Lombard Co. v. Chicago Housing Authority

587 N.E.2d 485, 221 Ill. App. 3d 730, 167 Ill. Dec. 216, 1991 Ill. App. LEXIS 1699
CourtAppellate Court of Illinois
DecidedSeptember 30, 1991
Docket1-90-1579
StatusPublished
Cited by26 cases

This text of 587 N.E.2d 485 (Lombard Co. v. Chicago Housing Authority) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lombard Co. v. Chicago Housing Authority, 587 N.E.2d 485, 221 Ill. App. 3d 730, 167 Ill. Dec. 216, 1991 Ill. App. LEXIS 1699 (Ill. Ct. App. 1991).

Opinion

PRESIDING JUSTICE MANNING

delivered the opinion of the court:

Plaintiff, The Lombard Company (hereafter plaintiff or TLC), appeals from the order of the circuit court of Cook County dismissing its verified four-count breach of contract complaint against defendant, the Chicago Housing Authority (hereafter defendant or CHA), for failure to timely file the cause of action pursuant to the four-year statute of limitations found in section 13 — 214 of the construction limitations act (Ill. Rev. Stat. 1987, ch. 110, par. 13 — 214). TLC contends that the 10-year statute of limitations found in section 13 — 206 (Ill. Rev. Stat. 1987, ch. 110, par. 13 — 206) is the governing provision because its complaint sought damages for extra work caused by defendant’s obstruction and interferences with TLC’s performance on a construction project in violation of the parties’ written contract. In the alternative, TLC contends that CHA was estopped from relying on section 13 — 214 to bar its action. We affirm in part, reverse in part and remand.

On October 7, 1981, TLC, an Illinois building contractor, was awarded a bid contract by CHA to construct 180 apartment units (hereafter the project). The contract required TLC to complete construction of the project within 480 days of November 2, 1981, i.e., by February 19, 1983. However, according to TLC because of CHA’s obstructions and interferences, it did not begin the project until mid-March 1982 and actually completed the construction on or about September 19, 1983.

In its complaint filed on September 12, 1989, TLC charged that CHA failed to fulfill its obligations pursuant to the contract and that such actions and inactions caused substantial construction delays, to wit, 267 days. The complaint specifically alleges, inter alia, that: (1) CHA failed to make the site available on November 2, 1981, as promised and, in fact, did not obtain title to the site until December 24, 1981; (2) CHA delayed in obtaining the necessary zoning permits until March 25, 1982; (3) CHA delayed the city’s issuance of a building permit until July 29, 1982, because it waited until May 1982 to authorize the architect, Graham, Anderson, Probst & White (hereafter architect or Graham, Anderson) to release the site plans to the city, a prerequisite for issuance of the building permit; and (4) CHA failed to approve shop drawings in the allocated time period or within a reasonable time although the parties had agreed to a condition that allowed CHA to be a part of the shop drawing submittal process and a new schedule which gave CHA and Graham, Anderson 30 days in which to review and approve or reject the shop drawings submitted by TLC. The complaint further alleged that after construction of the building itself finally began, CHA requested numerous changes; however, CHA then failed to timely approve TLC’s cost approvals that were required prior to implementation of the requested changes. TLC also alleged that CHA delayed getting utility services, which prevented TLC from installing gas and electric lines into the building, and CHA failed to supply kitchen appliances when required.

As a result of CHA’s actions, TLC incurred costs beyond those contemplated in the contract, to wit: (1) $69,165 in extra costs for additional materials, equipment and rental costs; (2) $116,205 in costs for masonry protection that was required because TLC had to construct temporary, winter protection structures in order to proceed with the concrete work when CHA failed to obtain title to the site or make arrangements for utility services for the buildings in a timely fashion; (3) $76,649 in extra expenses for wage increases; (4) $143,718 in extra expenses for field overhead; and (5) $130,348 in extra expenses for office overhead, for a total damages amount of $536,885. The complaint also alleged that CHA improperly withheld from TLC a retainage fund payment in the amount of $37,260.

CHA also entered into a contract with architect Graham, Anderson to perform all professional services necessary for planning and designing the project and architectural work. CHA, in turn, was required to approve the design documents and each phase of the work.

Soon after construction commenced, TLC began negotiating with CHA for reimbursement of the increased costs and, on May 14, 1982, submitted a formal request to CHA for a change order indicating that TLC was going to incur some $500,000 in extra costs. The complaint also alleges that some time during the series of meetings held in 1982 CHA acknowledged its liability to TLC for extra costs incurred due to CHA’s interference with TLC’s contract performance; that TLC was to hold its claim in abeyance during the period of contract performance; that once the building was completed, TLC was to submit a claim to CHA for the extra costs; and that TLC was entitled to additional days for contract completion due to delays not originating with TLC. CHA commissioners then approved “Change Order No. 34,” a payment to TLC in the amount of $142,538. TLC executed the order with the proviso that “it did not waive the remainder of its claim.” However, CHA never executed the change order. On October 20, 1983, TLC submitted its formal claim to CHA for extra compensation in the amount of $527,087.

On November 27, 1989, CHA filed a section 2 — 615 motion to dismiss the complaint (Ill. Rev. Stat. 1987, ch. 110, par. 2 — 615), on the ground that TLC’s claims were barred by the statute of limitations since CHA had engaged in the planning, designing, supervision or management of the project. CHA asserted that section 13— 214(a) requires a party to bring a construction-related action within four years from the time the person bringing the action knew or should have known of the act or omission giving rise to the cause of action. Thereafter, TLC filed briefs in opposition to the motion to dismiss relying on section 13 — 206 which provides a 10-year statute of limitations for an action on a written contract. The trial court granted CHA’s motion to dismiss on April 3, 1990, and thereafter denied TLC’s amended motion for reconsideration. In its amended motion to reconsider, TLC requested the trial court to consider facts “which show that defendant is equitably estopped from asserting a statute of limitations defense” and it attached correspondence between the parties to support its position that CHA never disputed liability, that settlement negotiations were limited to the extent of damages, and that the parties were negotiating both before and after the expiration of the putative limitations period.

The trial court held: “[The CHA] got so involved in the construction process and so involved in hindering and delaying and by their own mismanagement [they] brought themselves within the protection of [section 13 — 214].” TLC has appealed from these two adverse rulings, and for purposes of this appeal, all allegations of fact in TLC’s verified complaint filed are accepted as true.

TLC first argues on appeal that section 13 — 214 does not apply to the present case because the complaint does not contain any allegations of fact that CHA engaged in an act or omission described by this section, but merely alleges that CHA is being sued as a landowner for breach of contract. TLC contends that its complaint is not, in any way, based on some act or omission relating to “planning, designing, supervising or management” of the project within the meaning of section 13 — 214.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McMahan v. Sol Holland Co., Inc.
2023 IL App (1st) 211367-U (Appellate Court of Illinois, 2023)
Village of Big Rock v. Linden & Sons Sewer & Water, Inc.
2019 IL App (2d) 190186-U (Appellate Court of Illinois, 2019)
M&S Industrial Co., Inc. v. Allahverdi
2018 IL App (1st) 172028 (Appellate Court of Illinois, 2018)
Mular v. Ingram
2015 IL App (1st) 142439 (Appellate Court of Illinois, 2015)
Federal Ins. Co. v. KONSTANT ARCHITECTURE PLAN., INC.
902 N.E.2d 1213 (Appellate Court of Illinois, 2009)
Federal Insurance v. Konstant Architecture Planning, Inc.
902 N.E.2d 1213 (Appellate Court of Illinois, 2009)
Travelers Casualty & Surety Co. v. A.G. Carlson, Inc.
858 N.E.2d 491 (Appellate Court of Illinois, 2006)
Prate Installations, Inc. v. Thomas
842 N.E.2d 1205 (Appellate Court of Illinois, 2006)
Paschen Contractors, Inc. v. City of Kankakee
Appellate Court of Illinois, 2004
DeMarco v. Ecklund
341 Ill. App. 3d 225 (Appellate Court of Illinois, 2003)
O'Brien v. City of Chicago
Appellate Court of Illinois, 1996
People v. Asbestospray Corp.
616 N.E.2d 652 (Appellate Court of Illinois, 1993)
McKinnon v. City of Chicago
612 N.E.2d 67 (Appellate Court of Illinois, 1993)
Gavin v. City of Chicago
606 N.E.2d 506 (Appellate Court of Illinois, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
587 N.E.2d 485, 221 Ill. App. 3d 730, 167 Ill. Dec. 216, 1991 Ill. App. LEXIS 1699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lombard-co-v-chicago-housing-authority-illappct-1991.