Precision Standard, Inc v. United States

CourtUnited States Court of Federal Claims
DecidedJune 9, 2016
Docket11-558
StatusUnpublished

This text of Precision Standard, Inc v. United States (Precision Standard, Inc v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Precision Standard, Inc v. United States, (uscfc 2016).

Opinion

In the United States Court of Federal Claims No. 11-558C (Filed: June 9, 2016)

**********************************

PRECISION STANDARD, INC., Contract Disputes Act, 41 U.S.C. § 609(a) (2012); Plaintiff, Defense Priorities and Allocations Systems; v. waiver of delivery dates; e q u i t abl e adj ust m ent ; conditional approval THE UNITED STATES,

Defendant.

********************************* _____________

OPINION _______________

BRUGGINK, Judge.

Plaintiff, Precision Standard, Inc. (“PSI”), brings this case pursuant to the Contract Disputes Act, 41 U.S.C. § 609(a) (2012) and the Tucker Act, 28 U.S.C. § 1491(a) (2012) against the United States seeking equitable adjustment and damages arising under various contracts between it and the Defense Logistics Agency (“DLA” or “the Agency”), formerly known as the Defense Supply Center Richmond (“DSCR”). Pending is defendant’s motion for partial summary judgment on Counts 2 through 9 of the complaint.1 The motion is fully briefed, and oral argument was held on April 6, 2016. For the reasons stated below, we grant in part and deny in part defendant’s motion for summary judgment.

1 The complaint contains nine counts. Count 1, however, is not included in this motion. BACKGROUND2

There are 28 contracts at issue in Counts 2 through 9 of the complaint. These contracts, each of which was for a particular aircraft part, were entered into between April 2006 and January 2009. The majority of the contracts required first article testing to be performed at Warner Robins Air Force Base (“Warner Robins”). The remainder required first article testing at Hill Air Force Base (“Hill”). They are listed as follows:

Count Contract No. Contract Date Part 2 SPM4A7-07- March 23, 2007 Upper Thrust 0105 Reverser Fan Cowlers 3 SP0407-06-M- April 18, 2006 Structural 9684 Aircraft Panels 4 SPM4A7-08-M- March 31, 2008 Access Covers 5689 5 SP0407-05-C- March 28, 2005 Trailing Edge 2028 Panels 6 SPM4A7-09-D- July 2009 Bundle Covers 5547 7 SPM4A7-08-D- July 30, 2008 Coupling 0316 Adapter Sleeves 8(A) SPM4A7-07-D- March 6, 2007 Lower Left 3180 Panel Aircraft Assemblies 8(B) SPM4A5-08-M- February 22, Access Covers 2072 2008 8(C) SPM4A7-07-M- April 12, 2007 Fairing 6269 Assemblies

2 The facts are drawn from the appendices filed with the parties’ briefing.

2 8(D) SPM4A7-08-C- June 6, 2008 Aircraft Fairings 0387 8(E) SPM4A7-08-D- June 23, 2008 Fuselage Fairing 0274 Panels 8(F) SPM4A7-07-M- August 6, 2007 Aircraft Fairings A678 8(G) SPM4A7-07-M- September 14, Aileron Trailing C357 2007 Edge Assemblies 8(H) SPM4A7-08-C- August 16, 2008 Aircraft Access 0481 Doors 9(A) SPM4A7-08-M- November 29, Trailing Edge 2238 2007 Wing Assemblies 9(B) SPM4A7-08-M- January 17, Insulation 4809 2008 Panels 9(C) SPM4A7-08-M- February 25, Lower Bunk 6942 2008 Panels 9(D) SPM4A7-08-M- March 14, 2008 Aircraft Floor 7318 Panels 9(E) SPM4A7-08-M- April 1, 2008 Aircraft Fairings 8566 9(F) SPM4A7-08-M- May 16, 2008 Wheel Panel A725 Assemblies 9(G) SPM4A7-08-M- May 31, 2008 Aircraft A912 Retainer Assemblies 9(H) SPM4A7-08-M- June 10, 2008 Aircraft Floor B771 Panels 9(I) SPM4A7-08-M- July 23, 2008 Aircraft Panel D715 Assembly

3 9(J) SPM4A7-08-M- August 25, 2008 Helicopter F252 Access Covers 9(K) SPM4A7-09-M- January 30, Aircraft Access 3933 2009 Doors 9(L) SPM4A7-07-M- October 26, Cowlings 0637 2006 9(M) SPM4A7-08-M- March 5, 2008 Panel 7193 Assemblies 9(N) SPM4A7-08-M- March 21, 2008 Bulkhead Clips 7646

The parties set forth arguments which pertain to every contract, arguments which pertain to a specific group of contracts, and arguments that pertain to individual contracts. Before discussing these arguments, we will detail the facts that led to the dispute for each contract individually.

Count 2

DLA awarded contract number SPM4A7-07-0105 to PSI on March 23, 2007. The contract was for 33 upper thrust reverser fan cowling covers for a total price of $154, 300. The first article was due for testing 120 days later, on July 21, 2007. Defendant claims that the Agency received the first article in September 2007. After receiving and testing the first article, DLA rejected it on January 11, 2008. In its correspondence with PSI, the Agency stated that the first article did not conform to the procurement specifications and pointed out nine specific defects. The letter also stated that PSI had the opportunity to correct the nonconformance and resubmit two first articles for testing, at a cost to PSI of $5,880.20. PSI challenged the rejection on February 14, 2008, and requested conditional approval. In its May 7, 2008 response, DLA denied the request for conditional approval and informed PSI the first article was not manufactured in accordance with the drawings.

PSI submitted a second first article to Warner Robins for testing in September 2008. Contracting Officer (“CO”) Carl Hudson sent PSI a letter on April 15, 2009 informing PSI that the second first article failed inspection. The letter identified 10 different defects, and offered PSI the option of submitting another first article for testing or cancelling the contract. According to the

4 letter, the third re-test would cost PSI $6,062.47. In August 2009, DLA returned the second first article to PSI. In November 2009, DLA send PSI an email requesting that PSI inform the Agency whether it would submit another first article and requesting a revised delivery schedule or cancellation request by December 3, 2009. PSI did not respond to this email.

On January 4, 2010, the contracting officer issued a unilateral modification P00002 cancelling the contract “at no cost or obligation to either party.” Def.’s App. 19A. On April 30, 2010, PSI responded with an inventory schedule and advised DLA that it would be submitting is termination settlement proposal. Id. at 19C. DLA responded on May 4, 2010 with a show cause notice, which stated that modification P00002 should not have been issued as a unilateral no-cost modification and was therefore rescinded. However, the letter informed PSI that it was delinquent on the contract and that DLA was considering cancelling for default.

PSI responded to the show cause notice on May 11, 2010, asserting that the Agency illegally imposed a requirement that the parts conform exactly to the product-part specifications and arguing that the government had no valid basis for a termination for default. It also stated that, on June 1, 2007, PSI had written the government asking for assistance and cooperation in checking PSI’s drill bit template, but that the government never responded.

PSI sent a supplemental letter on June 30, 2010, asserting that the part it sent as its second first article was actually the same part as the initial first article, with the identified defects corrected, yet Warner Robins had found completely new defects in the second first article. The letter went on to state that the fact that Warner Robins is a manufacturing competitor of PSI created a conflict of interest that should disqualify Warner Robins as a first article tester.

On August 17, 2010, the contracting officer issued a termination for default for “failure to comply with the essential requirements of the contract.” Id. at 26. Notice of the termination was sent to PSI on September 3, 2010.

Count 3

DLA awarded contract number SP0407-06-M-9684 for the manufacture of 10 structural aircraft panels to PSI on April 18, 2006. The contract required that PSI send its first article to Hill within 90 days (by July 17, 2006). The

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Precision Standard, Inc v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/precision-standard-inc-v-united-states-uscfc-2016.