Atlantic Fish & Oyster Co. v. United States

116 F. Supp. 574, 126 Ct. Cl. 892, 1953 U.S. Ct. Cl. LEXIS 136
CourtUnited States Court of Claims
DecidedDecember 1, 1953
DocketNo. 50166
StatusPublished
Cited by1 cases

This text of 116 F. Supp. 574 (Atlantic Fish & Oyster Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Fish & Oyster Co. v. United States, 116 F. Supp. 574, 126 Ct. Cl. 892, 1953 U.S. Ct. Cl. LEXIS 136 (cc 1953).

Opinion

Madden, Judge,

delivered the opinion of the court

On May 4, 1949, the plaintiff and the Government made a contract under which the plaintiff was to deliver 30,000 pounds of Type III shrimp to the Government at its Quartermaster Market Center, San Francisco, California, on May 31. It was contemplated that the plaintiff would have the shrimp processed at the plant of the Clegg Shrimp Company of Port Lavaca, Texas. That Company’s plant was to be one of the points where the Government would inspect the shrimp. The contract was signed on behalf of the Government by a contracting officer at the Quartermaster Center at Chicago, Illinois.

Prior to May 31, the delivery date, the plaintiff requested the Government’s agent at Chicago to extend the time of performance to June 15. The plaintiff represented, falsely, that weather conditions along the Texas coast had made it impossible for shrimp boats to operate. The Government extended the time to June 15. On June 14, the plaintiff’s supplier, the Clegg Company, had not begun to process any shrimp for the contract and on June 15 no shrimp had, of course, been delivered.

After June 15, and until June 21, the Government’s contracting officer adopted an attitude of forbearance, hoping that the plaintiff would perform the contract. On June 17, the plaintiff was informed by its supplier, the Texas Fisherman’s Cooperative, that it looked like the Government order could be filled in the following three days. The Government was advised of this statement. On June 21 and 22, at [894]*894the request of the plaintiff, a Government inspector inspected and rejected all the shrimp the plaintiff had available at the Clegg plant, which was about 10,000 pounds. The reasons for the rejection were (1) part of the shrimp had been processed before the arrival of the inspector, and (2) the rest of the shrimp had been beheaded at sea. The first reason for rejection was valid. The second was not, but the inspector advised the plaintiff that if it obtained permission from the Quartermaster Center at Chicago for acceptance of the beheaded shrimp, he would pass them. The plaintiff did not seek that permission.

On June 21 the Chicago Center was told by the San Francisco Center that it had received no notice of shipment from the plaintiff; that shrimp stocks were running low, and that unless the plaintiff produced immediately it would be necessary to procure the shrimp on the open market. On that same day the Chicago Center telephoned the plaintiff that its contract was being terminated and that the Government was going to purchase shrimp elsewhere. On June 28 this same information was given in a letter to the plaintiff. The letter also advised the plaintiff that the excess cost of obtaining the shrimp elsewhere would be charged to the plaintiff.

After the telephone notice of termination, the Government took bids for the 30,000 pounds of shrimp, and let a contract to the lowest bidder, at a price substantially higher than the plaintiff’s contract price. It demanded from the plaintiff the payment of the difference and, upon the plaintiff’s failure to pay, collected the difference,which was $3,720, from the plaintiff by withholding it from other funds due the plaintiff.

The plaintiff claims that the termination was unjustified, and sues for the $3,720, and for the profits which' it claims to have lost by the termination of the contract.

It is fairly apparent that the plaintiff did not want to perform the contract. It made no move to do so during the first contract period of May 4 to May 31. It gave a false reason for not doing so and has not yet offered a valid reason. During the extended contract period, June 1 to 15, it did not perform, and has offered no reason for not doing so. After June 15, the Government adopted an attitude of for[895]*895bearance, still hoping for performance. That meant that if the plaintiff was diligent, it was entitled to be treated considerately, and not harmed by a harsh and inconsiderate rejection of its performance. It was treated considerately. It told the Government that it looked as if its order could be filled by June 20. On June 21 and 22 it had only one-third of the contract quantity available for inspection, of which a considerable quantity was properly rejected by the inspector. As to the quantity rejected because the shrimp had been beheaded at sea, it is probable that the inspector’s mistake could have been cured by a telephone call to Chicago, and it is impossible to believe that if the plaintiff had wanted .to perform its contract it would not have made that attempt. It was in no position to stand silent on its rights. The other party to the contract was, in this period, exercising forbearance, and the plaintiff should have been exercising diligence.

Because of the need for the shrimp, and the past failure of the plaintiff to perform, the contracting officer’s forbearance was exhausted and he telephoned the plaintiff on June 21 terminating the contract. The plaintiff says that this termination was not put in writing until June 23, and was not affective until then. But it did advise the plaintiff of what was coming and gave it a chance to minimize its loss, if it was threatened with any loss resulting from continued efforts to perform.

Our conclusion is that the plaintiff’s contract was lawfully “terminated, and that it is not entitled to recover. Its petition •will be dismissed.

It is so ordered.

Whitakek, Judge/ Littleton, Judge; and Jones, Chief -,Judge, concur.

FINDINGS OF FACT

The court having considered the evidence, the report of 'Commissioner Paul H. McMurray, and the' briefs and argument of counsel, makes findings of fact as follows:

1. On May 4, 1949, the parties entered into a contract whereby plaintiff agreed to deliver to defendant in San Fran•cisco, California, on May 31, 1949, 30,000 pounds of Type [896]*896III shrimp, in accordance with the Federal Specifications for Shrimp at a price of 68.9 cents per pound, or a total of $20,670.00. • The contract further provided that the shrimp were to be processed under Army Veterinary Corps supervision and that the inspection points were to be the Clegg Shrimp Company, Port Lavaca, Texas, which point the plaintiff selected, and at destination, Quartermaster Market Center, San Francisco, California. The contract was signed on behalf of defendant by a contracting officer at the Quartermaster Center, Chicago, Illinois.

2. Condition 4 of the contract provides:

4. Inspection. — Whether or not an inspection , point is specified herein, all material and workmanship shall be subject to inspection and test at all times and places (including inspection and test after arrival at destination) and, when practicable, during manufacture. In case any articles are found to be defective in material or workmanship, or otherwise not in conformity with the specification requirements, the Government shall have the right to reject such articles, or require their correction. Final inspection shall be conclusive except as regards latent defects, fraud, or such gross mistakes as amount to fraud. In the event public necessity requires the use of materials or supplies not conforming to the specifications, payment therefor shall be made at a proper reduction in price.

3. Condition 13 of the contract provides:

13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
116 F. Supp. 574, 126 Ct. Cl. 892, 1953 U.S. Ct. Cl. LEXIS 136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-fish-oyster-co-v-united-states-cc-1953.