Paschen Contractors, Inc. v. City of Kankakee

Procedural entryThis page is a short order in Paschen Contractors, Inc. v. City of Kankakee. Read the opinion of the Court — 353 Ill. App. 3d 628
Appellate Court of Illinois·Decided November 22, 2004·No. 3-03-0602 Rel·Published

Opinion

No. 3-03-0602

_________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

THIRD DISTRICT

A.D., 2004

PASCHEN CONTRACTORS, INC., ) Appeal from the Circuit

a Delaware Corporation, ) Court of the Twenty-First

Plaintiff-Appellant, ) Judicial Circuit, Kankakee

) County, Illinois

and )

) No. 92-L-34

MODERN ELECTRIC COMPANY OF )

ILLINOIS, a Delaware corporation, )

Plaintiff, )

)

v. )

CITY OF KANKAKEE, ILLINOIS )

Defendant-Appellee, )

DONOHUE & ASSOCIATES, INC., ) The Honorable

a Wisconsin corporation, ) Susan S. Tungate,

Defendant. ) Judge Presiding.

________________________________________________________________

JUSTICE McDADE delivered the opinion of the court:

________________________________________________________________

Plaintiff, Paschen Contractors, Inc. (Paschen), appeals from an order striking portions of its complaint, denying its motion to file a third amended complaint, and a grant of summary judgment in favor of defendants, City of Kankakee (Kankakee) and Donohue & Associates, Inc. (Donohue).  For the following reasons, we reverse.  

BACKGROUND

In 1984, Kankakee advertised for bids to build a wastewater treatment facility (the project) which would permit expansion of sanitary sewers in the city.  Kankakee hired Paschen in April 1986, pursuant to a general contract, as the general contractor for the project.  The general contract designated Donohue as the project engineer and the authorized representative of Kankakee.  The general contract provided as follows:

"6.9 **** Nothing in the Contract Documents shall create any contractual relationship between [Kankakee] or [Donohue] and any Subcontractor or other person or organization having a direct contract with [Paschen], nor shall it create any obligation on the part of [Kankakee] or [Donohue] to pay or see to the payment of any moneys due any Subcontractor or other person or organization, except as may otherwise be required by law."

In July 1986 Paschen hired Modern Electric Company (Modern) to perform the electrical work on the project for $1.5 million.  Modern was bound to Paschen under the terms of its subcontract by all the terms and conditions of the general contract.  Section 8 of the subcontract states:

"No charges by [Modern] for extras shall be binding upon [Paschen] unless accepted or approved by [Kankakee], and [Paschen] shall not be liable to [Modern] on account of such changes unless and until [Paschen] shall receive payment from [Kankakee]."

After executing the subcontract, Paschen began construction.  Because Kankakee had obtained federal funding for the project, Paschen’s contract was subject to certain Environmental Protection Agency regulations, which, among other things, provided an orderly process for changes in the work.  The general contract required that a "change order" be issued to effectuate such changes.  Donohue, under Kankakee’s direction, was responsible for reviewing and approving these change orders.  Any claim for an increase in the contract price, according to the general contract, "shall be based on written notice delivered to [Kankakee] and [Donohue] within 10-days of the occurrence of the event giving rise to the claim."

While the project was ongoing, Paschen negotiated with Kankakee and Donohue for certain changes in the "construction sequence" of the project, changes which would result, as Paschen claimed, in a cost savings for Kankakee.  In May 1987, Kankakee directed Donohue to accept the sequence changes suggested by Paschen.  This change order did not increase the original contract price.

During the course of Paschen’s performance, there were more than twenty change orders requested as provided in the contract that increased the contract price.  Five of these change order requests remained unresolved near the end of the construction. They were:

(1) Secondary Clarifier Slab Damage .  Paschen requested a change order in the amount of $108,711 to compensate it for the repair of the secondary clarifier No. 1 slab which was damaged during construction by uplift forces caused by site flooding.

(2) Sludge Storage Tank Foundation Reinforcing Steel .  Paschen requested a change order in the amount of $40,240 for additional reinforcing steel required for the four sludge storage tank foundations.

(3) Sludge Storage Tank Seal Replacement .  Paschen requested a change order in the amount of $103,500 to pay for the replacement of caulked seal with a combiflex seal in the joint between the wall and slab in each of four sludge storage tanks.

(4) Construction Sequence Constraints .  Paschen requested a change order to pay for costs for temporary facilities required to implement its revised construction sequence.

(5) Top Soil .  Paschen requested $54,288 for additional costs of purchase of top soil.

In each instance, Paschen requested additional compensation by way of a written letter to Kankakee, as required by the general contract’s provision governing claims for extra work.  The amount of these proposed change orders totaled $1,940,130.00.  Paschen also claimed that it regularly discussed with Kankakee its continuing problems, of which everyone was aware.  Donohue reviewed Paschen’s claims for additional compensation and determined that the work was within the scope of the general contract.  On April 16, 1987, Donohue notified Paschen that "no request *** for additional compensation will be accepted ***."  In a written letter dated on January 27, 1989, Donohue once again denied Paschen’s requests for additional compensation.

The net effect of the denial was that Paschen failed to pay Modern for all the work Modern had finished.  Modern filed a mechanic’s lien against Kankakee on February 14, 1989, totaling $1.6 million.

On May 12, 1989, Modern filed a complaint against Kankakee, Paschen, and Donohue.  Modern’s complaint included (1) a claim for accounting against Paschen and Kankakee (count I), (2) a fraud claim against Kankakee and Donohue (count II), and (3) a breach of contract claim against Paschen as general contractor (count III).  The project finally drew to a close in June 1989.

On August 20, 1991, Paschen entered into a written settlement agreement with Modern under which Modern received $100,000 in exchange for a full and complete release of Paschen from all liability.  The parties also agreed to jointly prosecute their claims against Kankakee.  The agreement states:

"10. Modern Electric and Paschen agree that they will cooperate in analyzing, preparing, presenting and prosecuting the Consolidated Claim against [Kankakee]."

On February 14, 1992, Modern voluntarily dismissed its May 1989 claim.  On the same day, Paschen and Modern brought breach of contract and fraud claims against Kankakee and Donohue.

Free access — add to your briefcase to read the full text and ask questions with AI

Paschen Contractors, Inc. v. City of Kankakee, (Ill. Ct. App. 2004).

Paschen Contractors, Inc. v. City of Kankakee (Paschen Contractors, Inc. v. City of Kankakee) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brehm v. Sargent & Lundy
384 N.E.2d 55 (Appellate Court of Illinois, 1978)
Logan v. Old Enterprise Farms, Ltd.
564 N.E.2d 778 (Illinois Supreme Court, 1990)
Outboard Marine Corp. v. Liberty Mutual Insurance
607 N.E.2d 1204 (Illinois Supreme Court, 1992)
Kozasa v. Guardian Electric Manufacturing Co.
425 N.E.2d 1137 (Appellate Court of Illinois, 1981)
Greb v. Forest Preserve Dist. of Cook Cty.
752 N.E.2d 519 (Appellate Court of Illinois, 2001)
Miller v. Pinnacle Door Co., Inc.
703 N.E.2d 628 (Appellate Court of Illinois, 1998)
Lombard Co. v. Chicago Housing Authority
587 N.E.2d 485 (Appellate Court of Illinois, 1991)
Loyola Academy v. S & S Roof Maintenance, Inc.
586 N.E.2d 1211 (Illinois Supreme Court, 1992)