R.J. Crowley, Inc. v. The United States

923 F.2d 871, 1990 U.S. App. LEXIS 23359, 1990 WL 200220
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 12, 1990
Docket90-1150
StatusUnpublished

This text of 923 F.2d 871 (R.J. Crowley, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.J. Crowley, Inc. v. The United States, 923 F.2d 871, 1990 U.S. App. LEXIS 23359, 1990 WL 200220 (Fed. Cir. 1990).

Opinion

923 F.2d 871

37 Cont.Cas.Fed. (CCH) 76,063

Unpublished Disposition
NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
R.J. CROWLEY, INC., Appellant,
v.
The UNITED STATES, Appellee.

No. 90-1150.

United States Court of Appeals, Federal Circuit.

Dec. 12, 1990.

Before ARCHER, MICHEL and CLEVENGER, Circuit Judges.

DECISION

CLEVENGER, Circuit Judge.

R.J. Crowley, Inc. (Crowley) appeals from a final decision of the Armed Services Board of Contract Appeals (Board), ASBCA No. 34872, denying its claim for an equitable adjustment for insulation installed during performance of Contract DACA31-86-C-0115. Only the issue of entitlement was before the Board. We reverse and remand.

OPINION

Crowley was awarded a contract to install roofing and repair exterior walls on two government buildings. Crowley's bid incorporated a subcontractor's bid for roofing and insulation.

R-values and U-values are conventional terms used in the roofing trade to measure insulating capacity. Every material, including air, has a characteristic R-value that measures resistance to the transmission of heat. Higher R-values indicate greater insulating value. The reciprocal of the resistance, 1/R, is the U-value. The U-value is the overall coefficient of thermal transmittance and is generally expressed as a rate of heat flow over a period of time.

The contract specifications provide that the "[a]ctual installed thickness of insulation shall be such as to provide a coefficient of heat transmission or U-value, through completed roof construction air-to-air, not in excess of .030 Btu per hour." The written specifications further provide that "[i]nsulation shall be laid in two or more layers."

Plate 6 of the drawings contain the following block labelled "Typical for Roofs--Sections 1, 2 and 3":

TABLE OF COEFFICIENT FOR NEW ROOFING
DESCRIPTION                     RVALUE
------------------------------  -------
   Outside air film             .17
   Isocyanurate Insulation      31.25
   7" Concrete Slab             .77
   Air Space                    .97
    3/4 " Metal Lath & Plaster  .47
   Inside Air Film              .61
                                -------
      Total Resistance =        34.24
      Total U Value 1/R =       .029

Three wall sections are depicted on this plate. In each section, two layers of insulation are drawn above an existing concrete deck. An arrow pointing to the two layers is labelled "New Roof Insulation W/R-value min. 12.5." Plate 7 of the drawings also contains an identical notation joined by a single arrow to two layers of insulation. The subcontractor interpreted the drawings as requiring a minimum of two layers of insulation which together would provide an R-value of at least 12.5.

Crowley recognized that use of insulation with a total R-value of 12.5 would not meet the specified U-value of .030. However, the specifications permitted achievement of the required U-value "through completed roof construction air-to-air." The subcontractor believed that existing insulation, generally present "in the 3/4 inch metal lath and plaster under a suspended ceiling," would make up the difference in U-value and would have been known to the architect or engineer that prepared the drawings for the Government. In a post-award communication with the Government, the subcontractor referred to "[c]eiling insulation or other varying inside conditions assumed to be existing." Thereafter, the Government informed Crowley that each of the two layers of insulation must provide a minimum R-value of 12.5, or twice what Crowley believed. The Government acknowledged that even with two layers of insulation, each with an R-value of 12.5, the specified U-value of .030 would not be met without additional contribution from some other unknown element.

The subcontractor installed two layers of insulation with a combined R-value of 30.96. Crowley submitted a claim for the additional cost of $89,667.09. The contracting officer failed to issue a timely final decision and Crowley appealed to the Board pursuant to Section 6(c)(5) of the Contract Disputes Act. 41 U.S.C. Sec. 605(c)(5) (1988).

I. The Board's Decision

Crowley's claim and the Government's response were presented to the Board on documents with affidavits, pursuant to Board Rule 11.

The Board denied Crowley's claim on the ground that the contract was patently ambiguous and that Crowley had failed to satisfy its duty to inquire.

In its opinion, the Board did not lay out a basis for its conclusion "that the ambiguity created by the drawings and specifications was a patent one about which the appellant had the duty to inquire." Notwithstanding an express holding that Crowley's interpretation of the contract was reasonable, the Board merely stated that because the additional contribution that Crowley assumed to exist "was more than 50 percent of the total amount required, [it] was, in our opinion sufficient to create a duty upon appellant to inquire whether its assumption was correct that it was all due to other conditions." In its reconsideration, the Board again stated "appellant's interpretation of the contract was reasonable that the drawings indicated a total R-value of both layers of insulation together. However ... because of the large discrepancy which then existed to meet the contract requirements, there was a patent discrepancy about which appellant should have inquired."

II. Standard Of Review

On appeal, the decision of the Board

on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.

41 U.S.C. Sec. 609(b) (1988).

The Board's conclusions regarding both the existence of a patent ambiguity and the reasonableness of Crowley's interpretation are legal conclusions that we review de novo. Newsom v. United States, 676 F.2d 647, 649 (Ct.Cl.1982) (existence of patent ambiguity in contract must be decided de novo by the court); Mountain Home Contractors v. United States, 425 F.2d 1260, 1264-65 (Ct.Cl.1970) (reasonableness of contractor's interpretation decided as a question of law).

III. Existence Of Patent Ambiguity

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hol-Gar Manufacturing Corporation v. The United States
360 F.2d 634 (Court of Claims, 1966)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Max Drill, Inc. v. The United States
427 F.2d 1233 (Court of Claims, 1970)
R.E.D.M. Corporation v. The United States
428 F.2d 1304 (Court of Claims, 1970)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Npc, Inc. v. Enviroengineering Products Co., Inc
923 F.2d 871 (Federal Circuit, 1990)
Mountain Home Contractors v. United States
425 F.2d 1260 (Court of Claims, 1970)
Chris Berg, Inc. v. United States
455 F.2d 1037 (Court of Claims, 1972)
S.O.G. of Arkansas v. United States
546 F.2d 367 (Court of Claims, 1976)
Newsom v. United States
676 F.2d 647 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
923 F.2d 871, 1990 U.S. App. LEXIS 23359, 1990 WL 200220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rj-crowley-inc-v-the-united-states-cafc-1990.