Montano Electrical Contractor v. United States

610 F. App'x 987, 122 Fed. Cl. 987
CourtCourt of Appeals for the Federal Circuit
DecidedApril 13, 2015
Docket2014-5133
StatusUnpublished
Cited by6 cases

This text of 610 F. App'x 987 (Montano Electrical Contractor v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montano Electrical Contractor v. United States, 610 F. App'x 987, 122 Fed. Cl. 987 (Fed. Cir. 2015).

Opinion

PER CURIAM.

Jose Montano appeals from the final decision of the United States Court of Federal Claims (Claims Court) granting the Government’s motion to dismiss for lack of jurisdiction and denying Mr. Mon-tano’s motion to transfer. Montano Electrical Contractor v. United States, 114 Fed.Cl. 675 (2014). We affirm.

Background

In 1999, the Army Corps of Engineers (the Corps) awarded a contract to American Renovation & Construction Company (ARC) for the design and construction of family housing at Redstone Arsenal in Huntsville, Alabama. ARC then subcontracted the electrical work on the project to Mr. Montano. At some point, ARC apparently defaulted on its contract with the Corps, which resulted in ARC’S surety, St. Paul Mercury Insurance Company (St. Paul), assuming ARC’S obligations under the contract and arranging for Soltek Pacific (Soltek) to complete the project as completion contractor. As part of this transition, Mr. Montano’s subcontract was *989 assigned to Soltek and Mr. Montano continued to perform under the subcontract.

Thereafter, Mr. Montano filed a claim with St. Paul, seeking payment for electrical work he performed at Redstone Arsenal. After St. Paul rejected this claim, Mr. Montano repeatedly sought assistance from the contracting officer at the Corps. Each time, the contracting officer explained that he was unable to provide the requested assistance because Mr. Montano did not have a contract with the government, and thus the government was not a party to the dispute. The contracting officer also explained that Mr. Montano should pursue any such claim against the prime contractor under the Miller Act, 40 U.S.C. § 3133. 1

In response, Mr. Montano filed a request with the Armed Services Board of Contract Appeals (ASBCA) seeking assistance resolving his contract matter. The ASBCA docketed Mr. Montano’s request as an appeal and dismissed the appeal for lack of subject matter jurisdiction.

Mr. Montano then filed an action in the Claims Court seeking monetary relief from the government for the money owed on his subcontract. In addition, Mr. Montano asserted that the government was liable for the tortious conduct of the contracting officer. Specifically, Mr. Montano asserted that the contracting officer breached his purported duty to inform Mr. Montano of his cause of .action against the prime contractor under the Miller Act before the limitations period expired. The Claims Court concluded that it lacked jurisdiction over Mr. Montano’s contract claim because he was not in privity with the government. The Claims Court also determined that it lacked jurisdiction over Mr. Montano’s tort claim because claims brought under the Federal Tort Claims Act (FTCA) are expressly excluded from the Claims Court’s jurisdiction. Finally, the Claims Court concluded that it could not transfer Mr. Montano’s FTCA claim because Mr. Mon-tano had failed to file an administrative claim and therefore no district court could exercise jurisdiction over the claim. The present appeal followed. We have jurisdiction under 28 U.S.C. § 1295(a)(3).

DISCUSSION

We review a dismissal for lack of subject matter jurisdiction de novo. Brandt v. United States, 710 F.3d 1369, 1373 (Fed.Cir.2013). Although we generally review a decision by the Claims Court not to transfer a matter under 28 U.S.C. § 1631 for abuse of discretion, the underlying determination that no transferee court would possess jurisdiction over the matter is reviewed de novo. Rick’s Mushroom Serv., Inc. v. United States, 521 F.3d 1338, 1342-43 (Fed.Cir.2008).

A

In his complaint, Mr. Montano first seeks relief for the money he is owed under his subcontract for the performance of electrical work at Redstone Arsenal. The Tucker Act authorizes the- Claims Court to exercise jurisdiction over claims against the government involving “any express or implied contract with the United States.” 28 U.S.C. § 1491(a)(1). Similarly, the Contract Disputes Act permits a *990 contractor to bring an action challenging an adverse decision by a contracting officer in the Claims Court. 41 U.S.C. § 7104(b)(1). Because a subcontractor ordinarily lacks privity with the government, however, a subcontractor generally cannot bring such an action unless the prime contractor sues the government on the subcontractor’s behalf. E.R. Mitchell Const. Co. v. Danzig, 175 F.3d 1369, 1370 (Fed.Cir.1999).

In this case, Mr. Montano acknowledges that he was not in privity with the government. In addition, Mr. Montano cannot assert that he nevertheless can bring the suit through the prime contractor because neither St. Paul nor Soltek are plaintiffs in this action. Thus, the Claims Court correctly concluded that it lacked jurisdiction over Mr. Montano’s contract claims.

B

Mr. Montano next seeks .monetary relief for damages suffered as a result of the contracting officer’s alleged negligence. Specifically, he argues that the contracting officer acted negligently in failing to timely advise Mr. Montano of his rights under the Miller Act. The sole vehicle for asserting such a tort claim is the FTCA. 28 U.S.C. § 1346(b). The FTCA explains, however, that

the district courts ... shall have exclusive jurisdiction of civil actions on claims against the United States, for money damages ... for injury or loss of property, or personal injury or death caused by the negligent or wrongful act or omission of any employee of the Government while acting within the scope of his office or employment....

Id. § 1346(b)(1). Likewise, the Tucker Act expressly excludes any claims “sounding in tort,” from the Claims Court’s jurisdiction. 28 U.S.C. § 1491(a)(1). Thus, the Claims Court correctly concluded that it lacked jurisdiction to adjudicate Mr. Mon-tano’s claims alleging tortious conduct by the contracting officer.

C

Finally, Mr. Montano argues that, the Claims Court erred in refusing to transfer his FTCA claim to an appropriate district court. When a court concludes that it lacks jurisdiction to hear an action, 28 U.S.C. § 1631

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
610 F. App'x 987, 122 Fed. Cl. 987, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montano-electrical-contractor-v-united-states-cafc-2015.