Philadelphia Housing Authority v. Dore & Associates Contracting, Inc.

111 F. Supp. 2d 633, 2000 U.S. Dist. LEXIS 12706, 2000 WL 1256897
CourtDistrict Court, E.D. Pennsylvania
DecidedSeptember 2, 2000
DocketCIV.A. 00-2077
StatusPublished

This text of 111 F. Supp. 2d 633 (Philadelphia Housing Authority v. Dore & Associates Contracting, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philadelphia Housing Authority v. Dore & Associates Contracting, Inc., 111 F. Supp. 2d 633, 2000 U.S. Dist. LEXIS 12706, 2000 WL 1256897 (E.D. Pa. 2000).

Opinion

MEMORANDUM & ORDER

KATZ, Senior District Judge.

Before the court is defendant Dore & Associates Contracting, Inc.’s motion for summary judgment. The motion must be granted, as the parties’ contract does not permit the plaintiff to bring suit in federal court at this time.

Background

In February 1995, the Philadelphia Housing Authority (PHA) entered into a contract with Dore & Associates Contracting, Inc., by which Dore agreed to implode and demolish buildings at the Five Tower Site. The terms of the project required Dore to obtain a performance bond, which was issued by Star Insurance Company, the other defendant in this case. After this agreement was signed, PHA and Dore modified the contract to provide for the implosion of the Three Tower Site. Dore imploded the Five Tower Site on April 30, 1995, and the Three Tower Site on July 30, 1995. In the summer of 1996, Dore represented that it had completed all work, and the PHA released the final payment due under the contract. Subsequently, the PHA began construction of new buildings on the two sites. According to the PHA, its contractors were required to do extensive remedial work because of Dore’s failure to prepare the sites properly. The PHA claims that it expended approximately $600,000 to correct Dore’s errors, and it now brings suit for breach of contract, fraudulent misrepresentation, negligent *635 misrepresentation, and breach of warranty.

This summary judgment motion does not address the merits of the PHA’s claim against Dore. Rather, Dore contends that the PHA did not comply with the contractual terms that permit Dore, at its option, to utilize arbitration, mediation, or internal appeal as an alternative to litigation. The PHA responds that it did comply and that Dore failed to exercise its right to demand an alternative mode of resolution in a timely fashion.

Discussion

The parties agree that the contract includes HUD form 5370, “General Conditions of the Contract for Construction, Public and Indian Housing Programs” (HUD General Conditions), see Def. Ex. A, as well as a document entitled “PHA General Conditions.” See Def. Ex. B; see also Contract Agmt. art. 5 (Compl.Ex.l) (specifically including “General and Special Conditions” as contract documents); Compl. ¶ 11 (same). Dore relies on two provisions from these documents in support of its contention that this matter should not proceed in federal court at this time. The first is found in the HUD General Conditions:

31. Disputes
(a)“Claim,” as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract. A claim arising under the contract, unlike a claim relating to the contract, is a claim that can be resolved under a contract clause that provides for the relief sought by the claimant....
(b) Except for disputes arising under the clauses entitled Labor Standards and Labor Standards Nonroutine Maintenance, herein, all disputes arising under or relating to this contract, including any claims for damages for the alleged breach thereof which are not disposed of by agreement, shall be resolved under this clause.
(c) All claims by the Contractor shall be in writing and submitted to the Contracting Officer 1 for a written decision. A claim by the PHA/IHA against the Contractor shall be subject to a written decision by the Contracting Officer.
(d) The Contracting Officer shall, within _(60 unless otherwise indicated) days after receipt of the request decide the claim or notify the Contractor of the date by which the decision will be made.
(e) The Contracting Officer’s decision shall be final unless the Contractor (1) appeals in writing to a higher level in accordance with the PHA’s/IHA’s policy and procedures, (2) refers the appeal to an independent mediator or arbitrator, or (3) files suit in a court of competent jurisdiction. Such appeal must be made within (30 unless otherwise indicated) days after receipt of the Contracting Officer’s decision.
(f) The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal, or action arising under or relating to the contract, and comply with any decision of the Contracting Officer.

HUD General Conditions ¶ 31 (Disputes Provision). In addition, the PHA General Conditions contains the following provision: “Arbitration Clause: Disputes in arbitration resolved pursuant to paragraph 31(e) DISPUTES clause of the HUD General Conditions shall also be subject to the *636 provisions of the Pennsylvania Commonwealth Uniform Arbitration Act. 42 Pa. C.S.A. Section 7302(c), as amended.” PHA General Conditions ¶ 21. Dore argues that the court must grant summary judgment because the PHA did not comply with these provisions.

In its response to the motion, the PHA submits correspondence pertaining to the sites and argues that two letters from its contracting officers constitute “decisions” that triggered Dore’s obligation to demand alternative resolution. With respect to the earlier dispute, James J. Lombardo, the PHA’s project director, and Arthur Dore, the president of Dore & Associates, exchanged a series of letters from October 1, 1996, through December 2, 1996. See Plf. Resp. Ex. A-H. In December, two additional letters passed between the PHA’s project engineer, Dale F. Morris, and Mr. Dore. See id. Ex. I-J. On December 16, 1996, Albert Novack, the director of the PHA’s contract division, wrote to Star Insurance Company, stating that Dore’s work violated the contract and directing future correspondence to the attention of James Herrmann, the PHA’s contracting officer. See Plf. Ex. K. This letter was copied to Mr. Herrmann and to Mr. Dore. See id. Mr. Dore subsequently informed Star that his corporation would indemnify Star, see id. Ex. L.; on January 28, 1997, Star’s director of bond claims, Aan Pavlic, also responded, requesting further information from Mr. Herrmann regarding the allegations in the December 16, 1996, letter from Mr. Novack See id. Ex. M, N. Mr. Herrmann answered on June 4, 1997, stating that Dore did not complete the work on the sites and that the PHA demanded payment for the monies the PHA expended to correct the alleged deficiencies. See id. Ex. P. This letter was not copied to Arthur Dore or to Dore Associates. According to the PHA, this letter to Star constitutes the contracting officer’s “decision” required by contract. 2

With respect to the alleged nonconformities discovered in 1999, correspondence began with letters between Mr. Lombardo and Mr. Dore. See Plf. Ex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
111 F. Supp. 2d 633, 2000 U.S. Dist. LEXIS 12706, 2000 WL 1256897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philadelphia-housing-authority-v-dore-associates-contracting-inc-paed-2000.