Massman Const. Co. v. United States

60 F. Supp. 635, 102 Ct. Cl. 699
CourtUnited States Court of Claims
DecidedJanuary 8, 1945
Docket45765
StatusPublished
Cited by20 cases

This text of 60 F. Supp. 635 (Massman Const. Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Massman Const. Co. v. United States, 60 F. Supp. 635, 102 Ct. Cl. 699 (cc 1945).

Opinion

MADDEN, Judge.

The plaintiff sues for $88,000 which, it claims, should be added to the price written in a formal contract which it made with the United States, because the plaintiff, by mistake, omitted an item of $88,000 when it computed its bid for the contract.

On October 23, 1940, the United States Engineer Office, New Orleans, Louisiana, advertised for bids for repairing the rubble-mound East jetty at Calcasieu Pass, Louisiana. Bids were to be opened November 7, at 2 P. M. Alternate (b) of the invitation was the one on which the contract here in question was awarded and it provided, as shown in finding 2, for furnishing all labor and materials except stone, which was to be furnished by the Government, for repairing and extending the jetty.

The-plaintiff’s home office was in Kansas City, Missouri. It had been in the contracting business for 25 years, and for 15 years its work had been principally on contracts with the Army Engineers, the contracts having amounted to some $60,000,000. When the plaintiff learned of the advertisement for the jetty project, it was about to complete other work where it had equipment suitable for the jetty job. George E. Owens, its general superintendent and chief estimator was away from Kansas City and returned there about November 4. It was decided that a bid would be made on the jetty job, and that Owens should go to New Orleans and there, after inquiry about local wage rates, fuel costs, freight rates, etc., prepare the bid.

Owens arrived in New Orleans on the morning of November 6, the day before the opening of bids. Since he needed no additional information about the value of the use of the plaintiff’s own equipment on the job, he first listed on an estimate sheet the items of equipment, the value of the use of *642 each piece per month, and the number of months it would be used. From these figures he computed and recorded on the sheet the value of the use of the machinery and equipment for the job as $88,000. This sheet is copied in finding 7. Owens spent the rest of November 6 gathering local information, and he then on a second sheet estimated the costs of labor in placing stone, supervision, fuel, insurance, and other miscellaneous matters. On a third sheet he estimated the labor costs of towing and unloading. He finished these sheets after midnight on November 6 and gathered up his scattered papers and put them in a brief case, intending to make up his final estimate and the plaintiff’s formal bid on the next morning.

On the morning of November 7, Owens, in taking the papers out of his brief case to complete his work, failed to take out the first sheet prepared by him the day before, on which sheet he had set down the items of value of the use of equipment amounting to $88,000. He therefore, in his final computation, as shown in finding 9, omitted that amount from consideration, and the bid which he submitted was lower by that amount than it would have been but for that omission. He filed the bid shortly before 2 P. M. on November 7, and it and three other bids were opened and read at that hour, as was the Government’s own estimate of the cost of the work.

The bids and the Government’s estimate are shown in finding 12. As explained in that finding, the Government’s estimate included items which would not have been included in a contractor’s bid, so its estimate, on a basis comparable to that of the bidders, would have been about $400,000, as against the plaintiff’s bid of $367,000. The three bids by other contractors were much higher, being $620,400, $798,600, and $935,-000. The District Engineer and his assistant, who were in charge of the opening of bids, had no thought that plaintiff’s bid involved a mistake. They talked to Owens about when the work would be started, whether plaintiff’s equipment was adequate and other relevant matters. Owens felt that for some reason his bid was too low, but thought he had used poor judgment in his estimates. He said nothing to the Governmental officials, however, about his feeling that there might have been a mistake.

The way in which the mistake in the bid had been made was not discovered by the plaintiff until November 18. The manner of its discovery is recited in finding 15. Upon its discovery the plaintiff wrote the Engineer Office at New Orleans. See finding 16. It requested that its bid be increased by $88,000, or be rejected without any liability on the bid bond. The District Engineer merely acknowledged this letter, on November 25, and on December 18 wrote the plaintiff accepting its bid as made, denying its request to change its bid and saying:

“You are advised that you have the right to file a claim with the District Engineer for submission through channels to the Comptroller General for further consideration.”

The contract and bonds were enclosed for signature by the plaintiff.

The plaintiff considered the advisability of refusing to sign the contract. One of the principal reasons why it did not refuse was that refusal might affect its future relations with the Government agencies with which, as we have seen, most of its business had been done for some years past. Another reason was the fact that it had put up a bond guaranteeing its bid. It was also hopeful that if it filed a claim, as tfie District Engineer had written that it might, the claim would be allowed.

About December 28, 1940, the plaintiff signed the contract, furnished the requisite bond, and forwarded these to the District Engineer, together with a protest, the text of which is quoted in finding 19, and a letter to the Comptroller General. The contract was approved by the Division Engineer January 8, 1941. The plaintiff’s let•ter to the Comptroller General recited the facts concerning the mistake substantially as we have found them, and asked that it be compensated for the use of its equipment, the value of which use it had not included in its bid.

The plaintiff’s officials had conferences with officials of the Corps of Engineers, and submitted affidavits and information to them. The Corps of Engineers forwarded the plaintiff’s letter to the Comptroller General on June 13, 1941 with a letter, a part of which is quoted in finding 20, saying there was doubt whether a mistake had been made, and that the estimate was prepared “in an extremely careless manner.” It further said:

“It is thought that it would not be unconscionable to require the contractor to perform the work at its bid price. The present record does not establish that the contractor would incur a loss in performing *643 at the contract price. It is recommended that the claim be disallowed.”

The Comptroller General disallowed the claim. The plaintiff performed the contract and was paid the contract price, except $100 which has not been paid because of the plaintiff’s refusal to sign the final voucher.

The plaintiff urges here that its contract with the Government should be reformed and enforced as reformed because of either (1) mistake of fact on its part and unconscionable conduct on the part of the Government, or (2) mutual mistake of fact.

At the time the contract was awarded to the plaintiff, pursuant to its bid, and at the time it signed the contract, the plaintiff was not mistaken.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great Lakes Dredge & Dock Co. v. United States
60 Fed. Cl. 350 (Federal Claims, 2004)
Overstreet Electric Co. v. United States
47 Fed. Cl. 728 (Federal Claims, 2000)
California Marine Cleaning, Inc. v. United States
42 Cont. Cas. Fed. 77,398 (Federal Claims, 1998)
Arthur Forman Enterprises, Inc. v. United States
37 Cont. Cas. Fed. 76,079 (Court of Claims, 1991)
Vanguard Security Inc. v. United States
20 Cl. Ct. 90 (Court of Claims, 1990)
Prineville Sawmill Company, Inc. v. The United States
859 F.2d 905 (Federal Circuit, 1988)
Prineville Sawmill Co. v. United States
34 Cont. Cas. Fed. 75,425 (Court of Claims, 1988)
Eagle Construction Corp. v. United States
31 Cont. Cas. Fed. 72,046 (Court of Claims, 1984)
P. Francini & Co. v. United States
30 Cont. Cas. Fed. 70,979 (Court of Claims, 1983)
Wickham Contracting Co. v. United States
546 F.2d 395 (Court of Claims, 1976)
Dale Ingram, Inc. v. United States
475 F.2d 1177 (Court of Claims, 1973)
Chris Berg, Inc. v. The United States
426 F.2d 314 (Court of Claims, 1970)
Wender Presses, Inc. v. The United States
343 F.2d 961 (Court of Claims, 1965)
Albert & Harrison, Inc. v. United States
68 F. Supp. 732 (Court of Claims, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
60 F. Supp. 635, 102 Ct. Cl. 699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massman-const-co-v-united-states-cc-1945.