Corbetta Construction Co., Inc. v. The United States

408 F.2d 450, 187 Ct. Cl. 409, 1969 U.S. Ct. Cl. LEXIS 140
CourtUnited States Court of Claims
DecidedMarch 14, 1969
Docket369-65
StatusPublished
Cited by2 cases

This text of 408 F.2d 450 (Corbetta Construction Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corbetta Construction Co., Inc. v. The United States, 408 F.2d 450, 187 Ct. Cl. 409, 1969 U.S. Ct. Cl. LEXIS 140 (cc 1969).

Opinion

OPINION

PER CURIAM:

This case was referred to the trial commissioner * with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 57(a). The commissioner has done so in an opinion and report filed on March 18,1968. Plaintiff excepted to the commissioner’s “Ultimate Finding” and to that portion of the recommended conclusion of law providing that plaintiff is not entitled to recover on its first claim and for its dismissal. Defendant requested that the court adopt the commissioner’s recommended opinion *451 and factual findings. The case has been submitted to the court on oral argument of counsel and the briefs of' the parties. Since the court agrees with the commissioner’s opinion, findings and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. See Seeds v. United States, 92 Ct.Cl. 97 (1940), cert. denied, 312 U.S. 697, 61 S.Ct. 731, 85 L.Ed. 1131 (1941) ; Cannon Construction Co. v. United States, 319 F.2d 173, 162 Ct.Cl. 94 (1963) ; Brock & Blevins Co., Inc. v. United States, 343 F.2d 951, 170 Ct.Cl. 52 (1965) ; Columbus Jack Corp. v. United States, 170 Ct.Cl. 902 (1965) (order). Therefore, plaintiff is not entitled to recover on its first claim which is dismissed. Plaintiff’s second claim is remanded to the trial commissioner for trial on the merits.

OPINION OF COMMISSIONER

BENNETT, Chief Commissioner:

In 1953, plaintiff entered into a contract with the Navy to construct a dry dock at the Brooklyn, New York, Naval Shipyard. In July 1955, plaintiff notified the Navy that it had encountered changed conditions during the course of construction for which it requested an equitable adjustment and time extension. On April 5, 1957, Change Order L and an accompanying letter agreement were signed allowing plaintiff an equitable adjustment of $2,600,000 for the changed conditions.

Subsequently, plaintiff filed suit here, its petition consisting of three separate claims. In its first claim, it seeks damages of $1,500,000 for delays allegedly caused by the changed conditions that were the subject matter of the April 5, 1957, equitable adjustment. In its second claim, it seeks damages of $1,000,000 for what is alleged (in part) to be unreasonable delay by the Navy in 1958 and 1959 in furnishing it necessary drawings and giving it notices to proceed. 1

Defendant moved for summary judgment on plaintiff’s first and second claims on the ground that Change Order L and the accompanying letter agreement constituted an accord and satisfaction which assertedly discharged completely plaintiff’s claim for damages. Plaintiff in turn filed a cross-motion for partial summary judgment on the first claim. On March 24, 1967, the court denied defendant’s motion and plaintiff’s cross-motion for partial summary judgment without prejudice and ordered that “the case * * * [be] remanded to the trial commissioner for trial on the issue of the parties’ intentions with respect to the scope of Change Order ‘L’, dated April 5, 1957, and the scope of the settlement agreement embodied in the accompanying letter of the same date.”

The facts, as established at trial, are set out in detail in the accompanying findings. As to the first claim of the petition, the record establishes that the parties intended by Change Order L and the accompanying letter agreement to settle any and all claims for additional costs, including delay costs arising out of the changed conditions. The record further establishes that the parties did not intend that Change Order L and the accompanying letter constitute a settlement of the second claim of the petition —and defendant so concedes.

It is concluded that plaintiff’s first claim should be dismissed and that the second claim should be remanded to the trial commissioner for a trial on the merits.

FINDINGS OF FACT

1. On August 4, 1953, plaintiff entered into a lump-sum, fixed-price contract with the Department of the Navy, Bureau of Yards and Docks (hereafter referred to as the Bureau), in the amount of $8,662,000. The general nature of the work required to be performed was the construction of the Brooklyn, New York, Navy Yard, of a reinforced concrete dry *452 dock approximately 770 feet in length by 116 feet in width by 41 feet in depth upon the site of an existing timber dry dock (Dry Dock No. 3) of smaller dimensions.

2. Under the terms of the contract the plaintiff was required, among other things, to demolish the existing dry dock, to excavate large quantities of earth for the installation and construction of the new and enlarged dry dock, to erect a cofferdam of steel sheeting around the perimeter of the excavation, and to shore and brace the excavation during the course of construction in the manner shown by plans and specifications prepared by the defendant and forming part of the contract.

3. The contract contained the standard form Changed Conditions, Changes and Extras, and Disputes clauses. It did not contain a Suspension-of-Work clause.

4. Upon execution of the contract, plaintiff commenced performance which was to be completed by July 25, 1955. The contract was amended and modified by Change Orders A through C-C which, among other things, extended the time for completion. On February 3, 1960, the Navy accepted plaintiff’s work as completed.

5. (a) After commencing construction, plaintiff, on July 21, 1955, wrote to the officer in charge of construction (OICC), Third Naval District, New York City, claiming that it had encountered changed conditions within the scope of the Changed Conditions clause, resulting in alleged serious slippage of soil around the edges of the dock. An equitable adjustment and a time extension were requested.

(b) More particularly, the bases of plaintiff’s claim were that it had encountered changed conditions within the meaning of article 4(b), as follows:

Subsurface or latent conditions at the site materially differing from those shown on the drawings or indicated in the specifications, including, but not limited to, the presence of varved layers of silt or silty clay, pockets of unstable soil commonly known in the New York area as “bulls-liver”, cavities, boulders, piles located otherwise than shown, piles materially shorter than shown, and heavy construction work being done by others in the vicinity of Drydoek No. 3; and
Unknown conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as being inherent in work of the character provided for in the drawings and specifications in that plaintiff encountered excessive forces in the soil in and around the site which were unforeseen and unanticipated by plaintiff and the Navy.

6. (a) Under usual procedures in the Navy, construction contracts are administered in the field.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Corbetta Construction Co. v. United States
461 F.2d 1330 (Court of Claims, 1972)
Emerson-Sack-Warner Corporation v. The United States
416 F.2d 1335 (Court of Claims, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
408 F.2d 450, 187 Ct. Cl. 409, 1969 U.S. Ct. Cl. LEXIS 140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corbetta-construction-co-inc-v-the-united-states-cc-1969.