF ¶¶ 27, 29, 31, 35; ASGIMF ¶¶ 27, 29, 31, 35. 20 ASUMF ¶¶ 94, 95, 104; RSUMF ¶ 30; ASGIMF ¶ 30. 21 ASUMF ¶¶ 96-98; app. supp. R4, tab 25. 4 extension and obtained state regulatory approval to continue entrance channel dredging through April 30, 2023.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
H&L Contracting LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hl-contracting-llc-asbca-2024.