Pueblo of Santo Domingo v. United States

16 Cl. Ct. 139, 1988 U.S. Claims LEXIS 203, 1988 WL 139999
CourtUnited States Court of Claims
DecidedDecember 22, 1988
DocketNo. 355-D
StatusPublished
Cited by3 cases

This text of 16 Cl. Ct. 139 (Pueblo of Santo Domingo v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pueblo of Santo Domingo v. United States, 16 Cl. Ct. 139, 1988 U.S. Claims LEXIS 203, 1988 WL 139999 (cc 1988).

Opinion

OPINION

FUTEY, Judge.

Plaintiff, Pueblo of Santo Domingo, moves the court to amend a 1969 stipulation and map setting forth defendant’s liability for extinguishing plaintiff’s aboriginal title to certain lands. Defendant contends this court can not entertain plaintiff’s motion because it is untimely and jurisdictionally barred pursuant to section 12 of the Indian Claims Commission Act. For the reasons stated hereinafter, plaintiff’s motion is denied.

Factual Background

Plaintiff's "Motion to Amend Map of Aboriginal Area, and 1969 stipulation as to Standing to Sue, Liability and Area,” now before this court1 arises from an action originally filed in 1951 by the Pueblo of Santo Domingo (Pueblo) with the Indian Claims Commission (ICC).2 The original [140]*140petition demanded rents and profits for trespass and invasions resulting from defendant’s failure to protect the Pueblo’s possessory rights in certain lands. The Bureau of Land Management, prepared a map of the disputed area in August of 1967 based in part upon evidence presented by the Pueblo. The map depicted the aboriginal lands claimed by plaintiff, and other tribes, as well as various land grants in the region.3

On October 29, 1969, the Pueblo and the United States entered into a “Stipulation as to Standing to Sue, Liability and Area” (stipulation), agreeing that the United States was liable for extinguishing the Pueblo’s aboriginal title to 77,273.24 acres as delineated on the map. In a decision of May 9,1973, the ICC determined the extent of the lands taken and the dates of taking. Pueblo of San Ildefonso, et al. v. United States, 30 Ind.Cl.Comm. 234 (1973). The Court of Claims affirmed this holding on appeal. United States v. Pueblo of San Ildefonso, et. al., 206 Ct.Cl. 649, 513 F.2d 1383 (1975).

Upon expiration of the ICC in 1978, all claims not fully adjudicated were transferred to the Court of Claims, upon which jurisdiction over these cases was conferred. 25 U.S.C. § 70v (1976). The present case was transferred to the Court of Claims on October 18, 1978, to determine the amount of compensation due as a result of the taking as set forth in the stipulation.

In 1981, plaintiff filed a motion to withdraw from the 1969 stipulation and map, contending that plaintiff’s attorney entered into the agreement without the Pueblo's knowledge or authority. The court denied this motion as untimely, holding that since relief was not sought seasonably, the Pueblo was bound by the stipulation even if, as plaintiff contended, its attorney was without express authority to enter into the stipulation. Pueblo of Santo Domingo v. United States, 227 Ct.Cl. 265, 647 F.2d 1087 (1981), cert. denied, 456 U.S. 1006, 102 S.Ct. 2296, 73 L.Ed.2d 1300 (1982).

Plaintiff asserts that while researching historical records in 1983, documents were found which indicate that the Pueblo acquired title to certain lands through the purchase of a Spanish land grant. With the exception of 2,400 acres, all of these lands are encompassed by the stipulation and map. The Pueblo’s title to the land arises from a land grant in 1730 from Spanish Governor Bustamante, to Diego Gallegos, a Spanish settler. In 1748 the Pueblo purchased this land for 400 pesos.

In 1983, plaintiff brought an action in the United States District Court for the District of New Mexico asserting title to this land. The district court determined that the Pueblo’s title to the Gallegos grant was valid and unimpaired by the United States. Pueblo of Santo Domingo v. Rael, No. 83-1888 HB (D.N.M., memorandum opinion and order filed May 16, 1986, judgment entered Sept. 4,1986), appeal pending, No. 86-2459 (10th Cir. filed Sept. 28, 1986).

In the present action, plaintiff contends that the 1969 stipulation and map reflecting the extinguished aboriginal title of the Pueblo should be amended to reflect the Pueblo’s ownership of the Gallegos grant. Defendant opposes amendment of the 1969 stipulation and map, averring (1) plaintiff knew of the documents relating to the Gallegos grant and has waited too long to seek relief, and (2) this action, which presents a new claim, is barred by section 12 of the Indian Claims Commission Act (ICCA). Oral argument on the motion to amend was heard by this court on September 22, 1988.

Discussion

Plaintiff claims that evidence of the Gallegos grant, upon which this amendment is based, is newly discovered evidence. It is asserted that if the Gallegos grant was known to the parties in 1969, the stipulation would have reflected the Pueblo’s title to this land.

[141]*141The Claims Court rule concerning relief in instances of newly discovered evidence, RUSCC 60(b), provides in pertinent part:

[T]he court may relieve a party ... from a final judgment, order, or proceeding for ... (2) newly discovered evidence which by due diligence could not have been discovered in time to move for a new trial under rule 59(b)____ The motion shall be made ... not more than one year after the judgment, order, or proceeding was entered or taken, (emphasis added)

Plaintiff’s motion for amendment does not meet the one year time limit of RUSCC 60(b). This court has enforced compliance with the mandatory language of this rule. See Zinger Const. Co. v. United States, 13 Cl.Ct. 752, 755 (1987); Myers v. United States, 8 Cl.Ct. 718, 721 (1985), aff'd, 795 F.2d 1016 (Fed.Cir.1986), cert. denied, 479 U.S. 1099, 107 S.Ct 1322, 94 L.Ed.2d 174 (1987). Accordingly, plaintiff’s motion must be denied.

Furthermore, this court remains unconvinced that evidence of the Gallegos grant is newly discovered. Plaintiff’s own assertions contradict such a finding. The documents which plaintiff now considers newly discovered evidence was presented in claims filed with the New Mexico Surveyor General in 1856, the Court of Private Land Claims in 1893, and submitted to the Bureau of Indian Affairs in 1937.4

In 1981, when plaintiff attempted to withdraw from the same stipulation contemplated in this action, the Court of Claims determined that the motion to withdraw, almost 12 years after entry of the stipulation, was untimely.5 Pueblo of Santo Domingo, 227 Ct.Cl. 265, 647 F.2d 1087. “|T]he conclusion is unavoidable that petitioner has tarried far too long” in bringing its claim to withdraw from the stipulation. 227 Ct.Cl. at 268, 647 F.2d at 1089. “Petitioner’s attempt herein to withdraw from a stipulation entered nearly twelve years ago falls egregiously outside the permissible range of delay.” 227 Ct.Cl. at 267, 647 F.2d at 1089. Similarly, this court finds plaintiff’s motion to amend the 1969 stipulation and map, now nineteen years after its entry, well beyond any reasonable time limit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
16 Cl. Ct. 139, 1988 U.S. Claims LEXIS 203, 1988 WL 139999, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pueblo-of-santo-domingo-v-united-states-cc-1988.