Paschen Contractors, Inc. v. City of Kankakee

819 N.E.2d 353, 353 Ill. App. 3d 628, 289 Ill. Dec. 196
CourtAppellate Court of Illinois
DecidedNovember 22, 2004
Docket3-03-0602
StatusPublished
Cited by16 cases

This text of 819 N.E.2d 353 (Paschen Contractors, Inc. v. City of Kankakee) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paschen Contractors, Inc. v. City of Kankakee, 819 N.E.2d 353, 353 Ill. App. 3d 628, 289 Ill. Dec. 196 (Ill. Ct. App. 2004).

Opinion

JUSTICE McDADE

delivered the opinion of the court:

Plaintiff, Paschen Contractors, Inc. (Paschen), appeals from an order striking portions of its complaint and denying its motion to file a third amended complaint and a grant of summary judgment in favor of defendants, City of Kankakee (Kankakee) and Donohue & Associates, Inc. (Donohue). For the following reasons, we reverse.

BACKGROUND

In 1984, Kankakee advertised for bids to build a wastewater treatment facility (the project) that would permit expansion of sanitary sewers in the city. Kankakee hired Paschen in April 1986, pursuant to a general contract, as the general contractor for the project. The general contract designated Donohue as the project engineer and the authorized representative of Kankakee. The general contract provided as follows:

“6.9 *** Nothing in the Contract Documents shall create any contractual relationship between [Kankakee] or [Donohue] and any Subcontractor or other person or organization having a direct contract with [Paschen], nor shall it create any obligation on the part of [Kankakee] or [Donohue] to pay or see to the payment of any moneys due any Subcontractor or other person or organization, except as may otherwise be required by law.”

In July 1986 Paschen hired Modern Electric Company (Modern) to perform the electrical work on the project for $1.5 million. Modern was bound to Paschen under the terms of its subcontract by all the terms and conditions of the general contract. Section 8 of the subcontract states:

“No charges by [Modern] for extras shall be binding upon [Paschen] unless accepted or approved by [Kankakee], and [Paschen] shall not be liable to [Modern] on account of such changes unless and until [Paschen] shall receive payment from [Kankakee].”

After executing the subcontract, Paschen began construction. Because Kankakee had obtained federal funding for the project, Paschen’s contract was subject to certain Environmental Protection Agency regulations, which, among other things, provided an orderly process for changes in the work. The general contract required that a “change order” be issued to effectuate such changes. Donohue, under Kankakee’s direction, was responsible for reviewing and approving these change orders. Any claim for an increase in the contract price, according to the general contract, “shall be based on written notice delivered to [Kankakee] and [Donohue] within 10-days of the occurrence of the event giving rise to the claim.”

While the project was ongoing, Paschen negotiated with Kankakee and Donohue for certain changes in the “construction sequence” of the project, changes that would result, as Paschen claimed, in a cost savings for Kankakee. In May 1987, Kankakee directed Donohue to accept the sequence changes suggested by Paschen. This change order did not increase the original contract price.

During the course of Paschen’s performance, there were more than 20 change orders requested as provided in the contract that increased the contract price. Five of these change order requests remained unresolved near the end of the construction. They were:

(1) Secondary Clarifier Slab Damage. Paschen requested a change order in the amount of $108,711 to compensate it for the repair of the secondary clarifier No. 1 slab, which was damaged during construction by uplift forces caused by site flooding.

(2) Sludge Storage Tank Foundation Reinforcing Steel. Paschen requested a change order in the amount of $40,240 for additional reinforcing steel required for the four sludge storage tank foundations.

(3) Sludge Storage Tank Seal Replacement. Paschen requested a change order in the amount of $103,500 to pay for the replacement of a caulked seal with a combiflex seal in the joint between the wall and slab in each of four sludge storage tanks.

(4) Construction Sequence Constraints. Paschen requested a change order to pay for costs for temporary facilities required to implement its revised construction sequence.

(5) Topsoil. Paschen requested $54,288 for additional costs of purchase of topsoil.

In each instance, Paschen requested additional compensation by way of a written letter to Kankakee, as required by the general contract’s provision governing claims for extra work. The amount of these proposed change orders totaled $1,940,130. Paschen also claimed that it regularly discussed with Kankakee its continuing problems, of which everyone was aware. Donohue reviewed Paschen’s claims for additional compensation and determined that the work was within the scope of the general contract. On April 16, 1987, Donohue notified Paschen that “no request *** for additional compensation will be accepted.” In a written letter dated on January 27, 1989, Donohue once again denied Paschen’s requests for additional compensation.

The net effect of the denial was that Paschen failed to pay Modern for all the work Modern had finished. Modern filed a mechanic’s lien against Kankakee on February 14, 1989, totaling $1.6 million.

On May 12, 1989, Modern filed a complaint against Kankakee, Paschen, and Donohue. Modern’s complaint included (1) a claim for accounting against Paschen and Kankakee (count I), (2) a fraud claim against Kankakee and Donohue (count II), and (3) a breach of contract claim against Paschen as general contractor (count III). The project finally drew to a close in June 1989.

On August 20, 1991, Paschen entered into a written settlement agreement with Modern under which Modern received $100,000 in exchange for a full and complete release of Paschen from all liability. The parties also agreed to jointly prosecute their claims against Kankakee. The agreement states:

“10. Modern Electric and Paschen agree that they will cooperate in analyzing, preparing, presenting and prosecuting the Consolidated Claim against [Kankakee].”

On February 14, 1992, Modern voluntarily dismissed its May 1989 claim. On the same day, Paschen and Modern brought breach of contract and fraud claims against Kankakee and Donohue. Paschen and Modern later amended the complaint (second amended complaint) to include a breach of contract claim by Paschen (count I), Modern’s claim as an alleged third-party beneficiary of the contract between Paschen and Kankakee (count II), Modem’s quantum meruit claim against Kankakee (count III), a claim by Paschen and Modern for intentional fraud against Kankakee and Donohue (count IV), and a negligent misrepresentation claim by Paschen and Modern against Donohue (count V).

On September 7, 1993, Donohue filed its motion to dismiss counts I, II, IV and V On September 21, 1993, Kankakee filed a motion to strike count I and to dismiss counts II, III and IV pursuant to sections 2 — 615 (735 ILCS 5/2 — 615 (West 2002)) and 2 — 619 (735 ILCS 5/2— 619 (West 2002)) of the Code of Civil Procedure (Code).

On March 15, 1994, the trial court dismissed counts II through V of the second amended complaint with prejudice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ocampo v. Grossinger City Autocorp,Inc.
2023 IL App (1st) 221381-U (Appellate Court of Illinois, 2023)
Pepper Construction Co. v. Palmolive Tower Condominiums, LLC
2021 IL App (1st) 200753 (Appellate Court of Illinois, 2021)
Enadeghe v. Dahms
2017 IL App (1st) 162170 (Appellate Court of Illinois, 2017)
Pepper Construction Company v. Palmolive Tower Condominiums, LLC
2016 IL App (1st) 142754 (Appellate Court of Illinois, 2016)
Feliciano v. Geneva Terrace Estates Homeowners Ass'n
2014 IL App (1st) 130269 (Appellate Court of Illinois, 2014)
Feliciano v. Geneva Terrace Estates
2014 IL App (1st) 130269 (Appellate Court of Illinois, 2014)
Sheth v. SAB Tool Supply Co.
2013 IL App (1st) 110156 (Appellate Court of Illinois, 2013)
Federal Ins. Co. v. KONSTANT ARCHITECTURE PLAN., INC.
902 N.E.2d 1213 (Appellate Court of Illinois, 2009)
Federal Insurance v. Konstant Architecture Planning, Inc.
902 N.E.2d 1213 (Appellate Court of Illinois, 2009)
Hartzog v. Martinez
Appellate Court of Illinois, 2007
Travelers Casualty & Surety Co. v. A.G. Carlson, Inc.
858 N.E.2d 491 (Appellate Court of Illinois, 2006)
Prate Installations, Inc. v. Thomas
842 N.E.2d 1205 (Appellate Court of Illinois, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
819 N.E.2d 353, 353 Ill. App. 3d 628, 289 Ill. Dec. 196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paschen-contractors-inc-v-city-of-kankakee-illappct-2004.