Jones, Chief Judge,

delivered the opinion of the court:

Plaintiff1 sues for breach of his contract of March 1Y,1950, with the Bureau of Reclamation of the Department of the Interior. This contract, No. 12r-18946, provided for construction of the Fort Sumner. Diversion Dam across the Pecos River at a point near Fort Sumner, New Mexico. Plaintiff contends that the termination of his right to proceed with the whole of the contract work, exercised by the Contracting Officer by letter dated January 30, 1951, under Article 9 of the contract, was wrongful because beyond the terms of that provision.

Article 9 provides, in pertinent part, as follows:

If the contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in article 1, or any extension thereof, * * * the G-overnment may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise * * *.

Also of importance here are paragraphs 38 and 3Y of Specifications No. 2906. They establish dates for the release of irrigation water, interim deadlines (March 1, 1951, for the paragraph 38 releases, and April 5, 1951, for the paragraph 3Y releases) occurring before the deadline for completion of the entire construction contract (July 23, [335]*3351951). These critical provisions read, in pertinent part, as follows:

[Paragraph 38]
In addition to other requirements of these specifications for passing natural or required flow of water past the diversion dam, the contractor shall arrange his operations to permit the passage of irrigation releases from Alamogordo Dam to the Carlsbad Pro j ect. The quantity of water passed during each release will be approximately 20,000 acre-feet and the rate of flow during such releases will be between 1,000 and 2,000 cubic feet per second. Not more than one release will be made during any one month and not more than 3 releases will be made during any one irrigation season, March through September, inclusive. The contracting officer will notify the contractor of such releases approximately 7 days in advance of the beginning of such releases. The contractor shall not interrupt or interfere with the natural or required flow of water past the dam for irrigation or other purposes without the approval of the contracting officer * * *.
[Paragraph 31]
The construction to be performed under these specifications will replace portions of the existing canal and structures of the Fort Sumner Canal, and these portions of the construction work will have to be performed at times when water is not flowing in the existing canal. The existing canal will be carrying water from approximately April 5 to October 31, and the contractor will not be permitted to interrupt the flow of the canal during that period. It is required that a continuous flow of 100 cubic feet per second of water be supplied through the existing canal during the irrigation season. The contractor shall make necessary provisions for supplying this quantity of water by whatever method he elects. If at any time immediately prior to or during the irrigation season the contracting officer determines that the contractor’s methods are inadequate to guarantee continued delivery of 100 cubic feet per second in the canal, the Government reserves the right to enter upon the site of the work and to take such minimum action as may be necessary to guarantee the required flow of water.

The events preceding the termination, briefly summarized, are these: This construction contract was awarded March 17, [336]*3361950, on a bid submitted in tbe names of plaintiff and one Nathan A. Moore as joint venturers. (The agreement between plaintiff and Moore provided that plaintiff was to bear full financial responsibility and exercise full authority for the administration of the contract. The association of Mr. Moore’s name with the contract was secured as a result of plaintiff’s concern that because of his own lack of experience in this particular type of heavy construction work, the requisite bonding could not otherwise be obtained.)

Plaintiff received notice to proceed on April 29, 1950. He made good progress from late May, when he began contract work, until September 30, when his discharge of the first of his three successive job superintendents occasioned a shutdown of 3 weeks. During this shutdown, plaintiff received the first of the several communications from the Bureau of Reclamation which he was to receive before the termination, expressing concern (in the light of the irrigation deadlines) over the progress of the job.

The tenure of plaintiff’s second superintendent (from mid-October to late December) saw occasional delays in the receipt of needed materials and equipment parts, which resulted from financing difficulties begun to be experienced by plaintiff. An additional delay of approximately 1 week resulted from defendant’s failure to provide the proper cement, and plaintiff was required to perform substantial extra work beyond the contract specifications; but for neither of these factors did plaintiff request an extension of time.

Plaintiff’s difficulties increased in severity during the month of January, and his shortage of operating capital resulted in delays. This lack of adequate funds was the principal reason for the resignation on J anuary 21, 1951, of the plaintiff’s third job superintendent. With this event, work on the job was shut down while plaintiff sought both a competent superintendent and additional capital with which to resume operations.

The day preceding the termination of J anuary 30,1951, a conference was held between plaintiff and representatives of the Bureau of Reclamation, at which time plaintiff informed the Bureau personnel of the fact that he had succeeded both [337]*337in securing an experienced superintendent and in arranging for a loan of $50,000 to. finance construction. Notwithstanding these assurances, the Bureau representatives (unconvinced that plaintiff would be able to meet the oncoming irrigation deadlines, the first of which was but a month away) insisted that plaintiff relinquish sole control over the project, which plaintiff refused to do. It was this refusal which precipitated the termination by defendant.

Following termination, plaintiff’s surety took over the work and completed the job as a whole on June 19,1951, more than a month before the final deadline. However, work necessary for the first of the irrigation flows — that provided under paragraph 38 and scheduled as possible anytime on or after March 1 — was not completed until March 19.

The resolution of two issues is necessary to a decision of this case:

(1) Was the defendant’s termination of the entire contract authorized by the terms of Article 9, under which it was exercised ?

(2) If the plaintiff may recover for breach of contract because the termination of the entire contract was beyond the authority of Article 9, is he nonetheless precluded from recovery for the termination of his right to proceed on that portion of the contract work necessary to meet the irrigation deadlines described in paragraphs 37 and 38 of Specifications 2906?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson, Inc.
Armed Services Board of Contract Appeals, 2015
Brett Arnold, P.C. v. United States
98 F. App'x 854 (Federal Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
164 Ct. Cl. 332, 1964 WL 8604, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphy-v-united-states-cc-1964.