Village of Big Rock v. Linden & Sons Sewer & Water, Inc.

2019 IL App (2d) 190186-U
Appellate Court of Illinois·Decided December 4, 2019·No. 2-19-0186·Unpublished·Cited by 1 cases

Opinion

No. 2-19-0186

Order filed December 4, 2019

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT

THE VILLAGE OF BIG ROCK, ) Appeal from the Circuit Court ) of Kane County.

Plaintiff-Appellant, )

)

v. ) No. 18-L-435 )

H. LINDEN & SONS SEWER AND WATER, ) INC., NORTH AMERICAN SPECIALTY ) INSURANCE COMPANY, and APPLIED ) TECHNOLOGIES, INC., ) Honorable ) James R. Murphy,

Defendants-Appellees. ) Judge, Presiding.

JUSTICE BRIDGES delivered the judgment of the court.

Justices Jorgensen and Hudson concurred in the judgment.

ORDER

¶1 Held: The circuit court did not err in dismissing as untimely the Village’s complaint for breach of several construction-related contracts because (1) equitable estoppel did not apply; (2) there was no basis to equitably toll the limitations period; and (3) the Village forfeited its argument that the discovery rule tolled the limitations period.

Therefore, we affirmed.

¶2 Plaintiff, the Village of Big Rock (the Village), appeals from the circuit court’s dismissal of its breach of contract complaint against defendants pursuant to section 2-619(a)(5) of the Code of Civil Procedure (Code) (735 ILCS 5/2-619(a)(5) (West 2018)), wherein it alleged the improper

construction of a sanitary sewer system on behalf of the Village and its residents. On appeal, the Village contends that the circuit court erred in concluding that its complaint was untimely under the four-year statute of limitations for faulty construction-related claims set forth in section 13- 214 of the Code (735 ILCS 5/13-214 (West 2018)) because (1) there are facts demonstrating that estoppel applies to bar H. Linden & Sons Sewer and Water, Inc. (Linden) from invoking the statute of limitations as a defense; (2) the statute of limitations was equitably tolled until Linden ceased repairs and plaintiff terminated the contract with Linden; and (3) the discovery rule applies to certain of the Village’s claims against Applied Technologies, Inc. (ATI). We affirm.

¶3 I. BACKGROUND

¶4 The Village filed a three-count breach of contract complaint on August 14, 2018, against defendants stemming from the construction of a sanitary sewer system that experienced widespread failures on April 18, 2013—less than one year after construction was completed. For the purposes of this appeal, we accept as true all the well-pleaded facts in the Village’s complaint and draw all reasonable inferences in its favor. Edelman, Combs & Latturner v. Hinshaw & Culbertson, 338 Ill. App. 3d 156, 164 (2003). The Village alleged that it entered into various agreements with defendant ATI to design, engineer, and supervise the construction of a sanitary sewer system and water reclamation facility (WRF) in the central part of the Village (Design Agreement and Observation Agreement, respectively), as well as to perform bidding services support for obtaining contractors for the project (Bidding Agreement). Under the Design Agreement, ATI prepared preliminary and final designs for the sanitary sewer system, which was designed to collect and transport wastewater from some 189 individual properties to the WRF for treatment. It was intended to be a watertight system, meaning no stormwater or groundwater would enter it. The system consisted of separate Septic Tank Effluent Pumps (STEP system)

located on each property that would discharge wastewater to pressurized sewers located in the Village’s right-of-ways, which in turn would discharge the wastewater to the WRF. The portion of the STEP system located on each individual property included a septic tank, a pump or pumps, valves and piping, and controls and wiring. Each septic tank was to be attached with epoxy to a 12-inch riser and a 24-inch riser, with each riser extending from the septic tank up to the ground surface. Each septic tank also contained a sanitary sewer line and an electrical line running from the house or other structure to the tank, as well as an outflow pipe which conveyed wastewater to the pressurized sewer system. Under the Bidding Agreement, ATI was to provide bidding service support to the Village relative to the project. Specifically, ATI published and obtained bids for the construction of the sanitary sewer system, evaluated said bids, and prepared recommendations to the Village on the selection of a construction contractor. Finally, under the Observation Agreement, ATI agreed to provide construction-related services to the Village, including making periodic visits to the project site to observe the progress and quality of the work, as well as providing training and other related services.

¶5 The Village selected defendant Linden to serve as general contractor for the project. It entered into two construction contracts with Linden, namely “Contract A—WRF” (Contract A) and “Contract B—Sanitary Sewer System” (Contract B). Contract A provided generally that Linden would construct a WRF in accordance with the plans provided by the Village. The WRF was designed to treat the wastewater that was collected from different locations and release the treated water into Big Rock Creek. The Village raised no issue in its complaint relative to this contract. Contract B provided generally that Linden would construct a sewer system in accordance with the plans and specifications provided by the Village; here, the plans prepared by ATI. This contract also provided that if any work was found to be defective within one year after the date of

substantial completion, Linden would promptly repair the defective work without cost to the Village. Pursuant to both contracts, Linden furnished performance bonds equal to the contract price as security for Linden’s obligations under the contracts. Said performance bonds were issued through defendant North American Specialty Insurance Company (North American).

¶6 Linden commenced installation of the septic tanks on the various properties within the Village in January 2012, and it completed all work on the sanitary sewer system contemplated in Contract B in April 2012. Neither Linden nor ATI ever notified the Village of any design or construction defect during or after construction of the sanitary sewer system.

¶7 After construction was completed but within the one-year guarantee period, the Village discovered widespread failures to the sanitary sewer system during a major rain event on April 18, 2013. Specifically, groundwater had entered numerous septic tanks on properties comprising the sanitary sewer system, causing numerous septic tank alarms to ring and alert the property owners and the Village. The Village immediately notified Linden and ATI.

Free access — add to your briefcase to read the full text and ask questions with AI

Village of Big Rock v. Linden & Sons Sewer & Water, Inc., 2019 IL App (2d) 190186-U (Ill. Ct. App. 2019).

2019 IL App (2d) 190186-U (Village of Big Rock v. Linden & Sons Sewer & Water, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harrington v. Miller
2025 IL App (1st) 250004-U (Appellate Court of Illinois, 2025)