Robert L. Guyler Co. ex rel. McCarty Corp. v. United States

593 F.2d 406, 25 Cont. Cas. Fed. 83,090, 219 Ct. Cl. 403, 1979 U.S. Ct. Cl. LEXIS 64
CourtUnited States Court of Claims
DecidedFebruary 21, 1979
DocketNo. 51-77
StatusPublished
Cited by6 cases

This text of 593 F.2d 406 (Robert L. Guyler Co. ex rel. McCarty Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robert L. Guyler Co. ex rel. McCarty Corp. v. United States, 593 F.2d 406, 25 Cont. Cas. Fed. 83,090, 219 Ct. Cl. 403, 1979 U.S. Ct. Cl. LEXIS 64 (cc 1979).

Opinion

PER CURIAM;

This case comes before the court on plaintiffs request, filed April 4, 1978, for review by the court of the recommended decision of Trial Judge Harry E. Wood, filed February 1, 1978, pursuant to Rule 166(c), on defendant’s motion and plaintiffs cross-motion for summary judgment, having been submitted to the court on the briefs and oral argument of counsel. Upon consideration thereof, since the court agrees with the trial judge’s recommended decision, as hereinafter set forth, it hereby affirms and adopts the decision as the basis for its judgment in this case. It is, therefore, concluded as a matter of law that the Board’s denial of plaintiffs claim to an equitable adjustment has not been shown to be arbitrary, capricious, unsupported by substantial evidence, or legally erroneous. Accordingly, defendant’s motion for summary judgment is granted, plaintiffs cross-motion for summary judgment is denied and the petition is dismissed.

OPINION OF TRIAL JUDGE

WOOD, Trial Judge:

In this action, before the court for review under the standards of the Wunderlich Act, 41 [406]*406U.S.C. §§ 321-22 (1970), plaintiff1 contends that administrative denial2 of an equitable adjustment for the cost of furnishing some 400 dishwashers in military housing units being renovated at Fort Bragg, North Carolina, is arbitrary, capricious, unsupported by substantial evidence, and erroneous as a matter of law.

Plaintiffs position is that under the contra proferentem doctrine,3 as well as for a considerable number of other reasons, the administrative decisions here under review are defective under Wunderlich Act standards, and that plaintiff is accordingly entitled to judgment herein. Defendant contends that the said decisions are supported by substantial evidence and legally correct, and should, therefore, be upheld. For reasons to be stated, it is concluded that plaintiff is not entitled to recover.

I

The facts found by the Board, or otherwise justified by the administrative record,4 are as follows:

On March 22, 1974, defendant, acting through the U. S. Army Engineer District, Mobile, Alabama, issued Invitation for Bids DACA 21-74-B-0105 ("the IFB”) for "FY-74 Family Housing Improvements” at Fort Bragg, North Carolina. The original date set for bid opening does not appear in the administrative record,5 but by an amendment to the IFB a bid opening date of May 23, 1974, was ultimately established.

As originally promulgated, IFB Special Provision 30, "IDENTIFICATION OF GOVERNMENT FURNISHED [407]*407PROPERTY (1968 SEP)”, provided that the government would furnish to the contractor, for incorporation or installation in the work or use in its performance, 540 dishwashers. The Fort Bragg family housing units to be renovated included 400 Wherry Housing Units and 140 Capehart Housing Units, and installation of a dishwasher in each such unit apparently was contemplated.6

Section 11A of the specifications attached to the IFB was captioned "DISHWASHERS AND FUTURE DISPOSERS”, and provided in part as follows:

1. SCOPE OF WORK:
(A) WORK INCLUDED: This section includes the installation of Government furnished dishwashers * * *
(B) RELATED WORK NOT INCLUDED IN THIS SECTION: The following items of related work are not included in this section:
* * * * *
(2) Plumbing work, including installing dishwashers and water, waste, and vent piping and connections to them.
* * * * *
3. INSTALLATION:
(A) GENERAL: Dishwashers shall be installed in accordance with requirements of Section 15A, PLUMBING; Section 16A, ELECTRICAL, INTERIOR; and Section 10C, KITCHEN CABINETS AND EQUIPMENT.

As originally promulgated, Section 15A, "PLUMBING”, contained the following provisions:

1. SCOPE OF WORK:
(A) WORK INCLUDED: This section includes the plumbing system complete within all buildings and connection to sewer and water services at a point not to exceed 5 feet outside of building walls.
[408]*408(B) RELATED WORK NOT INCLUDED IN THIS SECTION: The following items of related work are not included in this section:
(1) Furnishing garbage disposers and dishwashers.
10.FIXTURES AND FIXTURE TRIM:
*****
(D) FIXTURES:
*****
(4) Item P-(4), Kitchen sink, stainless steel, flat rim, double compartment, 32 inches by 21 inches by 5% inches deep.* * [7]

By Amendment 0002, bearing an "effective date” of May 3, 1974, defendant modified the IFB in a number of particulars. Among other things, both Special Provision 30 ("IDENTIFICATION OF GOVERNMENT FURNISHED PROPERTY (1968 SEP)”) and Section 11A "DISHWASHERS AND FUTURE DISPOSERS” were omitted. Amendment 0002 did not modify the "SCOPE OF WORK” clause of Section 15A "PLUMBING”, with the result that Section 15A 1(B) continued to provide that "Furnishing garbage disposers and dishwashers” was "RELATED WORK NOT INCLUDED IN THIS SECTION”. Section 15A 10(D)4, listing and describing a kitchen sink, was, however, modified by the following addition:

(a) Special requirement: Kitchen sinks for all dwelling units shall have special contractor furnished, "under the sink” type dishwashers. The kitchen sinks shall be double basin specially designed and recommended for use with undersink dishwashers. Refer to detail on plans. Special features shall include the following: * * *l8l [Emphasis supplied.]

Further, Section 15A 11, "INSTALLATION”, was modified9 by making paragraph I, "DISHWASHERS AND [409]*409FUTURE GARBAGE DISPOSERS” read in pertinent part as follows:

Provide water, waste, and vent piping for, and make final connections for dishwashers which will be furnished by the Contractor as hereinbefore specified. [Emphasis supplied.]

Upon receipt of the IFB as originally promulgated, plaintiff solicited bids from various specialty subcontractors, and the McCarty Company ("McCarty”) elected to bid on the mechanical portion of the contract work (which included plumbing). Both plaintiff and McCarty were experienced contractors and they had frequently worked together on renovation projects similar to that covered by the IFB.

Plaintiffs vice president and secretary, Mr. Walker, who prepared plaintiffs bid on the contract in suit, testified that, with respect to mechanical work, it was his practice to take the lowest responsible subcontractor bid price and insert it on his bid "recap” sheet. Mr. Walker did not read Section 15A as modified by Amendment 0002, but instead relied upon McCarty to go through the said amendment and discover any changes pertaining to mechanical work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hydro Group, Inc. v. United States
35 Cont. Cas. Fed. 75,723 (Court of Claims, 1989)
AABCO, Inc. v. United States
31 Cont. Cas. Fed. 71,346 (Court of Claims, 1983)
R-D Mounts, Inc. v. United States
30 Cont. Cas. Fed. 71,059 (Court of Claims, 1983)
Enrico Roman, Inc. v. United States
30 Cont. Cas. Fed. 70,907 (Court of Claims, 1983)
FFR Building Specialties Corp. v. United States
29 Cont. Cas. Fed. 81,999 (Court of Claims, 1981)
S. J. Groves & Sons Co. v. United States
495 F. Supp. 201 (D. Colorado, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
593 F.2d 406, 25 Cont. Cas. Fed. 83,090, 219 Ct. Cl. 403, 1979 U.S. Ct. Cl. LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robert-l-guyler-co-ex-rel-mccarty-corp-v-united-states-cc-1979.