Zinger Construction Co. v. United States

34 Cont. Cas. Fed. 75,411, 13 Cl. Ct. 752, 1987 U.S. Claims LEXIS 222, 1987 WL 21049
CourtUnited States Court of Claims
DecidedNovember 30, 1987
DocketNo. 94-86C
StatusPublished
Cited by2 cases

This text of 34 Cont. Cas. Fed. 75,411 (Zinger Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zinger Construction Co. v. United States, 34 Cont. Cas. Fed. 75,411, 13 Cl. Ct. 752, 1987 U.S. Claims LEXIS 222, 1987 WL 21049 (cc 1987).

Opinion

OPINION

YOCK, Judge.

This contract ease is currently before the Court on the defendant’s motion for summary judgment. For the reasons discussed herein, the defendant’s motion for summary judgment is granted, and the plaintiff’s complaint is to be dismissed.

Factual Background

This is the sixth time that the plaintiff’s value engineering (YE) claim arising out of Contract No. DACA51-73-C-0133 has been before a court or board for appropriate disposition. On July 11, 1984, the plaintiff appealed the decision of the Armed Services Board of Contract Appeals (Board), ASBCA No. 28585, 84-1 BCA ¶ 17,209 (the third Board decision), which had dismissed [753]*753Zinger’s appeal on the grounds of res judi-cata, to the Court of Appeals for the Federal Circuit.

In its decision of January 30, 1985, the Federal Circuit spelled out the factual background of this case in clear and concise language, as follows:

In June 1973 Zinger contracted to construct an incinerator plant at Watervliet Arsenal in Watervliet, New York, for $818,488. Subsequent modifications increased the total contract price to $963,-252. In August 1973 Zinger submitted a value engineering (VE) proposal which it estimated would produce a $50,000 savings. The United States amended the contract to take advantage of the proposal.
In September 1974 the United States terminated the contract for its convenience. Zinger submitted a settlement proposal and the parties began a series of negotiating sessions. During the sessions, Zinger raised the issue of payment for its VE proposal. Zinger contended that under the contract it was entitled to 50 percent of the savings realized by the United States as a result of its VE proposal. Initially, the United States responded that such payment was inappropriate. When Zinger raised the issue of the VE claim at the final negotiating session, the United States informed Zinger that the proposed settlement accounted for the VE claim. The United States specifically advised Zinger that the contract modification formalizing the settlement would provide that no outstanding liabilities under the contract remained. The parties informally agreed to a total settlement of $578,057, of which the United States had previously paid $331,-861.30. Relying on the informal agreement, the United States paid Zinger $246,095.70, withholding $100 pending the execution of a contract modification formalizing the agreement.
On July 15, 1977, Zinger sent a letter to the contracting officer stating that the issue of payment for the VE proposal was unresolved. Without responding to the letter, the contracting officer sent the contract modification to Zinger in August 1977. Zinger signed the contract modification on September 12, 1977, but later refused the final payment of $100 tendered by the United States.
On October 11, 1977, Zinger filed a notice of appeal with the board, alleging that the contracting officer had failed to render a decision on the VE claim. The board determined that the contract modification was an accord and satisfaction which barred Zinger’s claim. Accordingly, the board denied Zinger’s appeal. ASBCA No. 22499, 78-2 BCA ¶ 13,461, aff'd, 225 Ct.Cl. 596 (1980).
On January 28, 1982, Zinger filed a complaint with the board alleging that the United States had breached the construction contract. The board denied Zinger’s claim, reasoning that Zinger was barred by res judicata from asserting a different theory of recovery in an effort to relitigate the same claim. ASBCA No. 26733, 83-1 BCA ¶ 16,438.
On August 5, 1983, Zinger filed yet another complaint with the board in which it alleged that newly discovered evidence proved that the final settlement did not incorporate the VE claim. On February 24, 1984, the board dismissed the complaint, holding that the evidence in question (1) was previously available to Zinger and (2) did not dictate, in any event, a result contrary to the earlier decision of the board. 84-1 BCA at 85,-679. We now address Zinger's appeal of this third decision of the board.

Zinger Construction Co. v. United States, 753 F.2d 1053-54 (1985).

The Federal Circuit went on to decide that it did not have jurisdiction over the plaintiff’s appeal from the Board’s decision. It found that the plaintiff could not elect to proceed under the Contract Disputes Act of 1978 because its claim was not pending before a contracting officer on or after the effective date of the Act, which was March 1,1979. In order for the Federal Circuit to assume jurisdiction over a decision by a board, that board had to render a decision pursuant to the Contract Disputes Act. Zinger Construction Co. v. United States, supra, 753 F.2d at 1054. The contract [754]*754itself was signed in 1973. Unsaid by the Federal Circuit but implicit in the decision was the direction that the plaintiff must follow the old Wunderlich Act appeal route, if it intended to appeal. The United States Claims Court could hear the appeal pursuant to the standards of review called for by the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1982).

Although the Federal Circuit had no jurisdiction over the plaintiffs appeal from the Board, it did have an opinion on the merits of the plaintiffs claim. In concluding its discussion it stated:

With respect to Zinger’s VE claim against the United States, there have been five published opinions: three by the ASBCA, one by the United States Court of Claims, and the present one. It is evidence after all of the attention given to Zinger’s claim that there is no merit to it. Pursuant to discretion vested in this court by 28 U.S.C. § 1631 (1982), we should transfer the case to the United States Claims Court if we find that to do so would be in the “interest of justice.” On this record, we cannot so find. Cf. Brown v. United States, 741 F.2d 1374, 1377-78 (Fed.Cir.1984).

DISMISSED.

Zinger Construction Co. v. United States, supra, 753 F.2d at 1055.

Not having been discouraged by this broadside, the plaintiff filed its Wunderlich Act appeal in this Court on February 14, 1986.

Discussion

In its complaint, the plaintiff cites the Tucker Act, 28 U.S.C. § 1491 (1982), the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1982), and United States Claims Court Rule 60(b)(3) as sustaining this Court’s jurisdiction over this matter. Plaintiff seeks judgment in the amount of $25,000 plus interest, costs and fees, as its estimate of the amount due it for its VE proposal.

Using Rule 60(b)(3) as its vehicle, the plaintiff seeks an order from this Court vacating the three prior decisions issued by the Armed Services Board of Contract Appeals (Board) and the opinion issued by this Court’s predecessor, the United States Court of Claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Environmental Safety Consultants, Inc. v. United States
95 Fed. Cl. 77 (Federal Claims, 2010)
Pueblo of Santo Domingo v. United States
16 Cl. Ct. 139 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,411, 13 Cl. Ct. 752, 1987 U.S. Claims LEXIS 222, 1987 WL 21049, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zinger-construction-co-v-united-states-cc-1987.