The Brezina Construction Company, Inc. v. The United States

449 F.2d 372, 196 Ct. Cl. 29, 1971 U.S. Ct. Cl. LEXIS 3
CourtUnited States Court of Claims
DecidedOctober 15, 1971
Docket118-70
StatusPublished
Cited by11 cases

This text of 449 F.2d 372 (The Brezina Construction Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Brezina Construction Company, Inc. v. The United States, 449 F.2d 372, 196 Ct. Cl. 29, 1971 U.S. Ct. Cl. LEXIS 3 (cc 1971).

Opinion

COLLINS, Judge:

In this case the court once again finds itself faced with the task of resolving a dispute as to contract interpretation where its only guide is an ambiguous contract. There is no dispute as to any of the material facts, and the case is before the court on the parties’ cross-motions for summary judgment.

In March 1967, plaintiff was awarded a contract, in the amount of $1,343,000, for the construction of two barracks and an officers’ mess at the Naval Station at Long Beach, California. The invitation for bids issued by the Government solicited bids on the basis of four different alternatives (or items) of which only the first two are necessary to our consideration. The basis of bid item 1 was “the entire work complete in accordance with all requirements indicated and specified.” Bid item 2 was identical with bid item 1 except that, under bid item 2, casework in the living rooms of the barracks was expressly omitted. The contract was awarded on the basis of bid item 2.

The present controversy arose on January 29, 1969, when the contracting officer issued a deductive change order purporting to delete 919 lighting fixtures (types 36, 36A, and 52) from the living rooms of the barracks, thereby reducing the contract price by $33,600. This dollar amount represents the un-controverted value of the fixtures as shown by a detailed Government estimate in the record. Plaintiff protested, claiming, as it does here, that the fixtures in question were not a contract requirement under bid item 2, and, for that reason, it had not included an amount for the fixtures in its bid.

Plaintiff’s protest was based on its interpretation of bid item 2. According to this interpretation, the omission of casework carried with it the omission of all the lighting fixtures attached to the casework. Since all of the 919 fixtures involved were attached to the casework, they were not a contract requirement under bid item 2.

The contracting officer’s final decision was adverse to plaintiff, and an appeal to the Armed Services Board of Contract Appeals followed. The board’s decision, likewise, was adverse to plaintiff. This suit followed. The parties are in agreement that the only issue before the court is one of contract interpretation, a legal issue, and that the board’s decision is not entitled to finality under the Wunderlich Act, 41 U.S.C. §§ 321-322 (1964).

Before proceeding with the discussion of the issues, it would be well to identify with more precision the technical terms involved in this dispute. “Casework” refers to wooden interior trim consisting of such items as beds, desks, wardrobes, and wall partitions. These built-in units are part of the permanent structure and function in lieu of individual pieces of furniture. The type 36, 36A, and 52 lighting fixtures, which are the subject of the dispute, are all depicted in the drawings accompanying the specifications as attached to the casework under bid item l. 1 The type 36 fixture is a *374 shelf-mounted fluorescent fixture, 24 inches long. Type 36A is identical except that it is 48 inches long. The type 52 fixture is “a wall, or shelf mounted, shelf light 36" long x 10%©" deep.”

The Government’s position, of course, is that under bid item 2 the light fixtures were required to be furnished, notwithstanding the fact the casework to which the fixtures were to be attached was omitted. This position has its basis in two paragraphs of the specifications under the general heading of “Casework” :

6B.4.7 Electrical fixtures, where indicated, shall be provided by the casework manufacturer. Fixtures shall bear the Underwriters Laboratories, Inc. label of approval, and shall be furnished, complete, with 3-prong grounding plugs and sufficient cord to enable connection to the wall outlets indicated on the electrical drawings.

6B.4.7.1 Type. Fixtures shall be stem mounted, rotating type, 15 watt fluorescent, self contained without remote ballast. Overall outside dimensions of the fixtures shall be approximately 2 inches high by 3 inches deep by 22 inches long. Exterior finish shall be manufacturer’s standard baked-on enamel. Reflector shall be spherical shape with white baked-on enamel finish. Fixture shall be complete with push-pull switch. Fixtures of the type specified may be obtained from “Lightolier”, 2515 South Broadway, Los Angeles, California. Outlets shall be 3-prong grounding type, 15 amps, and conforming to requirements for outlets as specified in the section entitled “Electrical Work.” Fixtures by other manufacturers which are similar and equal in performance to the type specified may be provided, subject to prior approval.

According to the Government’s view, which was also the board’s, paragraph 6B.4.7.1 provides the decisive definition of which fixtures were a part of the casework under bid item 1 and, therefore, which fixtures were to be omitted with the casework under bid item 2. This being the case, the only fixtures to be omitted under bid item 2 would be 15 watt fluorescent fixtures approximately 2 inches high by 3 inches deep by 22 inches long. Therefore, the type 36, 36A, and 52 fixtures would not be omitted since they are, respectively, 24, 48, and 36 inches in length and, in addition, type 52 is 10%© inches deep and uses a 30 watt lamp. According to the Government, the 919 fixtures in question are not described in 6B.4.7.1. We think otherwise.

We agree with the Government that types 36, 36A, and 52 are excluded from 6B.4.7.1. But we do not agree that this factor is controlling, for, when 6B.4.7.1. is read with 6B.4.7, its parent, the result is an ambiguity.

Paragraph 6B.4.7 provides that “[e'jlectrical fixtures, where indicated [on the drawings], shall be provided by the casework manufacturer. Fixtures * * * shall be furnished, complete, with 3-prong grounding plugs and sufficient cord to enable connection to the wall outlets * * *.” In the first place, it is obvious that a conflict with 6B.4.7.1 is apparently created by the first sentence of 6B.4.7 since type 36, 3 6A, and 52 fixtures are all indicated on the drawings. If all three fixtures are required to be furnished by the casework manufacturer under bid item 1, the natural reading of bid item 2 would exclude the fixtures. Moreover, the apparent conflict between the paragraphs and the ambiguity of the specifications is compounded by the second sentence of 6B.4.7, because the 15 watt fluorescent fixture detailed in 6B.4.7.1 has a rigid conduit connection and no cord attached to it. In fact, the only fixture involved *375 here which has a cord and a 3-prong ground plug is type 36.

It is in cases such as this one, where the contract is ambiguous and where there are no extraneous aids to interpretation, that the courts are forced to resort to guidelines based on what is thought to be sound policy rather than on the intent of the contracting parties. The rule, often repeated by this court, is that if a Government contract is ambiguous and if the construction placed upon it by the contractor is reasonable, the contractor’s construction will be adopted, unless the parties’ intention is otherwise affirmatively revealed. See, e. g., Morrison-Knudsen Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baistar Mechanical, Inc. v. United States
128 Fed. Cl. 504 (Federal Claims, 2016)
Hydro Group, Inc. v. United States
35 Cont. Cas. Fed. 75,723 (Court of Claims, 1989)
Blough v. United States
35 Cont. Cas. Fed. 75,675 (Court of Claims, 1989)
Avedon Corp. v. United States
35 Cont. Cas. Fed. 75,592 (Court of Claims, 1988)
Solar Turbines International v. United States
31 Cont. Cas. Fed. 71,259 (Court of Claims, 1983)
Sofarelli Associates, Inc. v. United States
30 Cont. Cas. Fed. 70,530 (Court of Claims, 1982)
Chemical Technology, Inc. v. United States
645 F.2d 934 (Court of Claims, 1981)
Merando, Inc. v. United States
475 F.2d 601 (Court of Claims, 1973)
Dale Ingram, Inc. v. United States
475 F.2d 1177 (Court of Claims, 1973)
Corbetta Construction Co. v. United States
461 F.2d 1330 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
449 F.2d 372, 196 Ct. Cl. 29, 1971 U.S. Ct. Cl. LEXIS 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-brezina-construction-company-inc-v-the-united-states-cc-1971.