Ulysses, Inc. v. United States

66 Fed. Cl. 161, 2005 U.S. Claims LEXIS 194, 2005 WL 1540934
CourtUnited States Court of Federal Claims
DecidedJune 30, 2005
DocketNos. 04-938C, 04-939C
StatusPublished
Cited by1 cases

This text of 66 Fed. Cl. 161 (Ulysses, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ulysses, Inc. v. United States, 66 Fed. Cl. 161, 2005 U.S. Claims LEXIS 194, 2005 WL 1540934 (uscfc 2005).

Opinion

MEMORANDUM OPINION AND ORDER OF DISMISSAL

WILLIAMS, Judge.

In these consolidated eases, Ulysses, Inc. challenges the Defense Supply Center Columbus’ (DSCC) cancellation of two purchase orders for the production of circuit cards.1 Plaintiff disputes the agency’s determination that it is not an authorized manufacturer of the items, and seeks a declaratory judgment that it is an approved source. Further, Plaintiff seeks the total contract amounts it would have received absent the cancellation, representing its costs of production.

This matter comes before the Court on Defendant’s motion to dismiss for lack of subject matter jurisdiction, on grounds that Plaintiff has failed to meet the jurisdictional prerequisites of the Contracts Disputes Act (CDA), 41 U.S.C. § 601 et seq. Because Plaintiff has failed to submit a “claim” to the contracting officer (CO) or obtain a CO’s final decision as required by the CDA, this action is dismissed.

Factual Background2

Plaintiff was awarded Contraet/Purchase Order No. SP0960-02-M-4209 (Contract 4209) on April 22, 2002, for production of the P/N 178AS112 Circuit Card Assembly Critical Application Item. The contract was for eighty-five units for a total value of $44,625.00. On June 27, 2002, Plaintiff was awarded a second contract, ContracVPur-chase Order No. SP0960-02-M-5456 (Contract 5456) for the production of ninety-nine units of this identical item for a total value of $50,490.00. Both contracts specifically stated: “ACCELERATED DELIVERY IS ACCEPTABLE AND DESIRED AT NO COST TO THE GOVERNMENT.” Compls. H 4 (emphasis in original).3

Upon award of the contracts, Plaintiff immediately began production of the items in accordance with Defendant’s desires for “accelerated delivery.” On February 14, 2002, Plaintiff received a letter from Contracting Officer Brian Kennedy, in reference to both contracts 4209 and 5456, stating Plaintiff was not an approved manufacturer for Cage 072E5 178AS112 and warning that if Plaintiff could not supply the exact part, Defendant would cancel the contract without cost. Compls. 1110.

In August 2002, Defendant issued a stop work order directing Plaintiff to stop producing the units under both contracts. Compls. 1111. Plaintiff had by this time substantially manufactured the contracted items. Id. H12. Plaintiff responded to the stop work order by letter dated August 26, 2002, stating that it [163]*163has been a manufacturer of the end item, Circuit Firing Equipment P/N 178AS100 and that the item at issue here, Cage 072E5 178A5112 is a component of this end item. Id. H14. This letter went unanswered.

Plaintiff sent another letter dated October 14, 2002, requesting under the Freedom of Information Act, “the source who has indicated to you that we are not an approved source to manufacture this item.” Def.’s Reply Br., Attachment D. In a letter dated November 13,2002, Plaintiff advised Defendant:

One of the contracts is approximately 95% complete and the second contract is approximately 80% — 85% complete. In view of the fact that both contracts are close to completion we intend to go back into production and complete the remaining work that is to be done. We realize that in the event that the unthinkable happens, which is cancellation of the contracts on the basis that we are not the manufacturer of the item, the cost of the remaining percentage of the work to be done will not be included in the settlement cost. The reason for us in completing the assemblies is that it will not be economical to restock the components and reset the job in the future.
In the event you decide to cancel the contracts, we would appreciate your response to our letter of October 14, 2002, and furnish us with the information requested as well as justify the reasons for not considering us as the manufacturer of the item after we provided you with all the information indicating that we are.

Def.’s Reply Br., Attachment B.

By letter dated November 20, 2002, Plaintiff suggested that if Defendant had doubts about its ability to manufacture the item, it could impose a First Article testing requirement at no cost to Defendant. Plaintiff also suggested that a Defense Contract Management Command representative could “verify the data in our files as well as witness the inspection and test of the subject unit.” Def. Rep. Br., Attachment C. Defendant did not pursue these offers. Compls. 1125.

Over eight months later, on June 17, 2003, Defendant issued contract modifications canceling both contracts 4209 and 5456. Compls. H 26. The modifications cancelled all remaining contract line items under both purchase orders “at no cost or liability to the Government or the contractor.” Contract 4209, Modification P00001; Contract 5456, Modification P00001 (June 17, 2003). Plaintiff does not allege that it subsequently submitted any claim or other correspondence to the CO about these modifications. Plaintiff filed two complaints in this Court on June 1, 2004, which have since been consolidated. Plaintiff seeks the total contract amounts of $44,625.00 under Contract 4209, and $50,490.00 under Contract 5456.

Discussion

Subject matter jurisdiction may be challenged at any time, by any parties, by the Court sua sponte, and even on appeal. Booth v. United States, 990 F.2d 617, 620 (Fed.Cir.1993). In ruling on a motion to dismiss for lack of subject matter jurisdiction, the Court must presume undisputed factual allegations to be true and construe all reasonable inferences in favor of the plaintiff. Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 40 L.Ed.2d 90 (1974); Cedars-Sinai Med. Ctr. v. Watkins, 11 F.3d 1573, 1583 (Fed.Cir.1993); Holland v. United States, 57 Fed.Cl. 540, 551 (2003). Once the Court’s jurisdiction has been challenged, plaintiff bears the burden of establishing subject matter jurisdiction by a preponderance of the evidence. Taylor v. United States, 303 F.3d 1357, 1359 (Fed.Cir.2002); Newby v. United States, 57 Fed.Cl. 283, 289 (2003).

The Tucker Act, 28 U.S.C. § 1491, sets out the this court’s jurisdiction over disputes arising under the CDA 41 U.S.C. §§ 601-13 (2000) as follows:

The Court of Federal Claims shall have jurisdiction to render judgment upon any claim by or against, or dispute with, a contractor arising under section 10(a)(1) of the [CDA], including a dispute concerning termination of a contract, rights in tangible or intangible property, compliance with cost accounting standards, and other non-monetary disputes on which a decision of the contracting officer has been issued under [section 605 of the CDA].

28 U.S.C. § 1491(a)(2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
66 Fed. Cl. 161, 2005 U.S. Claims LEXIS 194, 2005 WL 1540934, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ulysses-inc-v-united-states-uscfc-2005.