Norcoast Constructors, Inc., and Morrison-Knudsen Company, Inc., a Joint Venture v. The United States

448 F.2d 1400, 196 Ct. Cl. 1, 1971 U.S. Ct. Cl. LEXIS 1
CourtUnited States Court of Claims
DecidedOctober 15, 1971
Docket376-68
StatusPublished
Cited by5 cases

This text of 448 F.2d 1400 (Norcoast Constructors, Inc., and Morrison-Knudsen Company, Inc., a Joint Venture v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norcoast Constructors, Inc., and Morrison-Knudsen Company, Inc., a Joint Venture v. The United States, 448 F.2d 1400, 196 Ct. Cl. 1, 1971 U.S. Ct. Cl. LEXIS 1 (cc 1971).

Opinions

NICHOLS, Judge.

This is another proceeding, before us on cross-motions for summary judgment, to review a disputes clause decision of the Armed Services Board of Contract Appeals (ASBCA) under the standards of the Wunderlich Act, 41 U.S.C. §§ 321-322. We have jurisdiction under 28 U.S.C. § 1491. The plaintiff, a joint venture, entered into a negotiated Contract, DA 95-507-Eng — 2112 (NEG) with the Army Engineers, having the usual standard Change Order and Disputes provisions. The work was in support of Project Long Shot, the underground explosion of a nuclear device at Amchitka, Alaska, a remote island in the Aleutians. Plaintiff was to do various items of work, totalling $4,222,780. Among these were the supply of gasoline and diesel fuel, as required, including storage, dispensing, and transport about the island on plaintiff’s tank trucks. One item, No. 43, was:

Furnish and Install Diesel Fuel

Storage Facilities ........ $139,900.

In fulfillment of this item, plaintiff constructed on the island two welded steel tanks for the diesel fuel, of 18,000 and 6,000 barrels capacity, respectively. After the contract was otherwise performed in full, plaintiff and defendant both claimed to own these tanks. That is the entire dispute. The ASBCA held for the defendant, but we disagree. Its construction of the contract is erroneous as a matter of law, and rests on some subsidiary fact findings that do not have the support of substantial evidence. Plaintiff is entitled to an equitable adjustment, for a constructive change order. As the Board postponed consideration of quantum, we will suspend proceedings here to enable it to determine that issue.

Plaintiff was one of four bidders. The original specifications on which it bid left the capacity and kind of the diesel fuel storage facilities unstated and within the contractor’s discretion, in light, evidently, of the anticipated rate of use and frequency of arrivals of tankers at the island. The estimated overall quantity of diesel fuel to be supplied was 950,000 gallons. A specification (21-05) provided in part:

* * *. Gasoline shall be stored in barrel or other approved containers. The locations, methods and quantities of diesel fuel storage shall be as indicated on the drawings or as approved by the Contracting Officer.

A drawing showed a 50,000 gallon “pillow tank” as a “typical installation detail,” for diesel fuel storage. The term “pillow tank” recurs constantly in the record, is nowhere defined, and is unfamiliar to the court. Counsel on oral argument here stated that it was a rubber portable container, having • a relatively short useful life, as compared to a steel tank. The pillow tank in the drawing is bedded in sand which is dug away beneath it and built up around its sides: thus apparently supporting the tank and restraining escape of fuel in case of a rupture. The tank, full, resembles in shape a bed pillow, no doubt thus accounting for the name.

Before the award to plaintiff the parties, on March 23rd and 25th, 1965, had two conferences, the minutes of which were taped and made a part of the contract by contract stipulation. Defendant’s representatives wanted to know how plaintiff would “handle” petroleum. Plaintiff’s representative, Mr. Egge, said they had located “on the shelf” a [1402]*1402new 500,000 gallon bolted tank, and they would use this for diesel fuel, with pillow tanks. Mr. George, for defendant, said the bolted tank would leak, as their experience showed. They urged no objection to pillow tanks. There was much discussion about the alleged leaking of the bolted tank and plaintiff failed to convince that it would not leak, but on the other hand, defendant did not flatly disapprove it, apparently expecting not to pay for any fuel that leaked out.

After these conferences, but before final signature of the contract, the parties made alterations in it, including a new specification (21-06) to follow the one previously quoted:

1. There is “no serious objection” to the use of pillow tanks for * * * Diesel oil if the following precautions are taken: [precautions follow]

Though the minutes do not so reflect, plaintiff during or after the conferences decided to buy and install the welded tanks. According to Mr. Egge’s testimony, it was because of the fear of leakage from a bolted tank, but the Government did not participate in the decision, nor specify the design of the tanks. There is no evidence that plaintiff communicated the decision to defendant prior to the award, and the new specification 21-06 suggests that plaintiff did not. After the conference the contract right of plaintiff to furnish only rubber pillow tanks thus not only subsisted but was re-emphasized. The record shows pillow tanks were cheaper to install, and why plaintiff did not use them exclusively is a question to which the record gives no clear answer. Mr. Egge did testify “we wanted to get the contract and we figured that this was an item that might please them if we furnished the welded tanks.” Plaintiff also hoped that its ownership of these tanks in place on Amchitka would enable it to underbid competitors for future Government contracts involving Amchitka. This hope was not communicated to defendant so far as appears.

Plaintiff after award sent a crew of boilermakers to Amchitka to assemble and weld the tanks. The evidence shows without contradiction that this on-site assembly cost more than the unassembled parts and also that the tanks would have had some salvage value if they had had to be removed, despite the necessity of cutting them up for shipment out. Mr. Egge figured that the tanks were worth about $180,000 in place at Amchitka.

Shortly after the award defendant presented plaintiff with a change order specifying, among other things, what items that plaintiff had installed would remain property of the Government (SC-48). This list did not include the welded tanks. The amendments then made to Specification 21 also say nothing about these tanks.

Defendant allowed plaintiff to remove its pillow tanks without any argument, when the contract was performed. The steel tanks had to be left there as they still had oil in them. The Board says plaintiff had used the pillow tanks for “its convenience” thereby somehow differentiating them from the steel tanks.

The Board holds that the welded steel tanks (but not the pillow tanks) were an “inducement” for award of the contract. Defendant’s capable counsel admitted in argument that the alleged “inducement” to defendant could not be found in the written contract and in effect was an oral modification thereof. Possibly defendant wants us to reform the contract as not reflecting the true agreement of the parties. The first question is one of proof. It can hardly be doubted that the party relying on an oral modification must be the one to prove that it was made. Defendant offered nothing to show when or how the “inducement” was communicated to it. The Board made no finding how it was communicated. Defendant’s counsel here relies wholly on Mr. Egge’s testimony, already quoted, that they wanted the contract and figured the welded steel tanks might please the Engineers. Plaintiff ordered the tanks on March 30th, 1965, five days after the second [1403]*1403conference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ladum v. United States
32 Cont. Cas. Fed. 72,456 (Court of Claims, 1984)
Salem Engineering & Construction Corp. v. United States
31 Cont. Cas. Fed. 71,312 (Court of Claims, 1983)
Norcoast Constructors, Inc. v. United States
477 F.2d 929 (Court of Claims, 1973)
Corbetta Construction Co. v. United States
461 F.2d 1330 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
448 F.2d 1400, 196 Ct. Cl. 1, 1971 U.S. Ct. Cl. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norcoast-constructors-inc-and-morrison-knudsen-company-inc-a-joint-cc-1971.