FEDERAL · 41 U.S.C. · Chapter 15
Contract price adjustment
41 U.S.C. § 1503
Title41 — Public Contracts
Chapter15 — COST ACCOUNTING STANDARDS
This text of 41 U.S.C. § 1503 (Contract price adjustment) is published on Counsel Stack Legal Research, covering United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
41 U.S.C. § 1503.
Text
(a)Disagreement Constitutes a Dispute.—If the Federal Government and a contractor or subcontractor fail to agree on a contract price adjustment, including whether the contractor or subcontractor has complied with the applicable cost accounting standards, the disagreement will constitute a dispute under chapter 71 of this title.
(b)Amount of Adjustment.—A contract price adjustment undertaken under section 1502(f)(2) of this title shall be made, where applicable, on relevant contracts that are subject to the cost accounting standards so as to protect the Federal Government from payment, in the aggregate, of increased costs, as defined by the Cost Accounting Standards Board and in accordance with the following requirements:
(1)The Federal Government may not recover costs greater than the a
Free access — add to your briefcase to read the full text and ask questions with AI
Related
The Boeing Company v. United States
968 F.3d 1371 (Federal Circuit, 2020)
Directv Group, Inc. v. United States
670 F.3d 1370 (Federal Circuit, 2012)
Boeing Company v. United States
119 F.4th 17 (Federal Circuit, 2024)
The Boeing Company v. United States
(Federal Claims, 2022)
Boeing Company v. United States
(Federal Claims, 2019)
Johnson Lasky Kindelin Architects, Inc v. United States
(Federal Claims, 2020)
Perry v. United States
(Federal Claims, 2020)
Gulley v. United States
(Federal Claims, 2020)
Source Credit
History
(Pub. L. 111–350, §3, Jan. 4, 2011, 124 Stat. 3699; Pub. L. 119–60, div. A, title XVIII, §1806(f)(1), Dec. 18, 2025, 139 Stat. 1240.)
Editorial Notes
Editorial Notes
Amendments
2025—Subsec. (b). Pub. L. 119–60 amended subsec. (b) generally. Prior to amendment, text read as follows: "A contract price adjustment undertaken under section 1502(f)(2) of this title shall be made, where applicable, on relevant contracts between the Federal Government and the contractor that are subject to the cost accounting standards so as to protect the Federal Government from payment, in the aggregate, of increased costs, as defined by the Cost Accounting Standards Board. The Federal Government may not recover costs greater than the aggregate increased cost to the Federal Government, as defined by the Board, on the relevant contracts subject to the price adjustment unless the contractor made a change in its cost accounting practices of which it was aware or should have been aware at the time of the price negotiation and which it failed to disclose to the Federal Government."
Statutory Notes and Related Subsidiaries
Regulations
Pub. L. 119–60, div. A, title XVIII, §1806(f)(2), Dec. 18, 2025, 139 Stat. 1240, provided that: "Not later than 180 days after the date of the enactment of this Act [Dec. 18, 2025], the Administrator for Federal Procurement Policy shall issue such regulations as are necessary to implement the amendments made by this subsection [amending this section]."
Amendments
2025—Subsec. (b). Pub. L. 119–60 amended subsec. (b) generally. Prior to amendment, text read as follows: "A contract price adjustment undertaken under section 1502(f)(2) of this title shall be made, where applicable, on relevant contracts between the Federal Government and the contractor that are subject to the cost accounting standards so as to protect the Federal Government from payment, in the aggregate, of increased costs, as defined by the Cost Accounting Standards Board. The Federal Government may not recover costs greater than the aggregate increased cost to the Federal Government, as defined by the Board, on the relevant contracts subject to the price adjustment unless the contractor made a change in its cost accounting practices of which it was aware or should have been aware at the time of the price negotiation and which it failed to disclose to the Federal Government."
Statutory Notes and Related Subsidiaries
Regulations
Pub. L. 119–60, div. A, title XVIII, §1806(f)(2), Dec. 18, 2025, 139 Stat. 1240, provided that: "Not later than 180 days after the date of the enactment of this Act [Dec. 18, 2025], the Administrator for Federal Procurement Policy shall issue such regulations as are necessary to implement the amendments made by this subsection [amending this section]."
Cite This Page — Counsel Stack
Bluebook (online)
41 U.S.C. § 1503, Counsel Stack Legal Research, https://law.counselstack.com/usc/41/1503.