Southern Nuclear Operating Co. v. United States

79 Fed. Cl. 135, 2007 U.S. Claims LEXIS 352, 2007 WL 3277271
United States Court of Federal Claims·Decided November 1, 2007·No. No. 98-614C·Published·Cited by 7 cases

Opinion

ORDER ON MOTION FOR PARTIAL RECONSIDERATION

MEROW, Senior Judge.

Defendant timely moved for reconsideration of discrete segments of the Opinion reported in this matter at 77 Fed.Cl. 396 (2007). Plaintiffs have filed a Response.1 After careful analysis of the parties’ submissions, for the following reasons it is concluded that defendant has not shown any viable basis for reconsideration.

[137]*137A. Standards for reconsideration

By a timely motion, a party may request the court amend its findings and judgment. RCFC 52(b). “[Reconsideration may be granted ... for any of the reasons established by the rules of common law or equity applicable as between private parties in the courts of the United States.” RCFC 59(a)(1). The court may take additional testimony, amend or make new findings of fact and conclusions of law, or direct the entry of a new judgment. Id.

Reconsideration is within the court’s discretion. Yuba Natural Res., Inc. v. United States, 904 F.2d 1577, 1583 (Fed. Cir.1990). “Motions for reconsideration must be supported ‘by a showing of extraordinary circumstances which justify relief.’ ” Caldwell v. United States, 391 F.3d 1226, 1235 (Fed.Cir.2004), citing Fru-Con Constr. Corp. v. United States, 44 Fed.Cl. 298, 300 (1999), aff'd, 250 F.3d 762 (Fed.Cir.2000) (Table). To prevail, the moving party must meet the “exacting standard of identifying ‘a manifest error of law or mistake of fact.’ ” Browning Ferris Indus., Inc. v. United States, 2007 WL 1412087, at *1 (Fed.Cl. May 10, 2007) (citing Pacific Gas & Elec. Co. v. United States, 58 Fed.Cl. 1, 2 (2003)). To establish manifest legal or factual error, the moving party must demonstrate: “(1) that an intervening change in the controlling law has occurred; (2) that previously unavailable evidence is now available; or (3) that the motion is necessary to prevent manifest injustice.” Stockton E. Water Dist. v. United States, 76 Fed.Cl. 497, 499 (2007) (citing Bishop v. United States, 26 Cl.Ct. 281,286 (1992)). See First Fed. Lincoln Bank v. United States, 60 Fed.Cl. 501, 502 (2004).

In the end, reconsideration of even part of a final judgment is extraordinary relief, not an opportunity for a dissatisfied party to repeat arguments previously rejected. “Motions for reconsideration are not intended to allow a party to reassert arguments that the Court has already considered.” Browning Ferris Indus., 2007 WL 1412087, at *1 (citations omitted). Also, RCFC 59 “is not intended to give an unhappy litigant an additional chance to sway the court.” Fru-Con Constr., 44 Fed.Cl. at 300. Reconsideration is not an opportunity to make arguments that could have been raised earlier but were not. Browning Ferris Indus., 2007 WL 1412087, at *1. See also Four Rivers Inv., Inc. v. United States, 78 Fed.Cl. 662, 664-65 (2007); Shirlington Limousine & Transp., Inc. v. United States, 78 Fed.Cl. 27, 29 (2007).

B. Background summary

In June of 1983, the parties signed a Standard Contract under which the Department of Energy (“DOE”) was to accept, transport and dispose of plaintiffs’ spent nuclear fuel (“SNF”), commencing performance not later than January 31, 1998. DOE’s failure to do so remains a partial breach of contract. Following a five-week trial on damages, extensive briefing and oral argument, the court issued its Opinion, a portion of which is subject to defendant’s reconsideration motion.

In its Opinion, the court made extensive findings and conclusions which are not here fully repeated. The mitigation damages awarded were “sufficient to place [plaintiffs] in as good a position as [they] would have been had [DOE] fully performed.” Indiana Michigan Power Co. v. United States, 422 F.3d 1369, 1373 (Fed.Cir.2005).

As instructed by Indiana Michigan, the court determined that, in the main: (1) plaintiffs’ mitigation efforts of building dry storage facilities for their spent nuclear fuel (“SNF”) because they were running out of room in their existing wet pools were reasonably foreseeable by DOE at the time of contracting; (2) DOE’s admitted delays and apprehension about the viability of DOE’s projections were a substantial causal factor in the mitigation decisions and the reasonable expenses thereof; and (3) the expenses were established with reasonable certainty. But for DOE’s delay, these expenditures would not have been incurred if DOE had performed at any reasonable rate, regardless of whether the burden was on plaintiffs or defendant to prove what would have happened if there had been no partial breach.

At (1) the time the mitigation decisions were made; (2) in 1998 when DOE was required to commence performance; (3) at [138]*138the time the expenses were incurred; (4) at the time of trial; (5) at the time of the court’s Opinion; and (6) at the date of this reconsideration proceeding, plaintiffs will not be better off by the award of mitigation expenses than if DOE performed at the levels it planned at any of those times. While the 1991 Annual Capacity Report (“ACR”) rates advocated by DOE cannot be held to comprise the performance contemplated by the contracting parties in the absence of a partial breach, even at those restrictive rates, the utilities through fuel management techniques, swaps, inter- or intra-company exchanges, use of the twenty percent increase option under the Standard Contract, and other measures, could have avoided dry storage if there had been confidence in DOE’s commencement and continuance of performance. Offsets for expenses plaintiffs avoided because of DOE’s partial breach were applied. Within its jurisdictional constraints, the relief awarded by the court attempted to make plaintiffs whole, not better.

C. Acceptance rate

With the foregoing background, defendant requests reconsideration of the court’s decision not to find a specific rate at which DOE would have performed starting January 31, 1998.2 Defendant argues that without determining the scope of DOE’s contractual obligations, it is impossible to determine what, if any, damages plaintiffs suffered.

Both parties asked the court to adopt a specific rate. In its post-trial brief, defendant urged the court to adopt the acceptance rates in the 1991 ACR as the bounds of DOE’s contractual obligation. (Def.’s Br. 146-61.) The court did not adopt defendant’s position. Southern Nuclear, 77 Fed.Cl. at 436 (“The court does not accept either defendant’s proffered 1991 ACR rate or the 3000 MTU (metric ton of uranium) rate advocated by plaintiffs.”). Accordingly, as it was previously briefed and argued, the court’s rejection of that rate may not comprise a proper subject of reconsideration. Nevertheless, upon analysis, defendant has not established any reason for reconsideration. The court’s mitigation analysis—causation, foreseeability and reasonable certainty—and examination of what costs would have been incurred in the nonbreach world as well as possible windfall, considered the various rates discussed both prior, and subsequent, to the signing of the Standard Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Southern Nuclear Operating Co. v. United States, 79 Fed. Cl. 135, 2007 U.S. Claims LEXIS 352, 2007 WL 3277271 (uscfc 2007).

79 Fed. Cl. 135 (Southern Nuclear Operating Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Conner v. United States
Federal Claims, 2022
Fillmore Equipment of Holland, Inc. v. United States
105 Fed. Cl. 1 (Federal Claims, 2012)
Southern Nuclear Operating Co. v. United States
637 F.3d 1297 (Federal Circuit, 2011)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Parker v. United States
93 Fed. Cl. 653 (Federal Claims, 2010)
Englewood Terrace Ltd. Partnership v. United States
86 Fed. Cl. 720 (Federal Claims, 2009)