Chaparral Industries, Incorporated v. Donald B. Rice, Secretary of the Air Force

975 F.2d 870, 1992 U.S. App. LEXIS 30818, 1992 WL 174534
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 27, 1992
Docket91-1382
StatusUnpublished

This text of 975 F.2d 870 (Chaparral Industries, Incorporated v. Donald B. Rice, Secretary of the Air Force) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chaparral Industries, Incorporated v. Donald B. Rice, Secretary of the Air Force, 975 F.2d 870, 1992 U.S. App. LEXIS 30818, 1992 WL 174534 (Fed. Cir. 1992).

Opinion

975 F.2d 870

NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
CHAPARRAL INDUSTRIES, INCORPORATED, Appellant,
v.
Donald B. RICE, Secretary of the Air Force, Appellee.

No. 91-1382.

United States Court of Appeals, Federal Circuit.

July 27, 1992.

Before ARCHER, MAYER and MICHEL, Circuit Judges.

MICHEL, Circuit Judge.

DECISION

Chaparral Industries, Inc. appeals the decision of the Armed Services Board of Contract Appeals (Board) denying Chaparral an equitable adjustment to the price of its contract to build missile containers based on allegedly defective government specifications. Chaparral Indus., Inc., ASBCA No. 34396, 91-2 BCA p 23,813 (1991). The Board held that (1) the government did not breach its implied warranty of its specifications, and (2) the follow-on test agreement did not constitute an admission of legal liability on the part of the government for problems in contract performance. Id. at 119,248. Because Chaparral has not shown that the Board's findings are unsupported by substantial evidence and because the Board correctly interpreted the test agreement, we affirm.

DISCUSSION

I. Implied warranty of specifications.

Chaparral relies on Spearin v. United States, 248 U.S. 132 (1918) to support its assertion that the government breached its implied warranty of the specifications. As Chaparral argues, that case, broadly read, stands for the proposition that if a contractor complies with government specifications, an acceptable product will follow. Id. at 137. Relief to the contractor in Spearin, however, was premised on the government specifications being defective. Id. at 136. Indeed, the Supreme Court expressly distinguished those cases in which the government specifications were not defective but where the contractor merely encountered unforeseen difficulties. Id. (citing Day v. United States, 245 U.S. 159 (1917); Phoenix Bridge Co. v. United States, 211 U.S. 188 (1908)).

In the instant case, an acceptable final product was obtained when the foam cushions were manufactured according to the government specified dimensions as properly construed, i.e., the foam cushions fit into the metal missile containers. Thus, the government specifications could not have been inherently defective.

Although Chaparral encountered difficulties when it cut the specified foam to the specified dimensions at remote locations and then shipped the cut foam pieces to another location for assembly, it does not follow that the specifications were defective. The contract did not require that the foam as initially cut meet certain dimensions or that the foam be manufactured or assembled at a certain location. The contract merely required that cut cushions made of the specified foam meet the dimensions set forth in the specifications. Under ordinary contract construction, that necessarily means at the time and place of acceptance. Chaparral chose Denver, Colorado, to be the place of acceptance, and therefore, was obligated to meet the dimensional requirements at that location.

Likewise, the contract did not specify the method the contractor should use to cut the foam, the temperature or humidity at which the foam should be cut, the amount of time the contractor should allow the foam to stabilize after being cut, or the time and manner of shipment. Because these methods of performance were not delineated in the specifications, the government's implied warranty of its specifications did not cover these aspects of performance. Instead, these aspects of performance, as well as that pertaining to the place of cutting the foam, were the sole responsibility of the contractor in producing cushions that met the required dimensional tolerances at the place of acceptance. That Chaparral incurred additional costs in meeting the specified dimensional tolerances because of its selected manner and place of performance does not mean the government's specifications were inherently defective and therefore the government breached an implied warranty of its specifications.

Chaparral argues that it could not have directed its subcontractors to cut the foam below dimensional tolerances because the contract permitted the Air Force to perform inspections at the subcontractors' places of business to insure that the subcontractors were manufacturing in strict accordance with the contract drawings and specifications. This argument is not persuasive. Chaparral admitted during oral argument that the government could also inspect at Denver. Given the government's suspicion, and later conclusion, that the change in altitude caused some of the foam to expand in transport from the subcontractors' places of business near sea-level in North Carolina and Massachusetts to mile-high Denver, the government could not have insisted on dimensional accuracy at the subcontractors' places of business.1 As Denver was the place of acceptance, that was the only location at which the government could insist on the specified dimensional accuracy.

Chaparral also argues that the government's choice of foam, not its own selected method of performance, is what caused the dimensional defects. However, the fact that the first article testing was successful and that Chaparral did not encounter any such defects with the larger percentage of the cushions supports the finding that the specifications were not inherently defective. The material selected by the government, expanded polyethylene 2 pound density per PPP-C-1752, Type 1, Class 2, could produce acceptable products, and indeed, did produce adequate products most of the time.

Chaparral argues that the government cannot rely on the satisfactory result of the first article testing and that Chaparral did not encounter difficulties with some of the cushions because the government specifications could still "be deemed defective for purposes of the author's liability to the user." Chaparral relied upon and quoted from R.E.D.M. Corp. v. United States, 428 F.2d 1304, 1308 (Ct.Cl.1970). That case, however, is clearly distinguishable from the instant case. In R.E.D.M., most, if not all, of the assemblies were manufactured within government specified tolerances. Twenty percent of the assemblies were unacceptable nonetheless. On that basis, the court found that the specification was defective. Id. In contrast, Chaparral did not encounter any rejections with the cushions which satisfied the government specified tolerances at Denver; only those cushions which were outside the government specified tolerances caused Chaparral problems. Accordingly, here there is no factual basis to infer that the specifications were defective.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phoenix Bridge Co. v. United States
211 U.S. 188 (Supreme Court, 1908)
Day v. United States
245 U.S. 159 (Supreme Court, 1917)
United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
R.E.D.M. Corporation v. The United States
428 F.2d 1304 (Court of Claims, 1970)
Beta Systems, Inc. v. The United States
838 F.2d 1179 (Federal Circuit, 1988)
B. D. Click Co. v. United States
614 F.2d 748 (Court of Claims, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
975 F.2d 870, 1992 U.S. App. LEXIS 30818, 1992 WL 174534, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chaparral-industries-incorporated-v-donald-b-rice--cafc-1992.