Northwestern Industrial Piping, Inc. v. United States

467 F.2d 1308, 199 Ct. Cl. 540, 1972 U.S. Ct. Cl. LEXIS 126
CourtUnited States Court of Claims
DecidedOctober 13, 1972
DocketNo. 541-71
StatusPublished
Cited by23 cases

This text of 467 F.2d 1308 (Northwestern Industrial Piping, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwestern Industrial Piping, Inc. v. United States, 467 F.2d 1308, 199 Ct. Cl. 540, 1972 U.S. Ct. Cl. LEXIS 126 (cc 1972).

Opinion

Skelton, Judge,

delivered the opinion of the court:

This case involves an appeal by plaintiff, Northwestern Industrial Piping, Inc. (formerly Northwestern Heating and Plumbing Company), from a decision of the Armed Services Board of Contract Appeals (ASBCA), (ASBCA No. 12676, 70-2, BCA ¶ 8552). Review is sought under the familiar standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1970). Plaintiff contracted with the Navy to provide a steam and condensate distribution system at the United States Naval Training Center, Great Lakes, Illinois. A controversy arose as to whether the contract required that above-ground pipe fittings be covered with aluminum jackets. It is plaintiff’s position that the contract required jackets only on straight lengths of pipe and not on fittings and that jacket-ing the fittings constituted a change which required extra compensation in the amount of $16,914 plus interest. Both the contracting officer and the ASBCA found that jacketing the fittings with aluminum was a requirement of the contract specifications and that plaintiff was thus not entitled to extra compensation. The case is presently before this court on cross-motions for summary judgment. We believe that the ASBCA decision is correct and should be upheld for the reasons hereinafter stated.

On January 22, 1965, plaintiff was awarded Contract No. NBy-56358 in the amount of $2,488,577, by the Department of the Navy for the construction of a steam and condensate [543]*543distribution, system connecting a main boiler plant with six existing steam plants servicing recruit barracks, hospital, administrative, and training facilities at the United States Naval Training Center, Great Takes, Illinois. The system ran above and below ground through manholes and over large concrete piers or structural steel frames and involved between 75,000 and 90,000 linear feet of piping.

On January 15, 1965, after receiving notice that it would be awarded the contract, plaintiff executed a subcontract with AC and S, Inc. (then Armstrong Contracting and Supply Corporation) in the amount of $335,000 for furnishing and applying the insulation required by the contract. On June 8, 1965, representatives of AC and S and plaintiff met with Mr. Sobolewski, a Navy engineer in charge of inspecting the project, to discuss the materials and methods to be used in insulating the system prior to AC and S’s making a formal written submittal. What transpired at this meeting is disputed by the jiarties. The representatives of AC and S and plaintiff testified in the administrative proceeding before the Board that at this meeting Sobolewski was advised that the specifications were silent concerning waterproofing of the insulation on above-ground fittings, that good trade practice required waterproofing and that AC and S would use asphalt mastic for this purpose. They further testified that Sobolew-ski was concerned that the fittings would then be black and contrast with the piping being covered with aluminum so they agreed to give the mastic two coats of aluminum paint so that the finish would appear uniform. Sobolewski’s testimony relative to the meeting indicated that he had agreed to the use of asphalt mastic, rather than roof felt, since it would produce a more watertight fitting, but he did not recall any discussion concerning the use of aluminum paint on the fittings. Moreover, he informed them that any agreement reached at this meeting would have to be confirmed in writing by the officer in charge of construction. Thus, while precisely what was said and agreed upon at this meeting is open to question, both sides apparently agree that the aluminum jacketing of above-ground fittings was not explicitly discussed.

[544]*544Following the June 8, 1965, meeting AC and S forwarded to the Navy, through plaintiff, a written submission in the form of a letter dated June 15, 1965, and attached submittal data sheets. This written submission indicated that outdoor fittings would be covered with asphalt mastic, but did not indicate that this mastic would be further covered with aluminum jackets or aluminum paint. The submission was approved by the Navy and returned on July 2, 1965, by a letter which stated that “ [t]he status of APPROVAL on the above listed items is as noted, subject to the requirements of the referenced contract * * A few months after receiving written'approval, AC andS began performance.

In June 1966, the Navy’s field inspector advised AC and S that the contract specifications called for installation of aluminum jackets on above-ground pipe fittings. AC and S notified plaintiff of the problem by letter, denying the existence of any contract requirement to provide aluminum jackets for the fittings, and advising that if the fittings were to be jacketed with aluminum, this must be construed as a change necessitating additional compensation. Sobolewski advised plaintiff that the Navy considered aluminum jacket-ing for the fittings to be a contract requirement and suggested that plaintiff file a claim in accordance with the disputes procedure. AC and S sought to rely on its understanding of the agreement reached at the meeting in June 1965, and advised that it would proceed to paint the fittings with aluminum paint. Then, the Commanding Officer, Midwest Division, Naval Facilities Engineering Command, by letter to plaintiff dated November 22, 1966, directed the installation of aluminum jackets on exterior pipe fittings. Following receipt of this directive, AC and S installed aluminum jackets on all exterior fittings.

Plaintiff’s claim for additional compensation was denied by the contracting officer on July 6, 1967. The ASBCA denied plaintiff’s appeal on October 29, 1970, upon determining that the aluminum, jacketing of the above-ground fittings was a requirement of the contract specifications.

[545]*545 I. Scope or Review

In any Wunderlich Act review the threshold consideration must be the scope of the court’s review. The Wunderlich Act makes Board decisions on questions of fact arising under the contract “final and conclusive unless the same is fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence.” (41 U.S.C. § 321.) On the other hand, Board decisions on questions of law are not entitled to finality (41 U.S.C. § 322) ; no presumption of correctness attaches to them and they are not binding on the court. Gorn Corp v. United States, 191 Ct. Cl. 560, 424 F. 2d 588 (1970); Maxwell Dynamometer Co. v. United States, 181 Ct. Cl. 607, 386 F. 2d 855 (1967).

The dispute in the instant case essentially boils down to a problem of contract specification interpretation. Defendant’s position is that the contract required exterior fittings to be covered with aluminum jackets, while plaintiff takes the stance that the contract was silent on the matter or was at least ambiguous. The Board’s decision herein is not binding on the court because the interpretation of contract specifications is a question of law. Corbetta Constr. Co. v. United States, 198 Ct. Cl. 712, 461 F. 2d 1330 (1972); Jamsar, Inc., v. United States, 194 Ct. Cl. 819, 442 F. 2d 930 (1971); Martin Lane Co. v. United States, 193 Ct. Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Knieper v. United States
38 Fed. Cl. 128 (Federal Claims, 1997)
Blake Construction Co. v. United States
38 Cont. Cas. Fed. 76,537 (Federal Claims, 1993)
Big Chief Drilling Co. v. United States
38 Cont. Cas. Fed. 76,418 (Court of Claims, 1992)
Snap-On Tools, Inc. v. United States
26 Cl. Ct. 1045 (Court of Claims, 1992)
Western States Construction Co. v. United States
38 Cont. Cas. Fed. 76,376 (Court of Claims, 1992)
Pacificorp Capital, Inc. v. United States
37 Cont. Cas. Fed. 76,292 (Court of Claims, 1992)
Alaska American Lumber Co. v. United States
37 Cont. Cas. Fed. 76,286 (Court of Claims, 1992)
Craft MacHine Works, Inc. v. The United States
926 F.2d 1110 (Federal Circuit, 1991)
Craft Machine Works, Inc. v. United States
36 Cont. Cas. Fed. 75,861 (Court of Claims, 1990)
Haehn Management Co. v. United States
34 Cont. Cas. Fed. 75,469 (Court of Claims, 1988)
Zinger Construction Co. v. United States
34 Cont. Cas. Fed. 75,411 (Court of Claims, 1987)
Flexible Metal Hose Manufacturing Co. v. United States
31 Cont. Cas. Fed. 72,120 (Court of Claims, 1984)
Lomas & Nettleton Co. v. United States
1 Cl. Ct. 641 (Court of Claims, 1982)
B. D. Click Co. v. United States
614 F.2d 748 (Court of Claims, 1980)
Molton, Allen & Williams, Inc. v. Hills
449 F. Supp. 492 (District of Columbia, 1978)
Farrell Lines Inc. v. United States
499 F.2d 587 (Court of Claims, 1974)
Sea-Land Service, Inc. v. United States
493 F.2d 1357 (Court of Claims, 1974)
Kaminer Construction Corp. v. United States
488 F.2d 980 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
467 F.2d 1308, 199 Ct. Cl. 540, 1972 U.S. Ct. Cl. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwestern-industrial-piping-inc-v-united-states-cc-1972.